This solicitation is for an Indefinite Delivery, Requirements (IDR) contract for dockside repairs of the United States Coast Guard Cutter HEALY. The scope of work includes ship repair and associated support work. The period of performance for the IDR contract is from date of award through December 2022. The anticipated period of performance for the initial task order for repairs of the HEALY is January 2022 through May 2022. The solicitation response date is December 3, 2021 and award is expected on December 23, 2021. This requirement is set aside as 100% small business and the NAICS code is 336611. Offerors must submit pricing for line items in Attachment 2 and meet the proposal requirements in Attachment 3 by the response date to be considered for the award of this IDR contract and initial task order for repairs of the HEALY.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 7 - Government Responses to Requests for Clarification Government Responses Solicitation: 70Z08522RP4505600
USCGC HEALY FY22 FYQ2
10 November 2021
Q1. Will the USCGC HEALY be available prior to bid submission for a site visit?
(5) INSPECTION OF CUTTER PRIOR TO SUBMISSION OF PROPOSALS
This RFP is for the Dry-Dock (DD) and Repairs of the USCGC HEALY (WAGB 20) hereinafter referred to as "vessel". The DD and repair is to be awarded via Task order under this contract. The vessel’s home pier is in Seattle WA. The vessel will not be available during the solicitation period. However, they can be available during one of the port calls:
14-16 October – Boston MA
A1. The USCGC HEALY will be available for inspection/site visit/ship check during on the following dates and locations:
14 November – 15 November 2021 at Naval Base San Diego, CA 22 November – 03 December 2021 at USCG Base Seattle, WA
Attachment 3 (REV 02, dated 11/21/21) Section FAR 52.212-1 Addendum (5) has been updated to reflect these dates and locations.
Q2. Is the intent for the contractor to replace the compressors with new GFP compressors or to overhaul the (3) air compressors with Contractor provided parts?
1.1 Intent. This work item describes the requirements for the Contractor to overhaul the Sauer Type WP 400 Start Air Compressor(s).
1.2 Government-furnished property
A2. It is the Government’s intent for the contractor to overhaul the three (3) air compressors with the government furnished overhaul kits. Each SAUER WP400-12KF kit contains the following parts. All other materials/consumables must be provided by the contractor.