This document contains a set of Questions and Answers related to a solicitation for a Steam Boiler Installation project at the USCG Base in Elizabeth City, North Carolina. The solicitation number is 70Z08124Q00000142.
The key details include:
- The equipment being provided is new from the factory.
- Controls will be provided with the equipment.
- The existing exhaust termination may be suitable for reconnection, or a new stack may be required.
- There are no chemical treatments or new pumps needed.
- The work will be performed inside the mechanical room and does not need to be coordinated with other ongoing work at the base.
- Permitting, inspection, and startup services are required.
- The contract will be a Firm-Fixed Price contract.
- The procurement is set aside for Small Businesses under NAICS code 238220.
- The estimated cost range is between $30,000 to $34,000.
- A site visit is required and will be held on 06/20/2024.
- Questions about the solicitation must be submitted by 07/03/2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B53 Boiler Q and A v3.pdf | ||
| B53 Boiler Ques and Answer v.2_Posted June 28.pdf | ||
| DAVIS BACON ACT WD NC20240056.pdf | ||
| DAVIS-BACON-ACT.pdf | ||
| B53 Install Replacement Steam Boiler SOW.docx | DOCX document | |
| Construction clauses less than 35k.docx | DOCX document | |
| SF1442-24 70Z08124Q00000142.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
These questions and answers provided to all possible offers.
USCG Base Elizabeth City, NC Bldg. 53 Boiler Installation Project Q & A Solicitation Number: 70Z08124Q00000142 Date; 6/25/2024
Questions & Responses
1. With the equipment being provided, is this new from factory? Yes, para. 17, General, Pg. 4
1. If the equipment isn’t new, has it been assembled in another location then moved?
1. Are there any controls being provided with the equipment? YES
1. The existing condition of the exhaust termination, suitable for reconnection. Or will new stack from the boiler to the top of the building ? Paragraph 17, D, pg. 5
1. Are there any specialty pieces (from manufacturer and or customer) to be installed with boiler ? Unknown
1. Are there any chemical treatments that need to be added ? No
1. Is there a need for new pump/ series of pumps needed ? No
1. Are any controls connected to a Building management system? No
1. After installation, will the customer need a monthly service schedule provided ? No
1. Work being done inside mechanical room, will it need to be coordinated due to location of other work being done on base ? No
1. Permitting and inspection & start-up ? Yes, Para. 17, 18, pg. 6 What is the customer’s preference? Both