AMENDMENT_0002_TE-3_REQUIRED_DELIVERY_DAYS.pdf

PDF 59 KB Posted

Attached to
Overhaul and Maintenance Repair of USCG owned Aids to Navigation (ATON) Buoys and Parts
Solicitation number
70Z08418RBHQ00500
Issued by

About this file

This amendment modifies the required delivery days for overhauling and outfitting aids to navigation buoys under a contract for the overhaul and maintenance repair of buoys owned by the U.S. Coast Guard. The amendment establishes timeframes for completing single buoy orders and bulk orders of various buoy types, ranging from 2 to 26 calendar days for individual buoys and 4 to 236 days for bulk orders. It provides examples showing how the delivery day requirements would apply to task orders involving multiple buoy types.

TECHNICAL EXHIBIT 3, REQUIRED DELIVERY DAYS

View the file

Other files

File Type Posted
Amendment_0008_to_Solicitation_70Z08418RBHQ00500.doc DOC document
Amendment_0007.doc DOC document
Amendment_0006_to_Solicitation_70Z08418RBHQ00500.pdf PDF
AMENDMENT_0006_ATTACHMENT_1,_ZONE_1,_OPTION_YEAR_3.xlsx XLSX spreadsheet
Amendment_0004_to_Solicitation_70Z08418RBHQ00500.pdf PDF
52.212-2_EVALUATION.pdf PDF
Amendment_0003_to_Solicitation_70Z08418RBHQ00500.pdf PDF
Zone_2_Color_Scheme.pdf PDF
Amendment_0002_to_Solicitation_70Z08418RBHQ00500.doc DOC document
ZONE_2_FUEL.xlsx XLSX spreadsheet
AMENDMENT_0002_ATTACHMENT_7_-_Past_Performance_Questionnaire_(MAR2015).pdf PDF
Zone_3_Color_Scheme.pdf PDF
ZONE_3_FUEL.xlsx XLSX spreadsheet
Final_Zone_4_Option_2.xlsx XLSX spreadsheet
Final_Zone_3_Option_3.xlsx XLSX spreadsheet
Final_Zone_4_Base.xlsx XLSX spreadsheet
Final_Zone_3_Base.xlsx XLSX spreadsheet
ZONE_4_STEEL.xlsx XLSX spreadsheet
Final_Zone_2_Option_1.xls XLS spreadsheet
ZONE_1_FUEL.xlsx XLSX spreadsheet
Final_Zone_4_Option_1.xlsx XLSX spreadsheet
Final_Zone_2_Base.xlsx XLSX spreadsheet
AMENDMENT_0002_Solicitation_Revision_AMENDMENT_0002.pdf PDF
ZONE_4_FUEL.xlsx XLSX spreadsheet
Final_Zone_1_Option_3.xlsx XLSX spreadsheet
Final_Zone_1_Option_2.xlsx XLSX spreadsheet
Final_Zone_3_Option_4.xlsx XLSX spreadsheet
Final_Zone_4_Option_3.xlsx XLSX spreadsheet
Zone_1_Color_Scheme.pdf PDF
AMENDMENT_0002_TE-4_Estimated_Color_Schemes.pdf PDF
Final_Zone_3_Option_2.xlsx XLSX spreadsheet
ZONE_2_STEEL.xlsx XLSX spreadsheet
Final_Zone_1_Option_1.xlsx XLSX spreadsheet
Final_Zone_4_Option_4.xlsx XLSX spreadsheet
Final_Zone_1_Base.xlsx XLSX spreadsheet
ZONE_3_STEEL.xlsx XLSX spreadsheet
Final_Zone_3_Option_1.xlsx XLSX spreadsheet
ZONE_1_STEEL.xlsx XLSX spreadsheet
Final_Zone_1_Option_4.xlsx XLSX spreadsheet
Zone_4_Color_Scheme.pdf PDF
121132_Rev_F.pdf PDF
121151_Rev_F.pdf PDF
121188_Rev_A.pdf PDF
121112_Rev_G.pdf PDF
120994_Rev_F.pdf PDF
121145_Rev_F.pdf PDF
121130_Rev_F.pdf PDF
120316_Rev_F.pdf PDF
121056_Rev_B.pdf PDF
Zone_4_Color_Scheme.pdf PDF
Show 40 more

Latest 50 of 116 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT 0002

TECHNICAL EXHIBIT 3

REQUIRED DELIVERY DAYS

The Contractor is required to complete the overhaul and/or outfitting of the buoy, to included transportation within the number of calendar days. If a buoy is not available for overhaul at the time of the work request, the delivery date shall be determined using the date the buoy is actually available. The date of the task order shall be the basis for determining the required delivery date.

CLIN Buoy Type Work Required

Calendar Days

For Routine (Only One)

Calendar Days For Routine*

(Multiple Buoys)

OOO1AA

9X35LWR

Overhaul 26 8 Color Change 11 4

OOO1AB

9X32LR and 9X32LBR

Overhaul 26 8 Color Change 11 4

OOO1AC

9X20BR/GR

Overhaul 26 8 Color Change 11 4

OOO1AD

8X26LBR, 8X26LGR,

8X26LR, 8X26LWR

Overhaul 26 8 Color Change 11 4

OOO1AE

8X21LBR and 8X21LR

Overhaul 26 8 Color Change 11 4

OOO1AF

7X20L1

Overhaul 26 8 Color Change 11 4

OOO1AG

7X17LR

Overhaul 26 8 Color Change 11 4

OOO1AH

6X20LBR and 6X20LR

Overhaul 16 4 Color Change 10 4

OOO1AJ

5X11LNR and 5X11LCR

Overhaul 16 4 Color Change 10 4

OOO1AK

INR and ICR

Overhaul 16 4 Color Change 10 4

OOO1AL

2NR and 2CR

Overhaul 10 2 Color Change 8 4

OOO1AM

3NR and 3CR

Overhaul 10 2 Color Change 8 4

OOO1AN

5NR and 5CR

Overhaul 10 2 Color Change 8 4

OOO1AP

3M and 3C1

Overhaul 10 2 Color Change 8 4

OOO1AQ 5M and 5C1 Overhaul 10 2

Color Change 8 4 OOO1AR 5X9LFR Overhaul 10 2 OOO1AS 2NFR and 2CFR Overhaul 10 2 OOO1AT 3NFR and 3CFR Overhaul 10 2 OOO1AU 4NFR and 4CFR Overhaul 10 2

* Used when there are multiple buoys on one task order.

AMENDMENT 0002

Example 1: Task order for (1) 9x35, (10) 2NR, and (3) 7x20L1.

(1) 9x35 26 Days (includes shipping days)

(10) 2NR 10 x 2 = 20 Days (no shipping)

(3) 7x20 u 3 x 8 = 24 days (no shipping)

Total Days:

70 days to deliver buoys

Example 2: Task order for (60) 1 NR

(1) INR 16 Days (includes shipping)

(59) INR 59 x 4 = 236 days (no Shipping)

Total Days:

252 days to deliver buoys

File details come from the government source that posted it. Updated .