This document contains an Environmental Mitigation and Monitoring Plan (EMMP) template for USAID-funded activities and a solicitation for USAID/Zambia's Enterprise Development and Growth Enhanced activity.

The EMMP template provides guidance on developing site-specific plans to implement mitigation measures from Initial Environmental Examinations, monitor their effectiveness, and report annually. It outlines required components of EMMPs including mitigation actions, monitoring indicators, frequencies, responsibilities, and a table to list these by activity. The solicitation seeks proposals for technical services to increase agricultural SME profitability in Zambia by addressing finance, skills, technology, and market access constraints. USAID will award a cost-plus-fixed-fee completion contract for up to $16 million over five years to provide these services under a NAICS code of 541990. Proposals are due by the specified response date.

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

[ Use appropriate branding and marking including USAID logo]

[ACTIVITY TITLE]

ENVIRONMENTAL MITIGATION AND MONITORING PLAN (EMMP)

Approved Date: [e.g. January 1, 2018] Version: [1]

[Contract/Agreement] Number: [Insert number] Activity Start Date and End Date: [e.g. January 1, 2014 to December 31, 2017] Total Award Amount: [$xxx] [COR/AOR] Name: [Insert names]

Submitted by:[Insert name & position]
[Insert office name]
Tel: [Insert land and cell phone numbers]
Email: [Insert email address]

July 2008 1

PURPOSE

Environmental Mitigation and Monitoring Plans (EMMPs) are required for USAID-funded projects, as specified in ADS 204, when the 22 CFR 216 documentation governing the project (e.g. the Initial Environmental Examination (IEE)) specifies mitigation measures are needed. EMMPs are in important tool for translating applicable IEE conditions and mitigation measures into specific, implementable, and verifiable actions.

An EMMP should clearly defines:

1. Mitigation measures. Actions that reduce or eliminate potential negative environmental impacts resulting directly or indirectly from a particular project or activity, including environmental limiting factors that constrain development.

2. Monitoring indicators.[footnoteRef:2] Criteria that demonstrate whether mitigation measures are suitable and implemented effectively. [2: Note: Monitoring indicators differ from performance indicators, which are the measures that USAID uses to detect progress towards the results included in a Results Framework.]

3. Monitoring/reporting frequency. Timeframes for appropriately monitoring the effectiveness of each specific action.

4. Responsible parties. Appropriate, knowledgeable positions assigned to each specific action.

5. Field Monitoring/Issues. Field monitoring needs to be adequately addressed i.e. monitoring dates, observations, issues identified and resolution. This field is primarily for documentation during implementation.

An EMMP is a living document. It should be reviewed against the IEE and updated/tailored as needed over the life of implementation, e.g. when new sites are identified or changes in scope are made through award modifications and IEE Amendments.

· 1.0 PROJECT/ACTIVITY SUMMARY

· 2.0 SITE SPECIFIC INFORMATION

· 3.0 ANNUAL REPORTING

Annually, the Implementing Partner will prepare an Environmental Mitigation and Monitoring Report (EMMR) to be submitted to the Activity Manager/AOR/COR and the USAID Environmental Compliance Database. This report will summarize the effectiveness of mitigation measures, issues encountered, resolutions, and lessons learned. As appropriate, attachments such as site photos, verification of local inspections, product warranties, etc should also be included.

· 4.0 EMMP TABLE FOR [PROVIDE NAME OF ACTIVITY]

Project/Activity/Sub-Activity
Identified Environmental Aspects or Impacts
Mitigation Measure(s)
Monitoring Indicator(s)
Monitoring and Reporting Frequency
Responsible Parties
Field Monitoring/Issues/Resolution

Field monitoring needs to be adequately addressed i.e. monitoring dates, observations, issues identified and resolution

Activity 1:

Activity 2:

Activity 3:

Activity 4:

Activity 5:

Activity 6:

Add rows as needed

BUREAU/MISSION/PROJECT