751/23180. ABG; Mackinac Island East Bluff Retaining Wall
Solicitation number
RFQ 171 250000000373 5
Issued by
Luce County, Mcbride Village, Michigan

About this file

This is Addendum No. 1 issued on May 15, 2025, for the Mackinac Island East Bluff Retaining Wall Replacement project, a state and local contract opportunity involving MI DTMB (Department of Technology, Management and Budget) and Mackinac Island State Park. The project involves the replacement of a retaining wall on Mackinac Island's east bluff. The bid date remains Wednesday, May 21, 2025, as unchanged by this addendum. Key project logistics include waived permit fees from Mackinac Island State Park and dock fees, though City of Mackinac Island permits are required for street use. Materials may be staged in the State Park service yard on Huron Road beginning after Labor Day, with transportation limited to prior to 10 a.m. until October 26, 2025. No vehicle movement is permitted on October 25, 2025, due to a running race, and work at the project site shall not commence until November 3, 2025. The contractor is responsible for removing all excavated earthwork, demolished materials, and excess materials from the island. A pre-bid meeting was held, with the attendance sheet attached to this addendum.

The addendum introduces a new unit price item for Earth Excavation (Item E) to be added to Section 312000, measured in cubic yards and applied only when unsuitable materials are discovered or other unforeseen conditions require excavation beyond the planned depth. The contract is structured as a lump sum project with unit prices for contingent work, including rock excavation, modular blocks (R-41, R-60, FS-T), backfill, and earth excavation. Anticipated quantities are provided for reference only; final rock excavation quantities that vary from plans will be adjusted at the unit price, while variations in other items will not be added or subtracted from the contract if the wall is installed as planned. Additional earth excavation will be compensated only if the Geotechnical Engineer determines the planned excavation bottom contains unsuitable soils requiring removal. Measurement of earth excavation quantities may be performed using cross-sections rather than surveying, with stored spoils kept separate to support verification.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM NO. 1

DATE: Thursday, May 15, 2025

PROJECT: Mackinac Island East Bluff Retaining Wall Replacement

DTMB FILE NO.: 751/23180.ABG

OWNER: MI DTMB / Mackinac Island State Park

BID DATE: Wednesday, MAY 21, 2025 ** THIS ADDENDUM DOES NOT CHANGE THE

BID DATE

The following shall be incorporated into the Contract Documents dated 23 APRIL 2025.

GENERAL

1. The pre-bid meeting attendance sheet is attached.

2. Mackinac Island State Park permit fees will be waived for this project.

3. Dock fees will be waived for this project.

4. City of Mackinac Island permits are required for using any of the city streets.

5. British Landing can be used for hauling materials to the Island.

6. Contractor will be allowed to begin staging materials in the State Park service yard on Huron

Road after Labor Day. Transportation of the materials shall be limited to being performed prior to 10 am until October 26, 2025, after which the time restrictions are removed.

7. No vehicle movement shall occur on October 25, 2025, due to a running race in the State Park that day.

8. The Mackinac Island road weight restrictions are attached.

9. Work at the project site on the roadway, fence, and retaining wall shall not begin until November

3, 2025.

10. All removed earthwork, demolished materials, and excess materials are the responsibility of the contractor and shall be removed from the island.

11. E-bikes need to be Class I and properly licensed through the City of Mackinac Island.

PROJECT MANUAL

See attached revised page from the Bid Summary for an updated Schedule of Unit Prices. A unit price has been added for Earth Excavation.

Section 312000 EARTH MOVING:

Add item E to Section 1.3 UNIT PRICES as follows:

E. Excavation, Earth Measurement: Volume of existing soils excavated and disposed of, in cubic yards, due to needing a deeper retaining wall, finding unsuitable materials, or other unforeseen conditions, as approved by the owner and architect. If the retaining wall is installed per the plans with no major changes or unknowns encountered, and the quantity of excavation, earth varies slightly from the anticipated quantity included for reference (either more or less), a change order will not be issued.

1. This item will be measured by the contractor and subject to verification by the Owner and Engineer. If surveying is not used to capture the quantity, we expect it will be "measured" by using simple cross sections similar to sections 1 and 2 on S-500, multiplied by the distance over which they extend. It is recommended that the additional removed spoils are stored in a pile separate from the base bid spoils to support the calculations and allow verification.

End of Addendum No. 1

Bidding and Contract Document (R 03/25) Mackinac Island East Bluff Retaining Wall Replacement File No. 751/23180.ABG

Schedule of Alternates - The Bidder will complete (or deduct from the Contract) the parts of the Work designated by the Alternates that follow and accept in full payment (or allow in full credit) for those parts of the Work the following Item Bid Prices:

Alternate Item No.

Bid Quantity

Description Unit Price

Item Bid Price

The Bidder further acknowledges and agrees that the separate prices bid on this “Schedule of Alternates,” where they are applicable and deemed acceptable by the Owner, will be used if incorporated into the Contract when the Owner issues the Notice of Award.

Schedule of Unit Prices or Contingent Change Order Prices - The Bidder shall use this “Schedule” to quote unit prices identified in the bid documents or propose other contingent Change Order prices. The proposed Unit Prices or contingent Change Order prices set forth in this schedule, at the sole discretion of the Owner, may, or may not be incorporated into the Contract Documents. The Owner reserves the right to negotiate Unit Prices or contingent Change Order prices set forth herein prior to their possible incorporation into the Contract Documents.

Item No. Bid Quantity

Description Unit Price

1 Per CYD Excavation, Rock 2 Per Each Modular Block, R-41 3 Per Each Modular Block, R-60 4 Per Each Modular Block, FS-T 5 Per CYD Backfill, Structure, CIP 6 Per CYD Excavation, Earth

Refer to the plans for anticipated quantities. They are included to assist you in developing unit prices and a total lump sum bid, but remain for reference only. Final measured rock excavation quantity that varies from the anticipated quantity on the plans will be added or subtracted from the contract at the unit price. For the other unit prices, if the retaining wall is installed to the size shown on the plans, since it is a lump sum project, slight variations in the quantities for those items will not be added to or subtracted from the contract. Additional “Excavation, Earth” will only be paid for if the planned bottom of excavation as it is currently shown on the plans is determined to have unsuitable soils and the Geotechnical Engineer requires them to be removed to create a suitable bearing surface.

See sections 31 20 00 Earth Moving and 32 32 23 Segmental Retaining Walls for further details on measurement requirements of each unit priced item.