This is a Construction Bid Addendum No. 1 issued by the Department of Technology, Management and Budget (DTMB), State Facilities Administration Design and Construction Division, in partnership with the Department of Natural Resources Facilities and Recreation Division (DNR_FRD) for the Gaylord Repair Shop Lighting Replacement project (File Number 751-19363AGY). The addendum, issued on July 12, 2019, clarifies and expands the scope of work to include removal and replacement of exterior wall packs with LED equivalents (10 fixtures with dusk-to-dawn capability), office and stock/parts area fixtures (18 2x4 LED flat panel 5000K fixtures and approximately 41 4-foot LED 5000K strip lights), and shop area high bay lighting (28 LED 5000K fixtures). The addendum also adds installation of two 56-inch industrial black ceiling fans with variable speed controls and emergency egress lighting components (5 emergency egress light packs, 4 EXIT-only signs with battery backup, and 2 EXIT and egress light combination units). The bid opening date was scheduled for July 24, 2019.
No pricing terms, set asides, incumbent information, funding sources, or other financial details are specified in this addendum document. All bidders must acknowledge receipt and understanding of this addendum in their bid submission, as failure to do so may result in bid rejection. The addendum becomes part of the contract documents and was approved by Project Director Sharon Conley of DNR_FRD.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 751-19363AGY Work Scope.docx | DOCX document | |
| 751-19363AGY GRS lighting 50K Spec (Rev02-19).docx | DOCX document | |
| 751-19363AGY GRS lights-0415 (Advertisment)(R04-19).doc | DOC document | |
| 751-19363AGY ADD#2 20190723.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTMB-0414 (Rev 12/17)
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
State Facilities Administration Design and Construction Division
CONSTRUCTION BID ADDENDUM NO. 1
This form identifies an Addendum to Bidding Documents, and incorporates interpretations or clarifications, modifications, acceptance of proposed “or equal” materials, and other information into the Bidding Documents. Addenda will be numbered by the Professional and distributed through www.michigan.gov/SIGMAVSS as an attachment.
| TO: |
| ALL BIDDERS |
| DATE ISSUED |
7/12/2019
PROJECT NAME
Gaylord Repair Shop – Lighting Replacement
FILE NUMBER
751-19363AGY
PROFESSIONAL
DNR_FRD Sharon Conley
PROJECT DIRECTOR
DNR_FRD Sharon Conley
BID OPENING DATE:
7/24/2019
ADDENDUM ITEMS: (attach additional sheets and drawings if required)
This addendum is being issued to clarify the number of light fixtures, the light spectrum and add emergency exit and egress lighting replacement.
EXTERIOR Remove and replace 10 existing exterior wall packs with new LED equivalent. All light packs to be dusk to dawn. There are six large pack lights above overhead shop bay doors and four smaller light packs over service doors.
OFFICE / STOCK/PARTS Areas Remove all existing fixtures and replace 18- 2x4 fixtures with new LED flat panel 5000k lights Remove all existing fixtures and replace approximately 41 4’ strip lights with LED 5000K equivalent
SHOP AREA
Remove all high bay fixtures and replace 28 high bay lights with LED 5000K equivalent. Place in existing locations to provide best lighting for shop areas.
Furnish and install 2 – 56” industrial, black, 3 blade ceiling fans with variable speed controls. Reuse control locations ADD: remove and replace of: 5 emergency egress light packs, 4 EXIT only signs with battery back up, 2 EXIT & egress light combo
ACKNOWLEDGEMENT: This Addendum must be acknowledged by the Bidder in the space provided in the Bid Summary and Bid Form. Failing to acknowledge Addenda may be cause for the Bid to be rejected. Addenda will become part of the Contract Documents.
PROFESSIONAL: DNR_FRD Sharon Conley
DATE: 7/12/2019
APPROVED BY:
PROJECT DIRECTOR: DNR_FRD Sharon Conley
DATE: 7/12/2019
image1.jpeg
File details come from the government source that posted it. Updated .