This document is an Amendment (A00005) to a federal solicitation for the U.S. Indian Health Service's Uintah & Ouray Pavement Project (PH23UO01C6) located at the Fort Duchesne PHS Indian Health Center in Utah. The amendment, issued on 9/12/2025, provides a response to Pre-proposal Inquiry #6 and replaces certain specification sections related to quality requirements, quality control, and testing laboratory services. The proposal due date remains unchanged at September 25, 2025 at 2:00 PM MST.

The amendment modifies the solicitation (75H701-25-R-00051) by updating Attachment J01a Specifications from 382 to 380 pages, specifically revising Sections 014000 (Quality Requirements), 014500 (Quality Control), and 014529 (Testing Laboratory Services). The document outlines detailed requirements for materials testing, quality control procedures, and inspection services to be performed by a testing laboratory retained by the General Contractor, with comprehensive guidelines for earthwork, landscaping, aggregate base, asphalt concrete, and concrete testing across various stages of the construction project.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

A00005

N/A

KELLY J. BRITTON

Project: PH23UO01C6, U&O Pavement

Amendment A00005 to provide the response to Pre-proposal Inquiry #6, replace Attachment J01a Specifications - U-O Pavement to provide revised sections 014000 Quality Requirements, 014500 Quality Control and 014529 Testing Laboratory Services. The proposal due date of September 25, 2025 at 2:00 PM MST remains unchanged.

SEE CONTINUATION PAGES

Indian Health Service Division of Engineering Services (DES) - Seattle 701 5th Ave, Suite 1600 Seattle, WA 98104

See Block 6

75H701-25-R-00051

PH23UO01C6

1 27

09/12/2025

07/28/2025

Amendment of Solicitation Amendment A00005 under Solicitation 75H701-25-R-00051 Project PH23UO01C6, U&O Pavement

SUMMARY OF CHANGES

1. The purpose of Amendment A00005 is to provide the response to Pre-proposal Inquiry #6 and replace Attachment J01a Specifications - U-O Pavement to provide revised sections 014000 Quality Requirements, 014500 Quality Control and 014529 Testing Laboratory Services, as follows:

a. Change the Solicitation 75H701-25-R-00051, SF1442 page 1 from “1 of 56” pages to “1 of 57” pages.

A conformed copy of Solicitation 75H701-25-R-00051 through Amendment A00005 has been posted to SAM.gov.

b. Replace the following Attachment J01a Specification Sections with the attached:

i. SECTION 014000 QUALITY REQUIREMENTS

ii. SECTION 014500 QUALITY CONTROL

iii. SECTION 014529 TESTING LABORATORY SERVICES

c. Replace Attachment J01a - Specifications - U&O Pavement, 382 pages with the attached J01a Specifications - U-O Pavement (Amendment A00005), 380 pages

d. Section J – List of Attachment is revised as follows:

SECTION J – LIST OF ATTACHMENTS

Attachment # and Document Title Date # of Pages

J01a - Specifications - U&O Pavement (Amendment A00005) 9/12/2025 380 J01b - Drawings - U&O Pavement 1/13/2025 15 J01c - Location Maps - Fort Duchesne PHS Indian Health Center N/A 4 J01d - Geotechnical Report – U&O Pavement (Amendment A00002) 8/12/2024 62 J02 - Wage Determination: General Decision Number UT20250103 1/03/2025 6 J03 - Self Performed Calculation Sheet N/A 4 J04 - Form TC-721G - Exemption Certificate for Government & Schools 5/2018 1 J05- Company Specialized Experience Form N/A 2 J06 - Past Performance Questionnaire N/A 5 J07 - Indian Health Service Buy Indian Act Indian Economic Enterprise

Representation Form N/A 1

END OF SUMMARY OF CHANGES

Amendment of Solicitation Amendment A00005 under Solicitation 75H701-25-R-00051 Project PH23UO01C6, U&O Pavement

INDIAN HEALTH SERVICE

DIVISION OF ENGINEERING

SERVICE

PRE-PROPOSAL INQUIRIES

Solicitation 75H701-25-R-00051

PROJECT: U&O Pavement

LOCATION: Fort Duchesne PHS Indian Health Center, Fort Duchesne, UT

PROJECT NO: PH23UO01C6

DOCUMENT

OWNER: Kelly Britton PHONE: 602-245-2206 DOCUMENTS:

DATE: 9/12/2025 DEPARTMENT: IHS/PAO/DFE

Item No.

Reference Drawing, Spec, Page COMMENTS POC IHS Approved Response

Amendment A00005 dated 9/12/2025

6. It appears that the Quality Control requirements for the project per J01a Spec Section 01 40 00 to 01 45 29 are similar to Federal Highway spec requirements. This level of quality control is very costly and seems to be more than what is typically needed for a project of this type and size. Could you confirm that this level of quality control is needed?

Derrick/ Apogee

See attached revised Spec Sections:

• 014000 QUALITY REQUIREMENTS

• 014500 QUALITY CONTROL

• 014529 TESTING LABORATORY SERVICES

Reference the revised Attachment J01a Specifications - U-O Pavement (Amendment A00005).

Fort Duchesne Uintah & Ouray Health Clinic January 14, 2025 Uintah & Ouray Pavement Project 100% for Construction Documents Fort Duchesne, Utah 84026 Project No: PH23UO01C6

01 40 00 - 1

SECTION 01 40 00

QUALITY REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for quality assurance and quality control.

B. Section includes references to material mockups that are described in detail in other sections of the specifications.

C. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve

Contractor of responsibility for compliance with the Contract Document requirements.

1. Specific quality-assurance and control requirements for individual construction activities are specified in the Sections that specify those activities. Requirements in those Sections may also cover production of standard products.

2. Specified tests, inspections, and related actions do not limit

Contractor's other quality assurance and control procedures that facilitate compliance with the Contract Document requirements.

3. Requirements for Contractor to provide quality assurance and control services needed by Architect, Contracting Officer’s Representative

(COR), or authorities having jurisdiction are not limited by provisions of this Section.

4. Specific test and inspection requirements are not specified in this Section.

1.2 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and

Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.3 DEFINITIONS

A. Quality Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.

B. Quality Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that actual products incorporated into the Work and completed construction comply

01 40 00 - 2 with requirements. Services do not include contract enforcement activities performed by Architect.

C. Field Quality-Control Testing: Tests and inspections that are performed on-site for installation of the Work and for completed Work.

D. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency.

E. Installer/Applicator/Erector: Contractor or another entity engaged by

Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.

1.4 DELEGATED DESIGN

A. Performance And Design Criteria: Where professional design services or certifications by a design professional are specifically required of

Contractor by Contract Documents, provide products and systems complying with specific performance and design criteria indicated.

B. Delegated Design Submittals:

1. In addition to Shop Drawings, Product Data, and other required submittals, submit a statement, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional, indicating that the products and systems are in compliance with performance and design criteria indicated. Include a list of codes, loads, and other factors used in performing these services.

2. Reports: Testing agency will prepare and submit certified written reports that include:

a. Date of issue.

b. Project title and number.

c. Name, address, and telephone number of testing agency.

d. Dates and locations of samples and tests or inspections.

e. Names of individuals making tests and inspections.

f. Description of the Work and test and inspection method.

g. Identification of product and Specification Section.

h. Complete test or inspection data.

i. Test and inspection results and an interpretation of test results.

01 40 00 - 3

j. Ambient conditions at time of sample taking and testing and inspecting.

k. Comments or professional opinion on whether tested or inspected

Work complies with the Contract Document requirements.

l. Name and signature of laboratory inspector.

m. Recommendations on retesting and reinspecting.

3. Permits, Licenses, And Certificates: for Contracting Officer’s Representative’s (COR’s) records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work.

1.5 CONFLICTING REQUIREMENTS

A. Referenced Standards: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer conflicting requirements that are different, but apparently equal, to Contracting Officer’s

Representative (COR) for a decision before proceeding.

B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to the Contracting Officer’s Representative (COR) for a decision before proceeding.

1.6 QUALITY ASSURANCE

A. General: Qualifications paragraphs in this article establish the minimum qualification levels required; individual Specification

Sections specify additional requirements.

B. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

01 40 00 - 4

C. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a verifiable record of successful in-service performance, as well as sufficient production capacity to produce required units.

D. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.

E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that are similar in material, design, and extent to those indicated for this Project.

F. Manufacturer's Technical Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to observe and inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.

1.7 QUALITY CONTROL

A. Contractor Responsibilities: Notify testing agencies at least 48 hours in advance of time when Work that requires testing or special inspections will be performed.

B. Contracting Officer’s Representative (COR) Responsibilities:

1. Where quality-control services are indicated as Contracting

Officer’s Representatives’(COR’s) responsibility, Contractor will engage a qualified testing agency to perform these services.

2. Contractor will furnish Contracting Officer’s Representative (COR) with names, addresses, and telephone numbers of testing agencies engaged and a description of types of testing and inspecting they are engaged to perform.

3. Payment for these services will be made by Contractor.

4. Costs for retesting and reinspecting construction that replaces or is necessitated by work that failed to comply with the Contract

Documents will be charged to Contractor.

5. Contractor shall be responsible for coordinating test activities with the Contracting Officer’s Representative (COR).

01 40 00 - 5

C. Retesting/Reinspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and reinspecting, for construction that replaced Work that failed to comply with the Contract Documents.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 REPAIR AND PROTECTION

A. General: On completion of testing, inspecting, sample taking, and similar services, repair damaged construction and restore substrates and finishes.

1. Provide materials and comply with installation requirements specified in other Specification Sections or matching existing substrates and finishes. Restore patched areas and extend restoration into adjoining areas with durable seams that are as invisible as possible.

B. Protect construction exposed by or for quality-control service activities.

C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services.

---END---

01 40 00 - 6

---INTENTIONALLY BLANK----

01 45 00 - 1

SECTION 01 45 00

QUALITY CONTROL

PART 1 - GENERAL

1.1 DESCRIPTION

A. This section specifies requirements for Contractor Quality Control

(CQC) for Design-Bid-Build construction projects.

1.2 APPLICABLE PUBLICATIONS

A. The publication listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

1.3 SUBMITTALS

A. Government approval is required for all submittals. CQC inspection reports shall be submitted under this Specification section and follow the Applicable Specification section naming convention.

1. Preconstruction Submittals

a. Interim CQC Plan

b. CQC Plan

c. Additional Requirements for Design Quality Control (DQC) Plan

2. Design Data

a. Discipline-Specific Checklists

b. Design Quality Control

3. Test Reports

a. Verification Statement

PART 2 - PRODUCTS – NOT USED

3.1 GENERAL REQUIREMENTS

A. Establish and maintain an effective quality control (QC) system that complies with the FAR Clause 52.246.12 titled “Inspection of

Construction”. QC consists of plans, procedures, and organization necessary to produce an end product which complies with the Contract requirements. The QC system covers all design and construction operations, both onsite and offsite, and is keyed to the proposed design and construction sequence. The project superintendent will be held responsible for the quality of work and is subject to removal by the Contracting Officer (CO) or Authorized designee for non-compliance with the quality requirements specified in the Contract. In this context the highest level manager responsible for the overall

01 45 00 - 2 construction activities at the site, including quality and production is the project superintendent. The project superintendent maintains a physical presence at the site at all times and is responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer (CO).

3.2 CQC PLAN

A. Submit the CQC Plan no later than 30 days after receipt of Notice to

Proceed (NTP) proposed to implement the requirements of the FAR Clause

52.246.12 titled “Inspection of Construction”. The Government will consider an Interim CQC Plan for the first 30 days of operation, which must be accepted within 5 business days of NTP. Design and/or construction will be permitted to begin only after acceptance of the

CQC Plan or acceptance of an Interim plan applicable to the particular feature of work to be started. Work outside of the accepted Interim CQC

Plan will not be permitted to begin until acceptance of a CQC Plan or another Interim CQC Plan containing the additional work scope is accepted.

B. Content of the CQC Plan: Include, as a minimum, the following to cover all design and construction operations, both onsite and offsite, including work by subcontractors, designers of record consultants, architects/engineers (A/E), fabricators, suppliers, and purchasing agents:

1. A description of the QC organization, including a chart showing lines of authority and acknowledgement that the CQC staff will implement the three phase control system for all aspects of the work specified. Include a CQC System Manager that reports to the project superintendent.

2. The name, qualifications (in resume format) duties, responsibilities, and authorities of each person assigned a CQC function.

3. A copy of the letter to the CQC System Manager signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the CQC System Manager, including authority to stop work which is not in compliance with the Contract. Letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities will to the

01 45 00 - 3

Contracting Officer (CO) or Authorized designee. be issued by the

CQC System Manager. Furnish copies of these letters

4. Procedures for scheduling, reviewing, certifying, and managing submittals including those of subcontractors, designers of record, consultants, A/E’s offsite fabricators, suppliers and purchasing agents. These procedures must be in accordance with Section 013300

Submittals.

5. Control, verification, and acceptance of testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test. (Laboratory facilities approved by the Contracting Officer (CO) or Authorized designee are required to be used)

6. Procedures for tracking Preparatory, Initial, and Follow-Up control phases and control, verification, and acceptance tests including documentation.

7. Procedures for tracking design and construction deficiencies from identification through acceptable corrective action. Establish verification procedures that identified deficiencies have been corrected.

8. Reporting procedures, including proposed reporting formats.

9. A list of the definable features of work. A definable feature of work is a task which is separate and distinct from other tasks has separate control requirements, and is identified by different trades or disciplines, or it is work by the same trade in a different environment. Although each section of specifications can generally be considered as a definable feature of work, there are frequently more than one definable feature under a particular section. This list will be agreed upon during the Coordination meeting.

C. Acceptance of Plan: Acceptance of the Contractor’s plan is required prior to the start of design and construction. Acceptance is conditional and will be predicated on satisfactory performance during the design and construction. The Government reserves the right to require the Contractor to make changes in the CQC Plan and operations including removal of personnel as necessary, to obtain the quality specified.

01 45 00 - 4

D. Notification of Changes: After acceptance of the CQC Plan, notify the

Contracting Officer (CO) or Authorized designee in writing of any proposed change. Proposed changes are subject to acceptance by the

Government prior to implementation by the Contractor.

3.3 COORDINATION MEETING

A. After the Preconstruction Conference, Post-Award Conference, before start of design or construction, and prior to acceptance by the

Government of the CQC Plan, meet with the Contracting Officer (CO) or

Authorized designee to discuss the Contractor’s quality control system.

Submit the CQC Plan a minimum of 5 business days prior to the

Coordination Meeting. During the meeting, a mutual understanding of the system details must be developed, including the forms for recording the

CC operations, design activities (if applicable), control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor’s Management and control with the Government’s Quality Assurance. Minutes of the meeting will be prepared by the Government, signed by both the Contractor and

Contracting Officer (CO) or Authorized designee and will become a part of the contract file. There can be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings or address deficiencies in the CQC system or procedures which can require corrective action by the Contractor.

3.4 SUBMITTALS AND DELIVERABLES

A. Submittals have to comply with the requirements in Section 013300

Submittals. The CQC organization is responsible for certifying that all submittals and deliverables are in compliance with the contract requirements.

3.5 CONTROL

A. CQC is the means by which the Contractor ensures that the construction, to include that of subcontractors and suppliers, complies with the requirements of the contract.

3.6 TESTS

A. Testing Procedure: Perform specified or required tests to verify that control measures are adequate to provide a product which conforms to contract requirements. Upon request, furnish to the Government duplicate samples of test specimens for possible testing by the

Government. Testing includes operation and acceptance test when

01 45 00 - 5 specified. Procure the services of an Indian Health Services approved testing laboratory or establish an approved testing laboratory at the project site. Perform the following activities and record and provide the following data:

1. Verify that testing procedures comply with contract requirements.

2. Verify that facilities and testing equipment are available and comply with testing standards.

3. Check test instrument calibration data against certified standards.

4. Verify that recording forms and test identification control number system, including all of the test documentation requirements, have been prepared.

5. Record results of all tests taken, both passing and failing on the CQC report for the date taken. Specification paragraph reference, location where tests were taken, and the unique sequential control number identifying the test. If approved by the Contracting Officer

(CO) or Authorized designee, actual test reports are submitted later with a reference to the test number and date taken. Provide an information copy of tests performed by an offsite or commercial test facility directly to the Contracting Officer (CO) or Authorized designee. Failure to submit timely test reports as stated results in nonpayment for related work performed and disapproval of the test facility for this Contract.

B. Testing Laboratories: All testing laboratories must be validated through the procedures contained in Specification section 014529

Testing Laboratory Services.

1. Capability Check: The Government reserves the right to check laboratory equipment in the proposed laboratory for compliance with the standards set forth in the contract specifications and to check the laboratory technician’s testing procedures and techniques.

2. Capability Recheck: If the selected laboratory fails the capability check, the Contractor will be assessed a charge equal to value of recheck to reimburse the Government for each succeeding recheck of the laboratory or the checking of a subsequently selected laboratory. Such costs will be deducted from the Contract amount due the Contractor.

C. Onsite Laboratory: The Government reserves the right to utilize the

Contractor’s control testing laboratory and equipment to make assurance

01 45 00 - 6 tests, and to check the Contractor’s testing procedures, techniques, and test results at no additional cost to the Government.

3.7 COMPLETION INSPECTION

A. Punch-Out Inspection: Conduct an inspection of the work by the CQC system Manager near the end of the work, or any increment of the work established by the specifications. Prepare and include in the CQC documentation a punch list of items which do not conform to the approved drawings and specifications. Include within the list of deficiencies the estimated date by which the deficiencies will be corrected. Make a second inspection the CQC System Manager or staff to ascertain that all deficiencies have been corrected. Once this is accomplished, notify the Government that the facility is ready for the

Government Pre-Final Inspection.

B. Pre-Final Inspection: The Government will perform the Pre-Final Inspection to verify that the facility is complete and ready to be occupied. A Government Pre-Final Punch List may be developed as a result of this inspection. Ensure that all items on this list have been corrected before notifying the Government, so that a Final Acceptance

Inspection with the customer can be scheduled. Correct any items noted on the Pre-Final Inspection in a timely manner. These inspections and any deficiency corrections required by this paragraph need to be accomplished within the time slated for completion of the entire work or any particular increment of the work if the project is divided into increments by separate construction completion dates.

C. Final Acceptance Inspection: The Contractor’s QC Inspection personnel, plus the superintendent or other primary management person, and the

Contracting Officer’s (CO) Authorized designee is required to be in attendance at the Final Acceptance Inspection. Additional Government personnel can also be in attendance. The Final Acceptance Inspection will be formally scheduled by the Contracting Officer’s (CO) or

Authorized designee based upon results of the Pre-Final Inspection.

Notify the Contracting Officer (CO) through the Contracting Officer’s

Representative (COR) office at least 14 days prior to the Final

Acceptance Inspection and include the Contractor’s assurance that all specific items previously identified to the Contractor as being unacceptable, along with all remaining work performed under the contract, will be complete and acceptable by the date schedule for the

01 45 00 - 7

Final Acceptance Inspection. Failure of the Contractor to have all contract work acceptably complete for this inspection will be cause for the Contracting Officer (CO) to bill the Contractor for the

Government’s additional inspection cost in accordance with FAR Clause

52.246-12 titled “Inspection of Construction”.

3.8 DOCUMENTATION

A. Quality Control Activities: Maintain current records providing factual evidence that required QC activities and tests have been performed.

Include in these records the work of subcontractors and suppliers on an acceptable form that includes, as a minimum, the following information:

1. The name and area of responsibility of the Contractor/Subcontractor

2. Operating plant/equipment with hours worked, idle, or down for repair.

3. Work performed each day, giving location, description, and by whom.

When Network Analysis (NAS) is used, identify each phase of work performed each day by NAS activity number.

4. Test and control activities performed with results and references to specification/drawing requirements. Identify the Control Phase

(Preparatory, Initial, and/or Follow-Up). List deficiencies noted, along with corrective action.

5. Quantity of materials received at the site with statement as to acceptability, storage, and reference to specification/drawing requirements.

6. Submittals and deliverables reviewed, with Contract reference, by whom, and action taken.

7. Offsite surveillance activities, including actions taken.

8. Job safety evaluations stating what was checked, results, and instructions or corrective actions.

9. Instructions given/received and conflicts in plans and specifications.

10. Provide documentation of design quality control activities. For independent design reviews, provide, as a minimum, identification of the Independent Technical Reviewer (ITR) team, the ITR review comments, responses, and the record of resolution of the comments.

B. Verification Statement: Indicate a description of trades working on the project; the number of personnel working; weather conditions encountered; and any delays encountered. Cover both conforming and

01 45 00 - 8 deficient features and include a statement that equipment and materials incorporated in the work and workmanship comply with the Contract.

Furnish the original and one copy of these records in report form to the Government daily with 1 week after the date covered by the report, except that reports need not be submitted for days on which no work is performed. As a minimum, prepare and submit a report for every 7 days of no work and on the last day of a no work period. All calendar days need to be accounted for throughout the life of the contract. The first report following a day of no work will be for that day only. Reports need to be signed and dated by the CQC System Manager. Include copies of test reports and copies of reports prepared by all subordinate QC personnel within the CQC System Manager Report.

3.9 NOTIFICATION OF NONCOMPLIANCE

A. The Contracting Officer (CO) or Authorized designee will notify the

Contractor of any detected noncompliance with the foregoing requirements. The Contractor should take immediate corrective action after receipt of such notice. Such notice, when delivered to the

Contractor at the work site will be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer (CO) can issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders will be made the subject of claim for extension of time or for excess costs or damages by the

Contractor.

01 45 29 - 1

SECTION 01 45 29

TESTING LABORATORY SERVICES

PART 1 - GENERAL

1.1 DESCRIPTION:

A. This section specifies materials testing activities and inspection services required during project construction to be provided by a

Testing Laboratory retained by the General Contractor.

1.2 APPLICABLE PUBLICATIONS:

A. The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

American Association of State Highway and Transportation Officials

(AASHTO):

T27-11..................Standard Method of Test for Sieve Analysis of

Fine and Coarse Aggregates

T96-02 (R2006)..........Standard Method of Test for Resistance to

Degradation of Small-Size Coarse Aggregate by

Abrasion and Impact in the Los Angeles Machine

T99-10..................Standard Method of Test for Moisture-Density

Relations of Soils Using a 2.5 Kg (5.5 lb.)

Rammer and a 305 mm (12 in.) Drop

T104-99 (R2007).........Standard Method of Test for Soundness of

Aggregate by Use of Sodium Sulfate or Magnesium

Sulfate

T180-10.................Standard Method of Test for Moisture-Density

Relations of Soils using a 4.54 kg (10 lb.)

Rammer and a 457 mm (18 in.) Drop

T191-02(R2006)..........Standard Method of Test for Density of Soil In-

Place by the Sand-Cone Method

T310-13.................Standard Method of Test for In-place Density and Moisture Content of Soil and Soil-aggregate by Nuclear Methods (Shallow Depth)

B. American Concrete Institute (ACI):

506.4R-94 (R2004).......Guide for the Evaluation of Shotcrete

C. American Society for Testing and Materials (ASTM):

A370-12.................Standard Test Methods and Definitions for

Mechanical Testing of Steel Products

01 45 29 - 2

C31/C31M-10.............Standard Practice for Making and Curing

Concrete Test Specimens in the Field

C33/C33M-11a............Standard Specification for Concrete Aggregates

C39/C39M-12.............Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens

C109/C109M-11b..........Standard Test Method for Compressive Strength of Hydraulic Cement Mortars

C136-06.................Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates

C138/C138M-10b..........Standard Test Method for Density (Unit Weight), Yield, and Air Content (Gravimetric) of

Concrete

C140-12.................Standard Test Methods for Sampling and Testing

Concrete Masonry Units and Related Units

C143/C143M-10a..........Standard Test Method for Slump of Hydraulic

Cement Concrete

C172/C172M-10...........Standard Practice for Sampling Freshly Mixed

Concrete

C173/C173M-10b..........Standard Test Method for Air Content of freshly

Mixed Concrete by the Volumetric Method

C330/C330M-09...........Standard Specification for Lightweight

Aggregates for Structural Concrete

C567/C567M-11...........Standard Test Method for Density Structural

Lightweight Concrete

C780-11.................Standard Test Method for Pre-construction and

Construction Evaluation of Mortars for Plain and Reinforced Unit Masonry

C1019-11................Standard Test Method for Sampling and Testing

Grout

C1064/C1064M-11.........Standard Test Method for Temperature of Freshly

Mixed Portland Cement Concrete

C1077-11c...............Standard Practice for Agencies Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Testing Agency Evaluation

C1314-11a...............Standard Test Method for Compressive Strength of Masonry Prisms

01 45 29 - 3

D422-63(2007)...........Standard Test Method for Particle-Size Analysis of Soils

D698-07e1...............Standard Test Methods for Laboratory Compaction

Characteristics of Soil Using Standard Effort

D1140-00(2006)..........Standard Test Methods for Amount of Material in

Soils Finer than No. 200 Sieve

D1556-07................Standard Test Method for Density and Unit

Weight of Soil in Place by the Sand-Cone Method

D1557-09................Standard Test Methods for Laboratory Compaction

Characteristics of Soil Using Modified Effort

(56,000ft lbf/ft3 (2,700 KNm/m3))

D2166-06................Standard Test Method for Unconfined Compressive

Strength of Cohesive Soil

D2167-08)...............Standard Test Method for Density and Unit

Weight of Soil in Place by the Rubber Balloon

Method

D2216-10................Standard Test Methods for Laboratory

Determination of Water (Moisture) Content of

Soil and Rock by Mass

D2974-07a...............Standard Test Methods for Moisture, Ash, and

Organic Matter of Peat and Other Organic Soils

D3666-11................Standard Specification for Minimum Requirements for Agencies Testing and Inspecting Road and

Paving Materials

D3740-11................Standard Practice for Minimum Requirements for

Agencies Engaged in Testing and/or Inspection of Soil and Rock as used in Engineering Design and Construction

E329-11c................Standard Specification for Agencies Engaged in

Construction Inspection, Testing, or Special

Inspection

E543-09.................Standard Specification for Agencies Performing

Non-Destructive Testing

E709-08.................Standard Guide for Magnetic Particle

Examination

F3125/F3125M-15.........Standard Specification for High Strength

Structural Bolts, Steel and Alloy Steel, Heat

01 45 29 - 4

Treated, 120 ksi (830 MPa) and 150 ksi (1040

MPa) Minimum Tensile Strength, Inch and Metric

Dimensions

D. American Welding Society (AWS):

D1.D1.1M-10.............Structural Welding Code-Steel

1.3 REQUIREMENTS:

A. Accreditation Requirements: Construction materials testing laboratories must be accredited by a laboratory accreditation authority and will be required to submit a copy of the Certificate of Accreditation and Scope of Accreditation. The laboratory’s scope of accreditation must include the appropriate ASTM standards (i.e.; C1077, D3666, D3740, A880, E543) listed in the technical sections of the specifications. Laboratories engaged in Hazardous Materials Testing shall meet the requirements of

OSHA and EPA. The policy applies to the specific laboratory performing the actual testing, not just the “Corporate Office.”

B. Inspection and Testing: Testing laboratory shall inspect materials and workmanship and perform tests described herein and additional tests requested by Contracting Officer’s Representative (COR). When it appears materials furnished, or work performed by Contractor fail to meet construction contract requirements, Testing Laboratory shall direct attention of Contracting Officer’s Representative (COR) to such failure.

C. Written Reports: Testing laboratory shall submit test reports to

Contracting Officer’s Representative (COR), Contractor, unless other arrangements are agreed to in writing by the Contracting Officer’s

Representative (COR). Submit reports of tests that fail to meet construction contract requirements on colored paper.

D. Verbal Reports: Give verbal notification to COR immediately of any irregularity.

PART 2 - PRODUCTS (NOT USED)

3.1 EARTHWORK:

A. General: The Testing Laboratory shall provide qualified personnel, materials, equipment, and transportation as required to perform the services identified/required herein, within the agreed to schedule

01 45 29 - 5 and/or time frame. The work to be performed shall be as identified herein and shall include but not be limited to the following:

1. Observe fill and subgrades during proof-rolling to evaluate suitability of surface material to receive fill or base course.

Provide recommendations to the Contracting Officer’s Representative

(COR) regarding suitability or unsuitability of areas where proof-rolling was observed. Where unsuitable results are observed, witness excavation of unsuitable material and recommend to Contracting

Officer’s Representative (COR) extent of removal and replacement of unsuitable materials and observe proof-rolling of replaced areas until satisfactory results are obtained.

B. Testing Compaction:

1. Determine maximum density and optimum moisture content for each type of fill, backfill and subgrade material used, in compliance with

ASTM D1557 Method A ASTM D698 and/or ASTM D1557.

2. Make field density tests in accordance with the primary testing method following ASTM D6938. Field density tests utilizing ASTM

D1556 shall be utilized on a case by case basis only if there are problems with the validity of the results from the primary method due to specific site field conditions. Should the testing laboratory propose these alternative methods, they should provide satisfactory explanation to the Contracting Officer’s Representative (COR) before the tests are conducted.

a. Pavement Subgrade: One test for each 335 m2 (400 square yards), but in no case fewer than two tests.

b. Curb, Gutter, and Sidewalk: One test for each 90 m (300 feet), but in no case fewer than two tests.

C. Fill and Backfill Material Gradation: One test per 100 cubic yards stockpiled or in-place source material. Gradation of fill and backfill material shall be determined in accordance with ASTM C136.

D. Testing Materials: Test suitability of on-site and off-site borrow as directed by Contracting Officer’s Representative (COR).

3.2 LANDSCAPING:

A. Test topsoil for organic materials, pH, phosphate, potash content, and gradation of particles.

1. Test for organic material by using ASTM D2974.

01 45 29 - 6

2. Determine percent of silt, sand, clay, and foreign materials such as rock, roots, and vegetation.

B. Submit laboratory test report of topsoil to COR.

3.3 ASPHALT CONCRETE PAVING:

A. Aggregate Base Course:

1. Determine maximum density and optimum moisture content for aggregate base material in accordance with ASTM D1557, Method D.

2. Make a minimum of three field density tests on each day's final compaction on each aggregate course in accordance with ASTM D1556.

3. Sample and test aggregate as necessary to ensure compliance with specification requirements for gradation, wear, and soundness as specified in the applicable state highway standards and specifications.

B. Asphalt Concrete:

1. Aggregate: Sample and test aggregates in stockpile and hot-bins as necessary to ensure compliance with specification requirements for gradation (AASHTO T27), wear (AASHTO T96), and soundness (AASHTO

T104).

2. Temperature: Check the temperature of each load of asphalt concrete at mixing plant and at site of paving operation.

3. Density: Make a minimum of two field density tests in accordance with ASTM D1188 of asphalt base and surface course for each day's paving operation.

3.4 SITE WORK CONCRETE:

A. Test site work concrete including materials for concrete as required in

Article CONCRETE of this section.

3.5 CONCRETE:

A. Batch Plant Inspection and Materials Testing:

1. Perform continuous batch plant inspection until concrete quality is established to satisfaction of Contracting Officer’s Representative

(COR) with concurrence of Contracting Officer (CO) and perform periodic inspections thereafter as determined by Contracting

Officer’s Representative (COR).

2. Periodically inspect and test batch proportioning equipment for accuracy and report deficiencies to Contracting Officer’s

Representative (COR).

01 45 29 - 7

3. Sample and test mix ingredients as necessary to ensure compliance with specifications.

4. Sample and test aggregates daily and as necessary for moisture content. Test the dry rodded weight of the coarse aggregate whenever a sieve analysis is made, and when it appears there has been a change in the aggregate.

5. Certify, in duplicate, ingredients and proportions and amounts of ingredients in concrete conform to approved trial mixes. When concrete is batched or mixed off immediate building site, certify

(by signing, initialing or stamping thereon) on delivery slips

(duplicate) that ingredients in truck-load mixes conform to proportions of aggregate weight, cement factor, and water-cement ratio of approved trial mixes.

B. Field Inspection and Materials Testing:

1. Review the delivery tickets of the ready-mix concrete trucks arriving on-site. Notify the Contractor if the concrete cannot be placed within the specified time limits or if the type of concrete delivered is incorrect. Reject any loads that do not comply with the

Specification requirements. Rejected loads are to be removed from the site at the Contractor’s expense. Any rejected concrete that is placed will be subject to removal.

2. Take concrete samples at point of placement in accordance with ASTM

C172. Mold and cure compression test cylinders in accordance with

ASTM C31. Make at least three cylinders for each 40 m3 (50 cubic yards) or less of each concrete type, and at least three cylinders for any one day's pour for each concrete type. After good concrete quality control has been established and maintained as determined by

Contracting Officer’s Representative (COR) make three cylinders for each 80 m3 (100 cubic yards) or less of each concrete type, and at least three cylinders from any one day's pour for each concrete type. Label each cylinder with an identification number. Contracting

Officer’s Representative (COR) may require additional cylinders to be molded and cured under job conditions.

3. Perform slump tests in accordance with ASTM C143. Test the first truck each day, and every time test cylinders are made. Test pumped concrete at the hopper and at the discharge end of the hose at the

01 45 29 - 8 beginning of each day’s pumping operations to determine change in slump.

4. Determine the air content of concrete per ASTM C173. For concrete required to be air-entrained, test the first truck and every 20 m3

(25 cubic yards) thereafter each day. For concrete not required to be air-entrained, test every 80 m3 (100 cubic yards) at random. For pumped concrete, initially test concrete at both the hopper and the discharge end of the hose to determine change in air content.

5. If slump or air content falls outside specified limits, make another test immediately from another portion of same batch.

6. Perform unit weight tests in compliance with ASTM C138 for normal weight concrete and ASTM C567 for lightweight concrete. Test the first truck and each time cylinders are made.

7. Notify laboratory technician at batch plant of mix irregularities and request materials and proportioning check.

8. Verify that specified mixing has been accomplished.

9. Environmental Conditions: Determine the temperature per ASTM C1064 for each truckload of concrete during hot weather and cold weather concreting operations:

a. When ambient air temperature falls below 4.4 degrees C (40 degrees F), record maximum and minimum air temperatures in each

24 hour period; record air temperature inside protective enclosure; record minimum temperature of surface of hardened concrete.

b. When ambient air temperature rises above 29.4 degrees C (85 degrees F), record maximum and minimum air temperature in each 24 hour period; record minimum relative humidity; record maximum wind velocity; record maximum temperature of surface of hardened concrete.

10. Inspect the reinforcing steel placement, including bar size, bar spacing, top and bottom concrete cover, proper tie into the chairs, and grade of steel prior to concrete placement. Submit detailed report of observations.

11. Observe conveying, placement, and consolidation of concrete for conformance to specifications.

12. Observe condition of formed surfaces upon removal of formwork prior to repair of surface defects and observe repair of surface defects.

01 45 29 - 9

13. Observe curing procedures for conformance with specifications, record dates of concrete placement, start of preliminary curing, start of final curing, end of curing period.

14. Observe preparations for placement of concrete:

a. Inspect handling, conveying, and placing equipment, inspect vibrating and compaction equipment.

b. Inspect preparation of construction, expansion, and isolation joints.

15. Observe preparations for protection from hot weather, cold weather, sun, and rain, and preparations for curing.

16. Observe concrete mixing:

a. Monitor and record amount of water added at project site.

b. Observe minimum and maximum mixing times.

C. Laboratory Tests of Field Samples:

1. Test compression test cylinders for strength in accordance with ASTM

C39. For each test series, test one cylinder in 7 days and one cylinder in 28 days. Use remaining cylinder as a spare tested as directed by Contracting Officer’s Representative (COR). Compile laboratory test reports as follows: Compressive strength test shall be result of one cylinder, except when one cylinder shows evidence of improper sampling, molding or testing, in which case it shall be discarded and strength of spare cylinder shall be used.

2. Make weight tests of hardened lightweight structural concrete in accordance with ASTM C567.

3. Furnish certified compression test reports (duplicate) to

Contracting Officer’s Representative (COR). In test report, indicate the following information:

a. Cylinder identification number and date cast.

b. Specific location at which test samples were taken.

c. Type of concrete, slump, and percent air.

d. Compressive strength of concrete in MPa (psi).

e. Weight of lightweight structural concrete in kg/m3 (pounds per cubic feet).

f. Weather conditions during placing.

g. Temperature of concrete in each test cylinder when test cylinder was molded.

h. Maximum and minimum ambient temperature during placing.

01 45 29 - 10

i. Ambient temperature when concrete sample in test cylinder was taken.

j. Date delivered to laboratory and date tested.

3.6 TYPE OF TEST:

Approximate Number of Tests Required

A. Earthwork:

Laboratory Compaction Test, Soils:

(ASTM D1557) _____

B. Landscaping:

Topsoil Test _____

C. Aggregate Base:

Laboratory Compaction, (ASTM D1557) _____

Field Density,(ASTM D1556) _____

D. Asphalt Concrete:

Field Density, (ASTM D1188) _____

E. Concrete:

Making and Curing Concrete Test Cylinders (ASTM C31) _____

Compressive Strength, Test Cylinders…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .