Question 1:

Why am I having difficulty reviewing the Task Orders and PWS for the USCG EDS solicitation and none of the links are functional on SAM?

Answer 1:

Please be sure that you are signed in. Search for the RFP number 70Z04420R20002500. This should help you locate and download the attachments.

Question 2:

One of the attachments state that the initial period of performance will be 10 months while the other attachment states that the initial period of performance will be 8 months. Which is correct.

Answer 2:

The period of performance for the base year of the Indefinite Delivery Indefinite Quantity (IDIQ) is 10 months. 3 The period of performance for the base year of the Task Order 1 is 10 months.

The Period of Performance will be corrected under RFP Amendment 0001 in the solicitation.

Question 3:

Cannot find a WDOL for South Kingstown, RI where the work will be performed. Can you provide us with the Wage Determination doc or how to access it for Washington County in Rhode Island as there is difficulty locating it?

Answer 3:

The Wage Determination (WD) for South Kingstown, RI, will be posted as attachment seven (7) under RFP Amendment 0001 and posted publicly.