70Z08425RCGA00001 Questions and Answers.pdf

PDF 160 KB Posted

Attached to
CG Academy fire sprinkler system service
Solicitation number
70Z08425RCGA00002
Issued by

About this file

This is a Questions and Answers document for solicitation 70Z08425RCGA00002 regarding fire sprinkler system maintenance services at the US Coast Guard Academy in New London, CT.

The document clarifies that only one technician is required (not two), technicians will only be escorted during initial campus familiarization, and the CGA Fire Marshal will assist with lift equipment when needed. The total contract price should not include costs for emergency service calls or deficiency work, which will be funded separately. Subcontracting deficiency work is allowed at no additional cost to CGA. There are 21 backflow systems (not 23 as previously stated) and Chase Hall Bravo is the only building with an antifreeze system. The previous contract (70Z08424DCGA00001) was awarded to Sanford Federal for $132,825 but was terminated in October. Currently, the CGA Fire Marshal is performing inspections until a new contractor is awarded. The proposal due date has been extended to December 20, with Past Performance Questionnaires (PPQs) due at the same time.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Does the coast guard academy require two technicians at all times?

-No

2. Will technicians be escorted around campus during inspections?

-Only during first time around campus for familiarization.

3. Will the CGA have personnel posted at the fire alarm panel during testing/servicing?

-No, will show how to silence or put in test mode for testing/servicing/ maintenance purposes. If verifications are needed, additional techs will need to be on site.

4. Is it acceptable to sub contract deficiency work if Siemens is not able to perform repairs?

- Yes , but at no additional cost to CGA .

5. The total price of this contract is to NOT include costs anticipated for service calls and deficiency work?

-Correct. If emergency service calls are required, additional funding will be arranged.

Deficiency work will be an addition to the contract and funding arranged for total amount needed.

6. Are there any areas throughout the CGA that would require a lift to inspect devices?

-Yes. However, CGA Fire Marshal is lift certified and will utilize on hand equipment if/when

7. Does the CGA have a lift available to use on site?

-Yes. However, CGA Fire Marshal is lift certified and will utilize on hand equipment if/when

8. Will bid need to have pricing filled out on both “SECTION II” and pricing starting on page 65?

Either way is fine as long as the pricing is itemized

9. Where does pricing for “ADITIONAL INTEMS” on page 22 be submitted?

See pricing sheet for additional items on the prospective years.

10. Some confusion on page 20, technicians are not required to inspect every individual sprinkler head, correct?

-Correct, general walk through of space is acceptable.

11. Can you please provide previous inspection reports?

Yes.

12. The completed PPQ is due on or before December 18, 2024 by 12:00 PM Eastern, unless the due date is extended via a Solicitation Amendment.

The due date has been extended to 20 Dec. PPQ are due at this time as well.

13. Is this the correct date or is it the submission date of the 20th and not the 18th?

See #12

14. I also wanted to know if anyone was currently doing this contract already? I looked and didn't see anything but wanted to confirm.

-Currently there is no contractor preforming the contract. CGA Fire Marshal is doing inspections personally until a contractor is awarded.

15. Is there an Incumbent in place? If so, kindly provide the contract award number, awardee name, and award amount of the contract.

There is no current incumbent. The previous contract was awarded under 70Z08424DCGA00001 to Sanford Federal for $132,825 and was terminated in Oct.

16. I would like to confirm that there are 23 Wet systems in total. However, I noticed that Appendix B lists 21 backflows. Could you clarify if this discrepancy is accurate, or if there are additional backflows not included in Appendix B?

-Correct. There are only twenty one backflows. Typo on Fire Marshal part.

17. Is Chase Hall Bravo the only building that has an antifreeze system as well?

-Correct.

18. I would like to ask you to please consider having this requirement of verification of past performance provided by your office to ensure you receive the information you are requesting. Once we submit the past performance document to your office, your office can then contact the customers and request them for the survey. However, if they do not respond, this should not be viewed negatively to our RFP submittal.

PPQ is required prior to the due date.

19. May i have the previous incumbent information and award amount?

20. I was wondering who currently is conducting the sprinkler Maintenance 70Z08425RCGA00002 and the current contract information ? Thank you in advance.

-CGA Fire Marshal is currently doing all visual inspections, and test runs of fire pumps.

21. Could you please confirm the current incumbent, contract price, duration and when their duration ends?

There is no current incumbent. The previous contract was awarded under 70Z08424DCGA00001 to Sanford Federal for $132,825 and was terminated in Oct.