Amendment 0002
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Abstract_19-B-BF2221.pdf | ||
| Amendment0001_19-B-BF2221.pdf | ||
| P10364042Dwgs1-31.pdf | ||
| P10364042Dwgs32-62.pdf | ||
| P10364042Specs_Reduced.pdf | ||
| P10276005Dwgs.pdf | ||
| P10276005Specs.pdf | ||
| IFB_70Z0G119BBF222100.pdf | ||
| General_Decision_Number_FL190222_02012019.pdf | ||
| Standard_Form_24.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
PAGE OF PAGES
1 1
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
06/18/2019
4. REQUISITION/PURCHASE REQ. NO.
2119G19BF2221
5. PROJECT NO. (If applicable)
10364042 & 10276005
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
Contracting Officer USCG Civil Engineering Unit Providence 475 Kilvert ST STE 100 Warwick, RI 02886
Same as Block 6 Attn: Daniel B. Walker, Contracting Officer
(401) 736-1764
(401) 736-1704 (fax)
8. NAME AND ADDRESS OF CONTRACTOR (NO., STREET, COUNTY, STATE AND ZIP CODE)
THIS AMENDMENT MUST BE ACKNOWLEDGED
See Block 11 below
9A. AMENDMENT OF SOLICITATION NO.
70Z0G119BBF222100
9B. DATED (SEE ITEM 11)
24 MAY 2019
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such Change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE REFERENCED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET
FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (SPECIFY TYPE OF MODIFICATION AND AUTHORITY)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
THE SOLICITATION REFERENCED IN BLOCK #9A IS AMENDED AS FOLLOWS:
1. QUESTIONS & ANSWERS SUBMITTED DURING THE PERIOD FOR RECEIPT OF QUESTIONS:
1. On sheet 3 of 32 RPUID 7907-BOQ-Base Officer Quarters, Note 5 says to remove water damaged stucco and replace with new stucco system. Where is this work to be performed? There is no unit price for this work.
ANSWER: The work is delineated on Sheet A-201H (sheet 30 of 62) see elevation C1 East Elevation notes D2 and Note 8. The limits of the work are indicated on the elevation, no need for a unit price.
Continued… Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or Print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
DANIEL B. WALKER, Contracting Officer
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED
16B UNITED STATES OF AMERICA
BY
(Signature of Contracting Officer)
16C. DATE SIGNED
6/18/2019
NSN 7540-01-152-8070 STANDARD FORM 30 (Rev. 10-83) PREVIOUS EDITION UNUSABLE Prescribed by GSA
FAR (48 CFR) 5
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
PAGE OF PAGES
2 2
2. Is this the work required by Sheet Key Note 8 on Sheet 30?
ANSWER: Yes, this work is addressed in notes D2 and note 8.
3. Note 13 on Sheet 3 says to replace the soffit lighting at the BOQ. But the plans do not show any to be replaced. Where and how many??
ANSWER: There are (5) five fixtures and they are located over the egress doors.
4. Please verify Site Personnel Requirements: Is one Superintendent (Qualified Supervisor) sufficient for this project or will there need to be a separate QC and/or any other additional site personnel?
ANSWER: The contractor is responsible to provide adequate (sufficient) staffing to complete the project in accordance with the schedule, plans, specifications and contract terms and conditions. Superintendence by the Prime is required in accordance with FAR 52.236-6, Superintendence by Contractor.
5. Is this considered one project or two for Supervision purposes?
ANSWER: This solicitation will result in one contract. The work includes multiple buildings. Superintendence (Supervision) by the Prime is required in accordance with FAR 52.236-6, Superintendence by Contractor.
6. Can the site visit sign in list be made available?
ANSWER: Yes. See attached.
2. Note: All Bidders shall provide pricing in accordance with the SF 1442 and the pricing schedule incorporated in Section B of the Invitation for Bids (Solicitation). Disregard references to UNIT PRICES included in Drawing Discipline Sheet Number G-003 (sheet 3 of 62).
3. The sign in sheet for the Pre-Bid meeting held on June 11, 2019 is hereby provided.
4. The Due Date for Receipt of Bids is extended to Friday, June 28, 2019, AT 2:00 PM LOCAL TIME, WARWICK, RI
All other terms and conditions remain unchanged.