This is a solicitation amendment (Amendment A00003) to Solicitation No. 70Z04026QSBPL0014 issued by the Coast Guard in response to vendor clarification requests regarding a vessel maintenance project at the Detroit facility.

The amendment addresses three key areas of vendor concern. First, the Coast Guard confirmed that IPF Detroit will provide haul-out, blocking/cradles, vessel repositioning, and relaunch services as needed by the contractor, eliminating the requirement for the contractor to include these services in their bid. Second, while a shipcheck had not been scheduled at the time of the amendment, vendors interested in conducting a site visit before the quotation deadline are directed to contact the Port Engineer/Contracting Officer's Representative, Senior Chief B. Biddle, to coordinate the inspection. Third, the Coast Guard confirmed that utilities and support—including electrical power, water, and space for equipment and temporary enclosure—will be available to the contractor onsite during the period(s) of performance. All other terms and conditions of the original solicitation remain unchanged.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. 70Z04026QSBPL0014 A00003

The above referenced solicitation is hereby amended in response to Request for Clarification.

1. QUESTION: Will the Coast Guard provide haul-out, blocking/cradles, any required vessel repositioning, and relaunch at the Detroit facility, or must the contractor include these services?

ANSWER: Yes, IPF Detroit can supply support activities as needed by the commercial vendor.

2. QUESTION: Is a ship check scheduled? If not, can a site visit be arranged before the quotation deadline as there are no square footages listed in the specification?

Please provide the scheduling contact and any applicable access requirements.

ANSWER: A shipcheck has not been scheduled as of yet but if the vendor would like to conduct a shipcheck, please reach out to the Port Engineer/COR, Senior Chief B. Biddle (email attached above), for the projects to coordinate.

3. QUESTION: What utilities and support will be available to the contractor onsite, including electrical power, water, and space for equipment and the required temporary enclosure?

4. Answer: Yes, support will and can be provided to the commercial vendor onsite during the period(s) of performance.

ALL OTHER TERMS AND CONDITIONS REMAIN UINCHANGED