USCGC ANTHONY PETIT (WLM 558)

RFQ NO 70Z085-19-Q-P4556800

AMENDMENT NO. 1

- QUESTIONS AND ANSWERS

1) Table 1 states 95% capacity is 245 gallons, 3.1.4.1 states to dispose of 5,000 gallons. How many gallons are to be disposed of?

USCG RESPONSE 1: Contractor can expect to dispose of 245 Gallons of F/O.

2) Can the KTR assume that the tanks listed in Table 1 will be at low suction?

USCG RESPONSE 2: Contractor should assume Ballast Tanks will be at low suction.

3) This is usually not required for a 175’ cutter, change the spec to make this a “N”.

USCG RESPONSE 3: See attached revised Specification-Revision 1, dated 25Feb19.

4) There is no under water hull or freeboard preservation items in the spec. Was this your intent for no hull coatings?

USCG RESPONSE 4: See attached revised Specification-Revision 1, dated 25Feb19.

5) Spec states to stow the potable water that is removed from the tanks. Does the contractor have the option refill the tanks with new potable water?

USCG RESPONSE 5: See attached revised Specification Revision-1, dated 25Feb19.