This amendment modifies the required delivery days for overhauling and outfitting aids to navigation buoys under a contract for the overhaul and maintenance repair of buoys owned by the U.S. Coast Guard. The amendment establishes timeframes for completing single buoy orders and bulk orders of various buoy types, ranging from 2 to 26 calendar days for individual buoys and 4 to 236 days for bulk orders. It provides examples showing how the delivery day requirements would apply to task orders involving multiple buoy types.
TECHNICAL EXHIBIT 3, REQUIRED DELIVERY DAYS
View the file
Other files
Show 40 more
Latest 50 of 116 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT 0002
TECHNICAL EXHIBIT 3
REQUIRED DELIVERY DAYS
The Contractor is required to complete the overhaul and/or outfitting of the buoy, to included transportation within the number of calendar days. If a buoy is not available for overhaul at the time of the work request, the delivery date shall be determined using the date the buoy is actually available. The date of the task order shall be the basis for determining the required delivery date.
CLIN Buoy Type Work Required
Calendar Days
For Routine (Only One)
Calendar Days For Routine*
(Multiple Buoys)
OOO1AA
9X35LWR
Overhaul 26 8 Color Change 11 4
OOO1AB
9X32LR and 9X32LBR
Overhaul 26 8 Color Change 11 4
OOO1AC
9X20BR/GR
Overhaul 26 8 Color Change 11 4
OOO1AD
8X26LBR, 8X26LGR,
8X26LR, 8X26LWR
Overhaul 26 8 Color Change 11 4
OOO1AE
8X21LBR and 8X21LR
Overhaul 26 8 Color Change 11 4
OOO1AF
7X20L1
Overhaul 26 8 Color Change 11 4
OOO1AG
7X17LR
Overhaul 26 8 Color Change 11 4
OOO1AH
6X20LBR and 6X20LR
Overhaul 16 4 Color Change 10 4
OOO1AJ
5X11LNR and 5X11LCR
Overhaul 16 4 Color Change 10 4
OOO1AK
INR and ICR
Overhaul 16 4 Color Change 10 4
OOO1AL
2NR and 2CR
Overhaul 10 2 Color Change 8 4
OOO1AM
3NR and 3CR
Overhaul 10 2 Color Change 8 4
OOO1AN
5NR and 5CR
Overhaul 10 2 Color Change 8 4
OOO1AP
3M and 3C1
Overhaul 10 2 Color Change 8 4
OOO1AQ 5M and 5C1 Overhaul 10 2
Color Change 8 4 OOO1AR 5X9LFR Overhaul 10 2 OOO1AS 2NFR and 2CFR Overhaul 10 2 OOO1AT 3NFR and 3CFR Overhaul 10 2 OOO1AU 4NFR and 4CFR Overhaul 10 2
* Used when there are multiple buoys on one task order.
AMENDMENT 0002
Example 1: Task order for (1) 9x35, (10) 2NR, and (3) 7x20L1.
(1) 9x35 26 Days (includes shipping days)
(10) 2NR 10 x 2 = 20 Days (no shipping)
(3) 7x20 u 3 x 8 = 24 days (no shipping)
Total Days:
70 days to deliver buoys
Example 2: Task order for (60) 1 NR
(1) INR 16 Days (includes shipping)
(59) INR 59 x 4 = 236 days (no Shipping)
Total Days:
252 days to deliver buoys