ILLUSTRATIVE BUDGET FORM
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_05_.pdf | ||
| 72065618R00023_Amendment_04.pdf | ||
| Amendment_03.pdf | ||
| Amendment_02.pdf | ||
| Amendment_01.pdf | ||
| AID1420-17_Employee_Biodata_Sheet.pdf | ||
| Sol_72065618R00023__DESIGN-BUILD_OF_THREE_HEALTH_HIV_LABS_IN_TETE,_MANICA_AND_SOFALA.pdf | ||
| Past_Performance_Form.docx | DOCX document | |
| Attachment_1_Forms_-_Tables_1-3.rtf | RTF text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Summary
| Summary Prices | ||||
| CLIN | Site Identification | Lot/Province | Description | Price in USD |
| 1 | S1 | Tete | Tete Lab, Tete | |
| 2 | S2 | Manica | Chimoio Lab, Chimoio | |
| 3 | S3 | Sofala | Ponta Gea Lab, Beira | |
| TOTAL | $0.00 |
Tete Lab
| S1 | TETE LAB Illustrative activities (CLIN 01) | |
| Nr | Activities | Price |
| 1 | Design proposal and recommendation | |
| 2 | Construction | |
| 2.1 | Preliminaries (camping, temporary works including water, sanitation and electricity) | |
| 2.2 | Removal of existing tiles and installation of epoxy or tiles or any other suitable material approved in the proposed design; | |
| 2.3 | Acquisition and Installation of approved ceiling including wooden ceiling framing and new PVC or similar type ceiling | |
| 2.4 | Acquisition and installation of ACs suitable for the existing rooms as applicable | |
| 2.5 | Execution of internal partitions | |
| 2.6 | Acquisition and Installation of approved doors (removing or adding) | |
| 2.7 | Acquisition and Installation of approved windows (removing or adding) | |
| 2.8 | Acquisition and Installation of electric system | |
| 2.9 | Acquisition and Installation of standby generator (60 Kva) | |
| 2.10 | Installation of new water supply systems including plumbing | |
| 2.11 | Repairs of the sewage systems | |
| 2.12 | Execution of the connection of the lab to other buildings | |
| 2.13 | Testing of electrical and water systems | |
| 2.14 | Handover of facility and respective systems | |
| Total price for Tete Lab |
Manica Lab
| S2 | MANICA LAB Illustrative activities (CLIN 02) | |
| Nr | Activities | Price in USD |
| 1 | Design proposal and recommendation | |
| 2 | Construction | |
| 2.1 | Preliminaries (camping, temporary works including water, sanitation and electricity, Municipal approval) | |
| 2.2 | Removal and properly store all internal partitions and fixtures including electrical fixtures, water supply and any other fixtures | |
| 2.3 | Removal and dispose the floor finishing materials and magnesium board; | |
| 2.4 | Supply and Installation of additional steel frame beams | |
| 2.5 | Supply and install profile sheeting, shear studs and rebar as appropriate. | |
| 2.6 | Installation of removed plumbing, cables including supply of materials | |
| 2.7 | Construction of the reinforced slab C-25 concrete with a minimum thickness of 10cm | |
| 2.8 | Supply and install epoxy or other finishes appropriate for the industry | |
| 2.9 | Painting to protect the existing walls from damages, concrete stains or scratches | |
| 2.10 | Reinstall all the internal partitions, electric fixtures, water supply lines and other forms of installation removed with the partitions | |
| 2.11 | Testing of electrical and water systems | |
| 2.12 | Handover of facility and respective systems | |
| Total price for Manica Lab |
Sofala Lab
| S3 | SOFALA LAB Illustrative activities (CLIN 03) | |
| Nr. | Activities | Price in USD |
| 1 | Design proposal and recommendation | |
| 2 | Construction | |
| 2.1 | Preliminaries (camping, temporary works including water, sanitation and electricity, Municipal approval) | |
| 2.2 | Demolitions of Roof Cover, Wooden Truss and Purlins, Wooden Ceiling, Interior Walls, Doors and Windows, Floor Tile, and the Top Layer of the Floor Concrete | |
| 2.3 | Construction of new Concrete Layer for the Floor to Receive Epoxy Finish | |
| 2.4 | Epoxy Finish | |
| 2.5 | Acquisition and Installation of Doors | |
| 2.6 | Acquisition and Installation of Windows | |
| 2.7 | Construction of Steel Truss and Purlin | |
| 2.8 | Construction of Roof Cover | |
| 2.9 | Construction of Partition Walls | |
| 2.10 | Construction of Ceiling | |
| 2.11 | Execution of Plaster and Paint of the Perimeter Walls | |
| 2.12 | Installation of Electrical Systems | |
| 2.13 | Acquisition and Installation of Backup Generator | |
| 2.14 | Acquisition and Installation of Water System Including Water Tank | |
| 2.15 | Acquisition and Installation of Sewer System Including Septic Tank, and | |
| 2.16 | Acquisition and Installation of Air Conditioning System | |
| 2.17 | Testing of electrical and water systems | |
| 2.18 | Handover of facility and respective systems | |
| Total price for Sofala Lab |