This document contains an amendment to an invitation for bid for maintenance dredging services at the United States Coast Guard Station Cape Disappointment in Ilwaco, Washington. The amendment provides answers to questions from potential offerors. The maintenance dredging work includes conducting dredging, disposal of dredged materials at approved sites, pre- and post-dredging surveys, compliance with environmental permits, and reporting requirements. The approved work window is from November 1, 2022 to February 28, 2023. Bids are due between December 5-12, 2022 and the procurement value is estimated between $1,000,000 to $5,000,000. The amendment clarifies that dredged materials can only be disposed at designated sites in the Baker Bay Flowlanes using bottom dump barges or hopper dredges unless pipeline disposal is approved. It also addresses questions about turbidity curtain requirements and submittal timelines.

View the file

Other files

File Type Posted
ABSTRACT OF OFFERS IFB 70Z08823R00000354.pdf PDF
Amendment 0009 - IFB_70Z08823R00000354_CAPE D MTC DREDGE.pdf PDF
APPENDIX C-SPECIFICATIONS_StaCapeDdredge_FinalRev15Dec2022.pdf PDF
Amendment 0008 - IFB_70Z08823R00000354_CAPE D MTC DREDGE_09Dec22.pdf PDF
Amendment 0007 - IFB_70Z08823R00000354_CAPE D MTC DREDGE_09Dec22.pdf PDF
Amendment 0006 - IFB_70Z08823R00000354_CAPE D MTC DREDGE_09Dec22.pdf PDF
Amend 5 Attachment 1-63169GP Modified Authorization_08Dec22.pdf PDF
Amendment 0005 - IFB_70Z08823R00000354_CAPE D MTC DREDGE_09Dec22.pdf PDF
Amend 3 Attachment 1-DSL Permit Exp 28Apr23_63169GP RenewalAuthorization20220803.pdf PDF
Amendment 0003 - IFB_70Z08823R00000354_CAPE D MTC DREDGE_08Dec22.pdf PDF
Amendment 0002 - IFB_70Z08823R00000354_CAPE D MTC DREDGE.pdf PDF
Amendment 0001 - IFB_70Z08823R00000354_CAPE D MTC DREDGE-Map.pdf PDF
APPENDIX B1-Environmental Permits.pdf PDF
APPENDIX F-Clarification Request Form.docx DOCX document
IFB_70Z08823R00000354_MAINTENANCE DREDGING AT USCG STATION CAPE DISAPPOINTMENT.pdf PDF
APPENDIX C-SPECIFICATIONS_StaCapeDdredge_21 Sept 2022.pdf PDF
APPENDIX E-Contractor Responsibility.pdf PDF
APPENDIX D-WAGE DETERMINATION_WA20220080_25Feb22.pdf PDF
APPENDIX G-CERT OF AUTHORIZATION TO BIND CORPORATION FAR 4.pdf PDF
APPENDIX B2-Dredge Prism Design-26Sept2022.pdf PDF
APPENDIX A-SF1442-STACAPED DREDGE_R0000354.pdf PDF
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. CONTRACT ID CODE PAGE OF PAGES

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1 3

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

0004 09Dec2022 51290PR220000354 21034736

6. ISSUED BY CODE 51290 7. ADMINISTERED BY (If other than Item 6)

CODE

Commanding Officer

CG CEU OAKLAND (CN)

1301 Clay Street 7th Floor, Suite 700N Oakland, CA 94612-5203

Commanding Officer

CG CEU OAKLAND (CN)

1301 Clay Street 7th Floor, Suite 700N Oakland, CA 94612-5203

8. NAME AND ADDRESS OF CONTRACTOR (No. Street, county, State and ZIP: Code) (4) 9A. AMENDMENT OF SOLICITATION NO.

X 70Z08823R00000354

9B. DATED (SEE ITEM 11)

09Dec2022

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning one (1) copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATA SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and data specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(4) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.)

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER: Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copy to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

MAINTENANCE DREDGING AT THE U.S. COAST GUARD (USCG), STATION CAPE DISAPPOINTMENT, ILWACO, WA

The purpose of this Amendment No. 0004 is to provide answers to RFI Numbers 7-10 on the following 2 pages.

- All other Terms & Conditions remain unchanged.

Except at provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Travis Cohen Contracting Officer

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

(Signature of person authorized to sign)

BY ___________________________________________

(Signature of Contracting Officer)

09Dec022

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)

PREVIOUS EDITION UNUSABLE COMPUTER GENERATED Prescribed by

IFB 70Z08823R00000354

MAINTENANCE DREDGING AT THE USCG, STATION CAPE DISAPPOINTMENT, ILWACO, WA

RFI’s 7-10

Question 7:

Reference: “All dredged sediment shall be removed using a mechanical clamsheel or hydrauling suction and transported by barge for disposal in either the Baker Bay FLowlane Disposal Area D or BB3 (Both within the Columbia River/Clatsop County OR). All work shall be completed during the in water work window of 01 Novermber 2022 through 28 February 2023.”

Please confirm whether “TRANSPORTED BY BARGE FOR DISPOSAL” is the only method to disposal the material or would pipeline disposal method permitted as well?

Response 7:

Our current Corps permit only allows disposal of sediment in the Baker Bay Flowlanes using a bottom dump barge or hopper dredge. The US Coast Guard has sent a request to modify this condition and allow the use of pipeline for disposal. The response for approval is pending.

Question 7a:

Please adjust the in-water working window.

Response 7a:

The in-water work window is set by the Oregon Department of Fish and Wildlife and the National Marine Fisheries Service to avoid times of the year when most species migration rates are at their peak. The US Coast Guard is not able to adjust this window.

Question 8:

Reference: “The maintained by vessel operators and dredge equipment. Contractor shall deploy a full length turbidity curtain surrounding the work area to minimize the suspected sediments to nearby eelgrass bed.”

Does the whole area of the coast guard station have to have a silt curtain around it or just the eelgrass area?

Response 8:

Yes. The requirement is for the work area to be surrounded by a full-depth turbidity curtain to reduce the effects of suspended sediments.

Question 9:

“This submittal is required 25 days prior to start of work and must be approved by the Corps prior to initiating the work.”

With regards to the submittals is there going to be enough time to do the work with 25 day requirements of advanced notice before dredging?

Response 9:

The US Coast Guard is cognizant of the time restrictions and limited schedule for this project. If planned appropriately, there is sufficient time for award, a kick off meeting, and pre-project compliance. The regulatory agencies require a pre-project meeting at least 7 days prior to initiating work, and the submittal of a Dredge Operations Plan (also referred to as Dredging and Disposal Workplan)- including a pre-dredge hydrographic survey and eelgrass survey- two weeks prior to the pre-project meeting. The US Coast Guard will need to review the dredge operations plan prior to submittal to the regulatory agencies for internal approval. Please plan accordingly.

Question 10:

Would the potential upland placement site in Port of Ilwaco be possible available for material disposal?

If so, do we need to remove/manage all the sediment that we pumped?

Response 10:

Disposal is only available, and approved, at the Baker Bay Flowlanes (Area D and BB3). The US Coast Guard does not have approvals or authorization to dispose of sediment at the Port of Ilwaco upland placement site.

- END -