USCGC KENNEBEC DD FY21 RFQ NO: 70Z085-20-Q- P4500300
AMENDMENT NO. 03
The purpose of this Amendment No. 3 is as follows:
A) To provide updated revised Specification and Price Sheet (2 separate revised attachments) titled:
1) “Attachment 1 - KENNEBEC DD FY21 SSOS Price Sheet Rev1_19Oct20”
a) WI 42 changed to Option from Definite. Question 8;
b) WI 41 is deleted from this project. Question 11;
c) WI 57 is deleted from this project. Question 1
2) “Attachment 2 - KENNEBEC DD 21 SPEC Rev3 dated 19Oct20”
* Be sure to use the correct Spec & Price Sheet when submitting RFQ responses.
B) To provide requested Drawings from Clarification questions. There are a total of six (6) additional separately attached Drawings as follows:
Two (2) for Questions 3 & 14, One (1) for Question 5, Two (2) for Question 6, One (1) for Question
14.
C) To answer RFQ clarification questions 1 thru 15.
1) REF: WI-D015, Propulsion Shat Seals (Inflatable), Inflatable Renewal
Q: The item contains paragraphs that are mislabeled and duplicated.
1. Paragraph 3.5.6 is mislabeled
2. Paragraphs 3.8 thru 3.8.2 (Inflatable Seal Testing) are duplicated by paragraphs 3.9 thru
3. Paragraphs 3.9 thru 3.9.2 (Restoration) are duplicated by 3.10 thru 3.10.2
4. Paragraph 3.10 (Preservation) is duplicated by paragraph 3.11
Will the government correct the work item?
A: Above has been corrected in attached Revision 3 of the Specifications. See new attached file titled: Attachment 2 - KENNEBEC DD 21 SPEC Rev3 dated 19Oct20
2) REF: FAR Clause 52.222-41, RFQ Pages 46-47
Q: In paragraph C page 46 of the FAR Clause 52.222-41 is not marked with an X usually this means the SCA is not used. In the flow down Far Clause page 47 to send to Subcontractors it is listed so is 52.222-41 applicable?
A: To confirm, FAR 52.222-41 is not checked and is not applicable to this project. The
Subcontractor flow-down for this clause only, is also not applicable.
3) REF: WI-60, Pg. 196, Para. 3.3, Compressed Air Piping Renew
Q: Paragraph 3.3 states to renew the cited damage piping to suit Coast Guard drawing 160B-
WLIC 4900-02. On this drawing the bill of materials in relation to the part numbers is not included. Please provide BM 61 referenced in the above mentioned drawing.
USCGC KENNEBEC DD FY21 RFQ NO: 70Z085-20-Q- P4500300
A: Viking plugs connections available maximum 400amps at 480 volts per plug. Two Appeleton connections on the mound 400 AMPS max. KTR will need to provide all connections to the mounds. Base NAVFAC will not provide, but will assist in hooking up power. BM-61 attached.
4) Ref: D-032, Rudder(s), Preserve 100%
Q: Work Item 3, Underwater Body, Preserve 100%, paragraph 4.1.1, U/W Body definition includes the rudders as part of the underwater hull. Can Work Item 32 be cancelled?
A: No. WI 32 Rudder(s), Preserve ("100%") is in the SPEC Package due to WI 31 Remove Inspect and Reinstall Rudders. If by chance the rudders fail the inspection and must be replaced they would have to be preserved as specified for Underwater Water (U/W) Body and Boot-Top
(U/W Body and Boot-Top, Steel Hulls (Up to 7 Years), in Salt Water, in SFLC Std Spec 6310, Appendix A (Cutter and Boat Exterior Painting Systems). In Work Item #3 U/W Body, Preserve (100%) the note 4.1.1 is just defining what all items that are considered to be U/W
Body
5) Ref: D-031, Para 2.4.1, 3.4.1.1 Rudder Assembly; Remove, Inspect and Reinstall
Q: Paragraph 3.4.1.1 directs the contractor to “renew all fasteners, gaskets, o-rings, and seals.
Renew packing in rudder stock packing glands”. The drawing and paragraph 3.4.1 reference
BM-32 as the Bill of Materials for this drawing. Please provide BM-32 so that the contractor may price the required materials.
A: Attached. See File titled: “Attach-Question 5 BM-32”
6) Ref: D-031, Para 3.4.1, Rudder Assembly; Remove, Inspect and Reinstall
Q: Paragraph 3.4.1 directs the contractor to “Reassemble and reinstall the port and starboard rudder assemblies, using Coast Guard Drawing 160B WLIC 2200-1”. This drawing renew all fasteners, gaskets, o-rings, and seals. Renew packing in rudder stock packing glands”. General
Note #8 of this drawing indicates to “Install all steering components in accordance with
Reference #8”. Reference #8, Drawing 160B WLIC 2200-2 was not provided as a reference.
Please provide Drawing 160B WLIC 2200-2, Hydraulic Steering System Installation and Record
Drawings.
A: Attached. See Files titled: “Attach-Question 6 160B-WLIC_32_1_-_-“ and “Attach-Question
6 160B-WLIC_2200_1_1_-_A”
7) Ref: D-037, Para 3.3.2.2, 3.4 Spud Wells, Preserve
Q: Paragraph 3.3.2.2 directs the contractor to “perform a visual inspection of spud well surfaces, including liner retainers and associated hardware”. Paragraph 3.4 directs the contractor to replace the spud well liners upon issue of an approved Change Request. Both of these paragraphs are duplicated in Work Item 38 Spud Wells, Inspect. Will the government consider deleting Work Item 38, Spud Wells, Inspect?
USCGC KENNEBEC DD FY21 RFQ NO: 70Z085-20-Q- P4500300
A: Keep both WI's but remove 3.3 from WI38, See attached updated Spec.
8) Ref: D-042, Tanks (Sewage Vacuum Collection), Preserve “Partial”
Q: Paragraph 3.3.2.2 directs the contractor to “perform a visual inspection of spud well surfaces, including liner retainers and associated hardware”. Paragraph 3.4 directs the contractor to replace the spud well liners upon issue of an approved Change Request. Both of these paragraphs are duplicated in Work Item 38 Spud Wells, Inspect. Will the government consider deleting Work Item 38, Spud Wells, Inspect?
A: WI42 changed to an Option Item for Partial preserve. See attached updated Spec. and Price
Sheet.
9) Ref: D-043, Para 3.1.6, Accessible Void(s), Preserve, Partial
Q: The work item directs the contractor to remove and dispose of all tank contents. How much fluid does the government expect to be in these voids?
A: There will be very little, if any, fluid in Voids upon arrival.
10) Ref: D-043, Para 3.2, Accessible Void(s), Preserve, Partial
Q: The work item directs the contractor to “power tool clean all affected surfaces to “bare metal”, in lieu of using abrasive blasting; and feather edges of existing intact coating to the prepared areas in order to provide a smooth transition to the new paint”. The contractor has no way of determining the amount of each void that will have to be power tool cleaned to bare metal without prior inspection. Industry other government entities use 20% total surface area as a standard when bidding on partial preservation in this manner. Will the government agree to using 20% total surface area for power tool cleaning to bare metal for bidding purposes in this work item?
A: WI 43 Accessible Voids Preserve Partial states up to 33%, will not go down to 20% for bidding purposes, and then possibly issue a CR if more than 20 less than 33.
11) Ref: D-044, Tanks (Sewage Vacuum Collection), Preserve 100%
Q: Work Item 44 Tanks (Sewage Vacuum Collection), Preserve 100% is duplicated by Work Item
41 Tanks (Sewage Holding), Preserve 100%. Will the government delete Work Item 44?
A: Remove WI 41 Sewage Hold Preserve 100%, and keep WI44 Sewage Vacuum Collection preserve 100%. See attached updated Spec. and Price Sheet.
12) Ref: D-057, Tanks (Sewage Holding), Preserve “Partial”
Q: Every Sewage “Tank” preservation item in this specification package refers to “Sewage
Collection Tank, Location 2-94-0-E, Capacity @95% = 450 Gallons.
Work Item 57 Tanks (Sewage Hold), Preserve “Partial” is duplicated by Work Item 42 Tanks
(Sewage Vacuum Collection), Preserve “Partial”. Will the government delete Work Item 57?
USCGC KENNEBEC DD FY21 RFQ NO: 70Z085-20-Q- P4500300
A: Yes, removed WI 57 sewage hold preserve partial. See attached updated Spec. and Price
Sheet.
13) Ref: O-059, Para 1.1, Lead-Based Paint & Abestos Containing Material, Perform Spot Abatement
Q: Work Item O-059 Lead-Based Paint and Asbestos-Containing Material, Perform Spot
Abatement directs the contractor to “perform Lead-Based Paint (LBP) and Asbestos-Containing
Material (ACM) abatement up to 300 sq ft when LBP or ACM is discovered during the performance of WIs within this Spec package”.
Work Item O-055 Lead-Based Paint, Perform Spot Abatement directs the contractor to “perform spot abatement of up to 300 sq ft of lead-based paint (LBP) when discovered through inspections in way of repairs performed under other work item in this specification package”.
Since the same type of abatement is being completed in both work items, can Work Item O-059 be deleted?
A: Keep both option items. WI55 is for LBP only spot removal and WI59 is for LBP and ACM
14) Ref: D-060, Para 3.3, Compressed Air Piping, Renew
Q: Work Item D-060, paragraph 3.3 directs the contractor to, “Renew the cited damage piping to suit Coast Guard Drawing 160B WLIC 4900-2 and in accordance with the General Notes in Coast
Guard drawing 160B WLIC 4900-1.”
The government provided a picture of damaged piping but never described the material to be replaced in the work item (i.e. replace parts 66, 103, 222, 14 and 6). Additionally, the drawing referenced does not have a Bill of Materials. The bill of Materials is listed in the drawing reference as BM-61.
Please provide a detailed description of the items to replace and provide the referenced Bill of
Materials, BM-61.
A: Both Drawing and BM is attached.
15) Ref: D-061, Para 3.3.3, Hull Forepeak, Repair
Q: Work Item D-061, paragraph 3.3.3 directs the contractor to, “weld repair (clad) and/or renew the chalked out sections of plating, a total of approximately 55 square feet and 10 linear feet of support structure”.
The government needs to provide quantities for bidding purposes. The full extent of the repair will not be known until after the UT inspection and the government decides what type and how much repair is required. No one will clad weld 55 square feet. That much clad welding requires the plate to be replaced.
USCGC KENNEBEC DD FY21 RFQ NO: 70Z085-20-Q- P4500300
How much weld repair (clad welding) and how much plate replacement should the contractor bid on for this item?
A: The amount of Clad Welding Is for 3 area's in the same compartment equaling up to 55 SQ
FT. The amount of plate replacement and the amount of clad welding will not be determined until after U/W Body inspection.
*** THE SOLICITATION CLOSING DATE HAS NOT CHANGED DUE TO THIS AMENDMENT.
RECEIPT OF PROPOSALS ARE DUE NO LATER THAN 06NOV20 @ 01:00 PM PACIFIC TIME.