This document includes an amendment to a solicitation for roof replacement services at a hospital in Crow Agency, Montana. The Indian Health Service is seeking proposals to replace the existing PVC roof on the hospital and support building, with the work to be completed within 60 calendar days of award. Proposals are due by June 29, 2020 and the estimated contract award date is July 23, 2020. The opportunity is set aside exclusively for small businesses. Insurance requirements and Davis Bacon wage determinations apply. The amendment provides responses to contractor questions, revised drawings, and documents related to tribal employment rights for the project.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

PAGE

OF

PAGES

Indian Health Service - DES 701 Fifth Avenue, Suite 1600 MS/24 Seattle, WA 98104

SEE BLOCK 6

8. NAME AND ADDRESS OF CONTRACTOR

(Number, street, county, State and ZIP Code) (X)

9A. AMENDMENT OF SOLICITATION NUMBER

75H701-20-R-00038

9B. DATED

(SEE ITEM

11) 05/28/2020

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

(SEE ITEM 13)

CODE

FACILITY CODE

2. AMENDMENT/MODIFICATION NUMBER
3. EFFECTIVE DATE
4. REQUISITION/PURCHASE REQUISITION NUMBER
5. PROJECT NUMBER (If applicable)
Amendment 00002
06/23/2020
TBD

6. ISSUED BY CODE

7. ADMINISTERED BY (If other than Item 6)
CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended.

is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

1. The purpose of Amendment 00002 is to incorporate the following into the solicitation:

a. Site Visit Agenda and Sign-in Sheet from the Site Visit held on June 10, 2020, 2 pages

b. IHS responses to Pre-Proposal Inquiries, 2 pages

c. FAR provision 52.228-1, Bid Guarantee (Sept 1996), 1 page

d. Parapet Detail and A4 Plans, 2 pages; Materials Schedule, 1 page; and A3 Plan Details, 1 page

e. Attached TERO documents concerning TERO within the Crow Nation, 38 pages,

2. The proposal due date remains unchanged. See continuation pages.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Andrew E. Hart, Contracting Officer

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED
16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

SITE VISIT

RFP-75H701-20-R-00038

Crow Roof Replacement Project Crow/Northern Cheyenne Hospital 10110 South, 7650 East, Crow Agency, MT 59022 Wednesday, June 10, 2020, 10:00 AM local time Agenda Welcome and Introduction of Government Team

· Contract Specialist: Rita Langager

· Contracting Officer’s Representative: Todd Rydquist, P.E. (Facility Manager: Marlin “Deano” Yarlott)

· Purpose of site visit is a walkthrough of the jobsite and Q&A. Scope clarifications shall be put in writing from the prime contractor.

· Contractor questions shall be submitted via email to Rita Langager AND Todd Rydquist

· Amendment(s) will be issued with copies of all solicitation Request for Information (RFI) / questions & answers Solicitation Information

· Purpose of the Project:

The purpose of this project is to replace the existing PVC roof on the Hospital and Support building. The existing roof membrane was installed when the facility was constructed in 1995 so it is 28 years old. The roof is beyond its reasonable design life and has required numerous patches to maintain integrity. Further degeneration of the roof and water leaks will prevent the facility from meeting the Joint Commission Environment of Care Standards, EC 02.06.01.

· POP– 60 calendar days from NTP

· This solicitation is 100% Set-Aside for Small Business (SB) contract firms

· Insurance Requirements in accordance with H-6 and I-1. Required Insurance Coverage

· Davis-Bacon Wage Determinations apply & may update before award

· Bid, Payment and Performance Bonds required (using proper forms, SF-24, SF-25, SF-25a)

· Refer to “L.11. PROPOSAL SUBMISSION DOCUMENTATION” regarding proposal document requirements

· Proposal shall include itemized price breakdown

· Bid bond IS required with proposal Solicitation Timeline

Milestone/Activity
Date/Time
Solicitation Issued
5/28/2020
Site Visit
6/10/2020 @ 10:00 AM (local time)
RFI cut-off date (10 calendar days prior to the solicitation closing)
6/15/2020 @ 12:00 PM (local time)
Proposal Due Date
6/29/2020 @ 2:00 PM (local time)
Estimated Contract Award Date
07/23/2020

Amendment of Solicitation Amendment 00002 under Solicitation 75H701-20-R-00038 Project BI18CR203H6, Title Roof Replacement Project for Crow Service Unit

INDIAN HEALTH SERVICE

DIVISION OF ENGINEERING SERVICE

PRE-PROPOSAL INQUIRIES

Solicitation 75H701-20-R-00038

PROJECT:
Crow Roof Replacement
LOCATION:
Crow/Northern Cheyenne Hospital

10110 South 7650 East Crow Agency, MT 59022

PROJECT NO:
BI18CR203H6
DOCUMENT OWNER:
Rita Langager
PHONE:
(406) 247-7099
DOCUMENTS:
DATE:
06/17/2020
DEPARTMENT:
IHS/BAO/DFM
Item No.
Reference

Drawing, Spec, Page

COMMENTS
POC
IHS Approved Response

Amendment 00002 dated 06/17/2020

1.
T2, Item 9

A2, Item 1

Specifications and drawings do not specify the new lightning protection system is to be certified by an accredited 3rd party inspector such as Underwriters Laboratories or equal. Drawing page T2 item 9 and A2 Item 1 in general notes states: All work shall conform to the most current version of IBC, NFPA, IHS criteria and applicable Local, State, and Federal codes. Nowhere that I can locate does it state to certify the system to be sure it functions and is brought up to compliance with current codes.
TR
The lightning protection system is to be installed as shown in drawings, which reflects the initial installation. Certification of the system will not be required as it has not been certified for over 20 years. Bring the lightning protection system into compliance with current codes may be considered under a separate project in the future.
2.
Detail 3/A3
Drawing 3/A3 shows PVC turning up the wall and is terminated using a termination bar fastened into the wall with sealant at the top. This is the same detail which is in place now and has failed. If the same detail is used, the same result will follow. The sealant is being applied to porous brick which can allow water intrusion, that together with the expansion and contraction of the sealant becomes a detail that is a maintenance item.
TR
Details 3/A3 and 1/A4 have been updated to include a saw cut-in at the mortar line of the brick and installation of reglet counterflashing over proposed termination bar.
3.
General
Does the Government have an as-built drawing shown what type of coverboard is in place now? The existing coverboard should be compatible with PVC, but if the coverboard has an asphaltic surface or coating, it will have an adverse effect on the new PVC.
TR
Details from the existing as-built drawings are attached to this amendment. The as-built drawing does not show the material used for coverboard, however, asphaltic coverboard is generally not used for rubber and vinyl membrane roofs.
4.
075417, 2.3
Specification 075419 – POLYVINYLE-CHLORIDE (PVC) ROOFING, 2.3 PVC Roofing A1 states: Thickness: 60 mils minimum. Without confirmation, contractors will bid project using a PVC 60 mil. PVC membranes are manufactured in accordance with ASTM 4434 Standard Specification for Polyvinyl chloride sheet roofing. ASTM D4434 is the optical method average and is not a minimuym
TR
The intention is that the smallest nominal membrane size to be used is a PVC 60 mil membrane.
5.
General
Would we be able to give NTP at the beginning of September
TR
Upon request of the successful bidder, the NTP may be scheduled for the first week of September.
6.
General
A request was made to consider a Versiflex PVC roofing system as an approved substitution for specified materials.
TR
Versico Roofing Systems Veriflex (PVC) membrane, 60 mil white, is an acceptable product.
7.
General
Is existing insulation to remain?
TR
Existing insulation that is in good condition is expected to remain. Insulation which is obviously damaged is to be replaced. An allowance for replacement of up to 10% of existing insulation and substrate by area is in the bid schedule.
8.
075419
Specification section 2.5 substrate board calls for 5/8” type X, but Section 2.8/D roof insulation board calls for ½” cellulosic fiberboard. Please clarify thickness and type of cover board to use.

Section 2.8 refers to substrate board between the metal deck and roof insulation. Section 2.5 refers to the cover board beneath the roof membrane.

9.
Line item 3
Line item #3 requires removal of membrane and any wet underlaying layers of insulation and cover board which includes a tapered insulation system. Tapered insulation systems involve a long lead time for material (two to three weeks). An unknown amount of an unknown dimension (taper) and only be determined upon demolition and inspection of the damaged tapered insulation. This would require us leaving the roof open for an extended period of time to obtain the proper amount of insulation.
TR
The bid sheet includes an allowance for replacement of up to 10% of insulation and substrate. Section 075419, Article 3.4 specifies temporary protection to be provided when work is halted indefinitely. Bidders should take into account temporary protection of up to 10% of the roof in their bid for an extended period of time. The successful bidder is free to perform core testing upon contract award to help determine the existence of damaged insulation, however, this will be at the contractor’s cost.
10.
SF-1442, 13.b.

FAR 52.228-1

I didn't see any information regarding bid bonds (offer guarantees) in the solicitation other than the fact they are required. I had a couple of questions about bonding: What is the amount of bonding we will need? And are there Liquidated Damages?

RL
FAR 52.228-1 is incorporated in full text. The bid guarantee amount shall be at least 20 percent of the bid price.

52.228-1 Bid Guarantee (Sept 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds-

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of clause)

3. All other terms and conditions of this solicitation shall remain unchanged.

image2.png oleObject1.bin image3.jpeg image4.jpeg image1.jpeg