SOW Inspect and Repair Main Switchgear at CGA.pdf
PDF 1 MB Posted
- Attached to
- Inspect and Repair of 13.2KV Main Switchgear
- Solicitation number
- 70ZH1526QCGA00009
- Issued by
- Not on record
About this file
This document is a Specifications file for a federal contract issued by the United States Coast Guard for maintenance and repair services at the U.S. Coast Guard Academy in New London, Connecticut.
The Coast Guard Academy requires inspection, fuse replacement, component repair, and testing of an existing Eaton/Cutler-Hammer MVS2 Medium Voltage Switchgear system operating at 13.2 kV. The primary focus is Cabinet 5 maintenance, which involves thorough inspection of all components, safe removal and replacement of three existing fuses with new Eaton 15CLE-250E fuses (15.5 kV, 3-inch Single Barrel), and insulation resistance (Megger) testing on a 15 kV feeder cable running from the switchgear to Smith Hall in accordance with ANSI/NETA ATS/MTS standards. The contractor must safely re-energize Cabinet 5 and the associated feeder line upon completion and procure three additional Eaton 15CLE-250E fuses as on-site spares. The project addresses previously cannibalized parts requiring a certified electrical contractor to assess, procure, and install replacement OEM components to restore full operational capability.
The contractor must comply with NFPA 70E electrical safety standards and OSHA regulations, provide Arc Flash rated PPE, coordinate Lockout/Tagout procedures with the facility Point of Contact, and submit outage requests at least 14 days in advance if facility-wide or partial power outages are required. All personnel must be appropriately licensed by state and local authorities. Deliverables include a detailed Field Service Report documenting inspections and repairs and a NETA-certified test report with Megger results for the feeder cable. The contractor is responsible for debris removal, hazardous waste disposal in compliance with federal, state, and local regulations, and restoration of any damaged work areas to pre-contract conditions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SwithGear QA CGA Response 5NOV26.pdf | ||
| Combined Synopsis Solicitation CGC Switchgear FY27.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of Homeland Security
United States Coast Guard
SPECIFICATIONS
Inspect and Repair of 13.2KV Main Switchgear
AT THE
U.S. COAST GUARD ACADEMY
NEW LONDON, CT
(NEW LONDON COUNTY)
LT Christian Reed, Design Project Manager
Mike Cost, Chief of C&E
CDR Avery Weston, Facilities Engineer
Chief of Division
P a g e | 2
1.0 Background & Objective
Coast Guard Academy requires an inspection, fuse replacement, component repair, and testing of existing Eaton/Cutler-Hammer MVS2 Medium Voltage Switchgear (13.2 kV), as well as insulation resistance testing on a specific 15kV feeder cable. Parts have been previously cannibalized from certain cabinets, requiring a certified electrical contractor to assess, procure, and install replacement
OEM components to restore full operational capability.
2.0 Equipment Specifications
Specification Value
Equipment Type Eaton/Cutler-Hammer MVS2 Load Interrupter Switchgear
System Voltage 13.2 kV
Fuse Type Eaton 15CLE-250E (15.5 kV, 3-inch Single Barrel)
Style Number (Reference) 1A33843G26
3.0 Scope of Work: Cabinet 5 Maintenance, Testing, and Re-
energization
The Contractor shall provide all labor, materials, equipment, and supervision to perform the following:
3a. Inspection: Thoroughly inspect all parts and components within Cabinet 5 to ensure safe operation.
Note any damaged parts.
3b. Fuse Replacement: Safely remove the existing fuses and install three (3) new Eaton 15CLE-250E fuses in Cabinet 5.
3c. Feeder Cable Testing: Perform Insulation Resistance (Megger) testing on the 15kV feeder cable running from Switchgear Cabinet 5 to its termination point at Smith Hall. Testing shall be performed in accordance with current ANSI/NETA ATS/MTS standards. Provide a certified test report detailing the resistance readings and pass/fail criteria. If testing requires a building shutdown, coordinate with the Contracting Officer’s Representative (COR).
3d. Re-energization: Safely put Cabinet 5 and the associated feeder line to Smith Hall back online.
3e. Spares: Procure and deliver three (3) extra Eaton 15CLE-250E fuses to the site point of contact to be kept as on-site spares.
P a g e | 3
4.0 General Requirements
A. Structural members shall not be cut or altered, without authorization of the Contracting Officer
(KO) or Contracting Officer Representative (COR). Work remaining in place that is damaged or defaced during this contract, shall be restored to the condition existing at time of award of contract.
B. The Contractor is responsible for moving any equipment located in the work area (except for equipment and/or paperwork that cannot be moved, in which case the Contractor shall provide adequate protection for such items before any work is started). All moved items should be put back to their original locations as work is completed.
C. When required, the Contractor shall provide necessary barrier and direction signs so that pedestrian and vehicle traffic is routed around the area while work is in progress.
D. All personnel engaged in the contract activities specified must be licensed by the state, local authority, and/or the local city authority for trades, crafts or professions that require licensing by such jurisdictions. The license must be of a grade or other level consistent with the requirement of the work being performed and/or as established by the above jurisdictions.
E. All outage requests, must be submitted and approved, in writing a minimum of 72 hours in advance. Work should be planned in advance to give as much time as possible to schedule an outage. No work is to be done until official approval of the request is given. There may be times when an outage request is denied because of insufficient lead-time or interference with ongoing activities and have to be rescheduled.
F. Any work performed by the Contractor at his/her own volition outside specified working hours will be at no additional expense to the Government.
G. No unauthorized work shall be initiated without the prior approval of the Contracting Officer (KO) or the Contracting Officer’s Representative (COR) only. The Contracting Officer shall approve any request, or proposal for changes in project scope, completion time and/or additional requirements, in writing prior to the Contractor proceeding with any related work. Any changes accomplished without prior written approval, will be done at the Contractor’s expense.
H. It is highly recommended that the Contractor visit the job site and visit the building in order to determine what is reasonable or necessary to ascertain the nature and location of the work to be performed in general, and the local conditions which can affect the work or the cost thereof. Failure to do so will not relieve the Contractor of his responsibility for estimating properly the difficulty or cost of successfully performing the work.
I. The Contractor shall be responsible for complying with any applicable laws, codes, and regulations
(federal, state and local) in connection with the prosecution of the work. Additionally, the
Contractor is responsible for obtaining all permits, licenses, etc. that are required by local law or ordinance.
P a g e | 4
J. The Contractor shall remove all debris from the project site and dispose of it in a proper, acceptable manner off the job site property. The debris created from this project will not be disposed of at the job site, in Government dumpsters, or on Government property.
K. Disposal of all waste material shall be in accordance with all applicable Federal, State, and local environmental regulations. The Contractor shall ensure and provide appropriate documentation to
Contracting Officer that all hazardous waste handlers, haulers, and disposal facilities are properly certified or licensed. The Contractor shall provide shipping manifest and documentation of disposal of any substance that is controlled by Federal, State and local regulation prior to final payment.
L. The Contractor shall make every reasonable effort to protect all Government property located in and adjacent to the construction area.
M. All work required for the Government to accomplish this project in strict accordance with the best practices of the building trades involved and as intended. The contractor shall be solely responsible for compliance with all OSHA, state, and local regulations.
N. Clean up all debris caused by work of this section, touch up any scratches or abrasions on equipment or clock faces.
5.0 Safety & Outage Coordination
Safety Standards: All work must comply with NFPA 70E (Standard for Electrical Safety in the Workplace) and OSHA regulations. The Contractor must provide their own Arc Flash rated PPE.
Lockout/Tagout (LOTO): The Contractor shall coordinate with the facility Point of Contact (POC) to ensure proper LOTO procedures are executed prior to opening any switchgear cabinets.
Outage: If a facility-wide or partial power outage is required to safely perform the repairs and testing, the Contractor must submit an outage request to the COR at least 14 days in advance.
6.0 Deliverables
Field Service Report: A document detailing the inspections, fuse replacements, and repairs made to all awarded cabinets.
NETA Test Report: Certified Megger test results for the Cabinet 5 to Smith Hall feeder cable, plus testing reports for any repaired cabinets.
P a g e | 5
Nameplate for the Switchgear.
P a g e | 6
Medium Voltage breaker cabinet 5, stress cones and feeders to Smith Hall.
P a g e | 7
Medium Voltage Switchgear Line-Up.
Smith Breaker Cabinet.
P a g e | 8
Meter component door with cabinet back box
Metering backbox with components
| 1.0 Background & Objective |
| 2.0 Equipment Specifications |
| 3.0 Scope of Work: Cabinet 5 Maintenance, Testing, and Re-energization |
| 4.0 General Requirements |
| 5.0 Safety & Outage Coordination |
| 6.0 Deliverables |