Pre-Award Preparation Package
Shipyard Pre-Award Survey Preparation Package
USCG SFLC QUALITY ASSURANCE (Rev. 03/2017) FOUO (When Completed) 2
The below listed items will be requested by a U.S. Coast Guard Representative for each survey conducted and may include additional items which are contract specific. This list is covered in detail in the checklist which follows.
Contractor Organizational Chart
Sub-Contractor List with address, points of contacts, phone numbers
Estimating form or spreadsheet (Initial and CFR)
Contractor Furnished Equipment Management Process or OPS manual
Heavy Weather/Severe Weather and Fire Emergency Procedures
Safety Program
Prior (2 each) CG Vessels in for repair at facility: Vessel Name, Contract Number, and Port Engineer
Example of a past Progress Chart (GANTT)
CFR Form
Gas Free Program and Competent Person qualifications
Updated Certifications including:
o NDT o Welding Certifications (Requires industry endorsed initial certification and 6 month continuity)
Painting QA Program with current Certifications
Production QA Program or Process
Environmental Compliance:
o Title V air permit o Confirmation of MACT compliance o Asbestos removal license o EPA Cert to remove ODS or repair AC&R o State or Federal EPA issued Hazardous Waste Generation ID Number o Two Past copies of Hazardous Waste Manifests o Notification of PCB Activities with EPA o Copies of Manifest or BOL for asbestos shipments o Blast Material Disposal permit o EPCRA Tier I or II Report (or confirmation of exemption) o Hazardous Material Tracking System Docs o NPDES permit (include Hydro blast Certifications or License if applicable) o Spill Prevention, Control and Countermeasures approved by EPA o Facilities response Plan approved by EPA (may be contained in Spill Plan)
All Dry-Dock/Mobile Hoist relevant certificates and documentation
CG Facility Certification as per USCG SFLC Standard Specification 8634
Dock Master Resume
USCG SFLC QUALITY ASSURANCE (Rev. 03/2017) FOUO (When Completed) 3
Common Acronyms
CFE-Commercial Furnished Equipment
CFR- Condition Found Report
EPCRA- Emergency Planning and Community Right-to-Know Act
FRP-Facility Response Plan
GANTT- A Gantt chart is a type of bar chart, which illustrates a project schedule
GFE-Government Furnished Equipment
GFP-Government Furnished Property
KTR-Contractor
MACT-Maximum Achievable Control Technology
MTI-Mandatory Turn-In
NDT- Nondestructive testing or Non-destructive testing
NDE-Nondestructive examination
NDI-Nondestructive inspection
NPDES-National Pollutant Discharge Elimination System
ODS- Ozone Depleting Substance
QA-Quality Assurance
SFLC- Surface Forces Logistics Center
SPCC- Spill Prevention, Control, and Countermeasure Plan
WX-Weather http://www.epa.gov/osweroe1/content/lawsregs/epcraover.htm http://cfpub.epa.gov/npdes/
USCG SFLC QUALITY ASSURANCE (Rev. 03/2017) FOUO (When Completed) 4
MANAGEMENT PERSONNEL
Description Response
1. Organization
Required Doc:
Organization Chart
1. Does the contractor have a well organized Personnel/
Organization Chart?
2. Total workforce size?
2. Sub-Contractor Control/Resources
Required Doc:
Sub-contractor list
List of All Required Technical Reps
Teaming Memo/Joint Venture
1. Provide a list of sub-contractors for contract?
2. What work items are the sun-contractors responsible for?
3. Is there a “Contractor Teaming Arrangement”
4. What % of work will be conducted by subcontractors?
5. Has there been any issue with unresponsive or unreliable subs?
6. Who is responsible for oversight of sub-contractors workmanship?
3. Estimating Capability
Required Doc:
KTR Estimating Form
Condition Found Report Form
Critical Inspection Report Form
1. Is the estimating process well documented and thorough?
2. Does the estimating sheet show an understanding of the work?
3. Does the CFR form address technical requirements, are they detailed?
4. Does KTR have a Critical Inspection form?
5. How are the forms submitted?
4. Personnel Qualification Accountability 1. Does the KTR maintain training records for employees? If yes, by who?
2. How does the KTR ensure work is done by properly skilled personnel?
3. Is there a method for recording completion of “certified” work?
5. Labor Base
1. How difficult is it to increase workforce for surge requirements?
2. Does the KTR have a list of ready hires if necessary?
3. Does the KTR use a hiring service? If so, who?
6. Labor and Management Communication
1. Does the KTR have a written communication policy/procedure?
2. How often does management meet and who does that include?
(Foreman/Supervisors/Project Managers (PM))
3. How is conflict resolved, internally or with CG?
4. Who is the POC for conflict/complaints?
5. Will there be a dedicated PM for DD? If yes, who?
7. Process for Identifying, Purchasing, and Tracking CFE
Required Doc:
Contractor Furnished Equipment Management
Process or OPS manual
1. Does the KTR have a written procedure for purchases?
2. Who orders CFE, and how are supplies tracked/managed?
3. Will GFE/CFE be stored in a secured place? Where? Who has access?
Remarks: *
Overall Evaluation: Risk overall is * High Moderate Low * Surveyor shall, in remarks above, provide a narrative explanation for the overall risk selected for this evaluation factor.
USCG SFLC QUALITY ASSURANCE (Rev. 03/2017) FOUO (When Completed) 5
SAFETY
8. Emergency Procedures:
Required Doc:
Heavy Weather Plan
Fire Plan
1. Does KTR have a “Severe WX Plan” IAW SFLC Std Spec 0000
3.2.3?
2. Does KTR have a Fire Plan?
9. Safety Program
Required Doc:
Safety Program
(index if program is multivolume, too large to be attached, and can easily be requested by section)
1. Does KTR have a written program that addresses common safety concerns, such as:
a. Personal Protective Equipment (PPE)
b. Safety Data Sheets (SDS)
c. Dive Plan
d. Hot Work/Fire Watch
e. Tag-Out
f. Confined spaces
g. Emergency actions
h. First Aid
i. Training for new hires
j. Toxic and hazardous Substances
10. Insurance-Certificate of Liability
Required Doc:
Certificate of Liability
1. Does the KTR have insurance to cover major equipment involved in the availability (i.e. cranes, mobile hoists, docks)?
11. Emergency Services
Required Doc:
OSHA Injury Report
Memorandum of Understanding /FD
1. Last OSHA reportable injury?
2. Do you have a MOU with local FD?
3. How often does FD conduct site visits?
4. Distances-
a. Closest Fire Department________
b. Closest Ambulance____________
c. Closest Hospital______________
12. HAZMAT Program & EPA Compliance
Required Doc:
Title V Air Permit
EPA ID #
Hazardous Waste Manifest-General
Hazardous Waste Manifest-Blast Material
EPA 7710-53
EPCRA Tier I or Tier II Report
NPDES Permit
1. Complete “Environmental Compliance for Shipyards” Worksheet
2. Does the KTR use “Best Management Practices” for water run-off and containment of blast media?
3. Does KTR have an Environmental Waste Management Plan IAW
SFLC STD Spec 0000, Appendix B2?
Overall Evaluation: Risk overall is * High Moderate Low * Surveyor shall, in remarks above, provide a narrative
USCG SFLC QUALITY ASSURANCE (Rev. 03/2017) FOUO (When Completed) 6
SATISFACTORY RECORD OF INTEGRITY AND BUSINESS ETHICS
13. Better Business Bureau complaints? 1. Is company rated by BBB or equivalent?
14. Business Classification
Required Docs:
Letter of Proof of classification (Self Certification)
1. Set Aside?
2. Small business
3. Hub Zone
4. Service Disabled Veteran
5. Women/Minority/Native American
6. Are you registered in BETA SAMS (System for Award
Management )
Overall Evaluation: Risk overall is * High Moderate Low * Surveyor shall, in remarks above, provide a narrative
USCG SFLC QUALITY ASSURANCE (Rev. 03/2017) FOUO (When Completed) 7
ABILITY TO MEET DELIVERY OR PERFORMANCE DATE
15. Prior CG Vessels and POC for each
Required Docs:
Prior CG Vessel List (w/ cost and POC info)
Past Performance Reports
1. Any delays in delivery?
2. What % of work was from Growth? Reason for growth?
3. Where there any issues/problems with CFE/GFE?
4. Any conflicts associated with contract/personnel?
5. Any Contract Deficiency Reports issued by Contracting Officer?
6. Any Letters of Concern issued by Contracting Officer?
16. Prior Commercial Vessels (if new to CG work)
Required Docs:
Prior Vessel List (w/ cost and POC info)
Past Performance Reports
1. Any delays in delivery? Growth? Problems with CFE?
2. Any conflicts?
17. Prior CG Vessels of similar size and scope (Unless included in Item 15)
Required Docs:
Prior CG Vessel List (w/ cost and POC info)
Past Performance Reports
Note** When/if this information is captured and there is no history, recommend a MODERATE RISK assessment in this category and overall.
1. Does the Contractor have any past history working on similar (or larger) class of cutters/boat? If so, when?
2. Provide the POC and contract number for the above referenced contracts, (Contracting Officer, Port Engineer, and Engineering
Officer)
3. Were there any issues or delays associated with these contracts?
If so, explain.
Overall Evaluation: Risk overall is * High Moderate Low * Surveyor shall, in remarks above, provide a narrative
USCG SFLC QUALITY ASSURANCE (Rev. 03/2017) FOUO (When Completed) 8
PRODUCTION CAPABILITY
18. Production Quality Control Program
Required Doc:
QA/QC Program
1. Does the KTR have a written/documented QA/QC program IAW
SFLC STD Spec 0000 3.2.4?
2. Who monitors and ensures quality of work on each project? How often? It is documented on a form?
19. Projected Workload
Required Doc:
Projected Schedule during availability timeline
1. During the scheduled availability timeline, are there any other major projects?
2. How does the predicted workload compare to normal (heavy, average, light)?
20. Scheduling Flexibility 1. If necessary due to CG requirements or unforeseen circumstances, can the work be handled if it is moved either earlier or later, and by how much?
21. Performance Period Verification 1. Does the KTR believe the work-hours required for the spec are realistic for the availability window?
2. How many hours per shift, shifts per day, days per week?
3. Will over-time be required?
4. Do the Optional items make a substantial difference?
22. Availability of Supplies/Services 1. Are there any concerns of delay due to receipt for goods? Have any of the work items historically had problems?
2. Can KTR provide all items listed in Work Item “Temporary
Services”?
23. Graphical Planning Document
Required Doc:
Example of a Planning and Progress Chart
1. Does the chart address critical inspections?
Overall Evaluation: Risk overall is * High Moderate Low * Surveyor shall, in remarks above, provide a narrative
USCG SFLC QUALITY ASSURANCE (Rev. 03/2017) FOUO (When Completed) 9
TECHNICAL CAPABILITY
24. Gas Free Program or Confined Space Program
Required Doc:
Gas Free or Confined Space Program
Marine Chemist Certifications
Competent Person Certifications
1. Does KTR have a written Program? Does it address Competent
Person (CP) and Marine Chemist requirements?
2. Will a Marine Chemist be subcontracted (provide contact info)?
3. Are (CP) staffed?
4. How often does KTR train CP? OSHA Training?
25. Nondestructive Inspection (NDI) of welds
Required Doc:
NDI Written Programs
NDI Personnel Qualifications/Certification
1. Does the KTR have a written NDI Program?
2. Does KTR comply with AWS (SCWI or CWI) or ASNT
3. Are NDI personnel staffed or subcontracted?
4. If staffed; provide certifications, if not, provide contact information for NDI Company.
26. Painting Quality Assurance Program
Required Doc:
Paint Inspection Certifications (QP1/NACEIII)
QA Paint Manual-should list qualified individuals
SSPC Audit Letter
Instrument/Tool Calibration List(due at Arrival
Conference)
1. Does the KTR have a written Paint Program?
2. Are QP1 inspectors staffed/subcontracted? Provide
Certifications, Paint QA manual and SSPC Audit Letter.
3. If NACE III subcontracted, provide contact information. (The
Tech Rep shall neither be an employee of the Contractor, nor of any coating system manufacturer)
4. What media will be used for U/W paint removal?
27. Welding Program
Required Doc:
Welding Procedures Specification (WPS)
(AWS D1.1, AWS D1.2 and ASME Section IX)
Welders Performance Qualifications/Procedures
Qualification Record (PQR)
Welder Qualifications Continuity Record (last 2 years)
1. Does the KTR have a Written Welding Program?
ABS/AWS/NAVSEA/ASME/ASTM
2. What welding is required for this Specification?
Aluminum/Steel/HY/Pipe/Brazing
3. If AWS/ABS, are WPS Stamped?
4. If ABS; approved by ABS Office Houston SFLC IAW Std Spec
5. If NAVSEA; provide Annual Audit Letter from USN
6. Provide certifications with continuity records?
7. Will the majority of welding be subcontracted? If yes, how will oversight be maintained?
28. Dock Master Program
Required Doc:
Dock Master Resume
Docking Plan
1. Does the KTR have a formal/written docking plan?
2. Who is the dock master?
3. Provide a resume as per SFLC Std Spec 8634 requirements
(Qualification process and past experience).
4. How many dockings performed in the last 6 months? 12?
Overall Evaluation: Risk overall is * High Moderate Low * Surveyor shall, in remarks above, provide a narrative
USCG SFLC QUALITY ASSURANCE (Rev. 03/2017) FOUO (When Completed) 10
FACILITY CAPABILITIES
29. Capacity and Capability of Dry-Dock/Railway/Mobile Hoist
Required Doc:
Dry-Dock/Mobile Hoist /Crane Certification
1. What will be used to haul out CG Cutter?
2. Are all certifications current, signed by a PE, and in keeping with SFLC Std Spec 8634?
3. Is KTR listed in NAVARCH Database?
4. When is DD due to expire?
30. Pre-Award Dry-Dock Calculations 1. Calculations available?
2. Who will complete them?
31. Shop Capability, Equipment, Layout, Cleanliness, Office
Space
1. What shops does KTR have that will be used during the availability?
2. Any specialty equipment?
3. Are the shops clean and well organized?
4. Was the Hazardous Materials Storage Site organized? Were items labeled? Secured?
5. What office /berthing will be available to the CG crew?
32. Pier Facilities
Required Doc:
CG Facility Certification as per SFLC Std Spec 8634
1. Where will CG moor?
2. What services are available, i.e.
3. PW/FM/Sewage/compressed air/power (AMP/VT/Phase)?
4. If the Cutter/Boat will be on Blocks/Cradle, what substrate will it be on? Is it solid and homogeneous? Was it evaluated by PE and recorded on SFLC Std Spec 8634?
33. Yard Access from Land/Sea 1. Will the facility’s land access be controlled 24/7?
2. What security measures are available (guard/cameras)?
3. Can facility be locked from outside IAW SFLC Std Spec
0000 3.2.11.4?
4. Minimum water depth to and at moor (low tide)?
5. Minimum water depth in floating dock (low tide)?
34. Physical Plant Condition: 1. Is all major equipment well cared for and maintained?
Overall Evaluation: Risk overall is * High Moderate Low * Surveyor shall, in remarks above, provide a narrative
USCG SFLC QUALITY ASSURANCE (Rev. 03/2017) FOUO (When Completed) 11
Environmental Compliance for Shipyards Worksheet Description Docs Submitted
AIR MEDIA Yes No N/A In
Compliance
Non
Compliance
Remarks
35. Does the shipyard use more than 265 Gallons of marine paint per year?
If yes, the shipyard is required to have a Title V Air permit to be in compliance with the Clean Air Act.
If no, the shipyard is not required to follow the MACT.
If un known, then shipyard’s status will have to be determined.
36. Does the shipyard have a Title V Air Permit?
Required Docs: Title V Permit
37. If the shipyard has a Title V Air Permit, does the shipyard follow the Maximum Achievable
Control Technology (MACT) for Marine
Coatings IAW 40 CFR Part 63?
If yes, then shipyard is in compliance
38. If no, does the shipyard emit 25 tons of one
HAP or 100 tons of all HAPs in one year?
If yes, then shipyard is out of compliance with the Clean
Air Act
If no, then shipyard is not required to have a permit and in compliance
If un known, then shipyard’s status will have to be determined.
Volatile organic compound
(VOC) Hazardous Air
Pollutant (HAP)
39. Does the shipyard have an asbestos removal license IAW the Asbestos Model Accreditation
Plan (MAP)?
Required Docs: License
If yes, record license #/state
40. If shipyard does not have an asbestos license, do they use a contractor to remove asbestos?
If no, then the SOW should not include asbestos removals
If yes, then contractor’s license#/state
41. Does the shipyard have EPA Certified
Technicians to remove Ozone Depleting
Substances (ODS) or repair AC&R equipment
IAW 40 CFR Part 82?
Required Docs: License
If shown, then shipyard is in compliance
If none, the shipyard cannot work on AC&R equipment
If yes, record license #/state
USCG SFLC QUALITY ASSURANCE (Rev. 03/2017) FOUO (When Completed) 12
LAND MEDIA Yes No N/A In
Compliance
Non
Compliance
Remarks
42. Does the shipyard have an EPA ID# for
Hazardous Waste generation?
Obtained from EPA 8700-12B or HazWaste Manifest
Information can be verified on EPA Website
If no, then shipyard is out of compliance
If yes, enclose EPA Form or
Manifest
43. Does the shipyard have 2 copies of HazWaste
Manifests?
Required Docs: Manifest copies
If yes, the shipyard is in compliance If not provided, the shipyard is out of compliance with the Resource Conservation and Recovery Act
If yes, enclose Manifest
44. Has the shipyard filed a Notification of PCB
Activity with the EPA?
Required Docs: EPA 7710-53
If no, then the shipyard cannot store PCBs for disposal.
The SOW should not include PCB removals
45. Have shipyard show copies of manifests or bills of lading for asbestos shipments.
Required Docs: Manifests
If none can be found and removals have been conducted, then shipyard is out of compliance with the Clean Air Act
46. Is abrasive blast material used to remove paint?
Use of Silica blast grit is prohibited.
Specify Type:
47. If abrasive blast material is used, how is it disposed of?
Landfill or Recycle
Is media tested before removal?
48. If it is recycled, facility must have a blast material disposal permit. If it is sent to a landfill, provide the address.
Required Docs: Blast Material Disposal Permit or
Facility(ies) name and address for this year
49. Is a sub contractor used for all blasting? If so provide all contact information.
USCG SFLC QUALITY ASSURANCE (Rev. 03/2017) FOUO (When Completed) 13
LAND MEDIA Yes No N/A In
Non
Compliance
Remarks
50. Does the shipyard show an EPCRA Tier I or
Tier II Report from this year.
Required Docs: Tier I/II report
Stands for Emergency Planning and Community
Right-to-Know Act (EPCRA)
If yes the shipyard is in compliance
If no, then shipyard is out of compliance
51. Does shipyard have a Hazardous Materials
Tracking System?
If no, the shipyard could be out of compliance
WATER MEDIA Yes No N/A In
Non
Compliance
Remarks
52. Does the shipyard have a NPDES permit?
Required Doc: NPDES Permit
If yes, in compliance
53. If shipyard does not have a NPDES, do they have a Notice Of Intent with the State for the following;
a. General Storm Water
b. Sewage Waste Water
If no, shipyard is out of compliance
Note: If the shipyard does not have a NPDES permit, it cannot discharge cooling water from CG vessels while the vessel is out of the water.
54. How is run-off from water jetting and washing operations contained to prevent from entering ground, waterways, and storm & sewer systems?
(SFLC Std Spec 0000 Appendix B2.2.16.1.7)
55. How is hydro blast water treated?
On-Site or Off-Site
Allowed to drain in water system?
Written Plan? If so, Provide
56. If Hydro blast water is treated on-site, does
Shipyard have a NEPES permit?
(If yes, the permit should cover treatment)
(If no, the shipyard is out of compliance)
57. If Hydro blast is stored and treated off site, obtain manifests or bills of lading.
If none, then have shipyard give address of treatment facility (ies) for last year.
USCG SFLC QUALITY ASSURANCE (Rev. 03/2017) FOUO (When Completed) 14
WATER MEDIA Yes No N/A In
Non
Compliance
Remarks
58. Does the shipyard have a total above ground
Petroleum, Oils, and Lubricants POL storage capacity greater than 1,320 Gallons?
Containers 55 gallons and greater are counted.
If no, the shipyard is in compliance
59. If shipyards POL > 1,320 gals, does the shipyard have a Spill Prevention, Control and
Countermeasures Plan approved by the EPA.
Required docs: Spill Plan
If shown, the shipyard is in compliance.
If no, the shipyard is out of compliance.
60. Does shipyard transfer POL to/from vessels and has a total POL capacity greater than 42,000
Gallons?
If no, then shipyard is in compliance
61. If shipyard transfer POL to/from vessels and has a total POL capacity greater than 42,000
Gallons obtain
Required docs: Facilities Response Plan approved by EPA
If no, then shipyard is out of compliance
62. Does shipyard transfer POL to/from vessels that have capacities greater than 250 barrels
(10,500 Gal.) via fixed or mobile facilities transferring oil.
If no, then shipyard is in compliance
CG vessels over 175 foot fall into this category.
63. If shipyard transfers POL to/from vessels > 250 barrels (10,500 Gal.), obtain
Required docs: Spill Plan (Oil Response
Plan, Facility Response Plan IAW 33 CFR
154.1010) approved by the local Captain of the
Port.
(A current USCG Marine Safety Office (MSO) / Captain of the Port (COTP)-approved Facility Response Plan per
33 CFR Section 154.1017 will be considered acceptable in meeting these requirements) If shown, then shipyard is in compliance
If not shown, the shipyard is out of compliance
USCG SFLC QUALITY ASSURANCE (Rev. 03/2017) FOUO (When Completed) 15
COMPLIANCE CHECKLIST FOR CONTRACTOR’S PROPERTY CONTROL SYSTEM
REQUIREMENT YES NO N/A REFERENCE
A. MANAGEMENT
1. Has or will the contractor assign a Property Administrator to the contract to ensure that the requirements of FAR Part 45 and the contract requirements will be met?
B. CONTROL
1. For both the Government provided and Contractor Acquired Property, is there a system for:
(a) Recording the receipt of property?
(b) Recording the rejection of property?
(c) Recording the acceptance of property?
(d) Recording the property in the formal property account?
(e) Marking property?
(f) Recording and reporting overages?
(g) Recording and reporting damages?
2. Is there a system for providing a complete inventory schedule of all on hand materials to the Property Administrator of the Government-Owned property?
3. Is there a system or technique for locating any item of Government property within a reasonable time period after a request from the
Government?
4. Is there a system for the immediate identification and reporting of excess
(no longer needed) Government Property?
5. Does the contractor require that a physical inventory of Government
Property be made? If yes, circle how often it will be done:
Monthly Quarterly Semi-Annually Annually
6. Is there a system for the proper care and maintenance of Government
Property that will be stored for long duration contracts?
7. Will the property be stored in a secure area to prevent theft?
8. Will Government Property be provided to or acquired by subcontractors?
9. If the answer to 8. is “YES”, has the contractor included FAR Part 45, and the applicable property clauses in the subcontract(s)?
10. If the answer to 8. is “YES”, has the contractor reviewed and approved the Sub-contractor’s Property Control System to ensure that the Property
Control System Requirements covered by this checklist and the contract are met?
11. Other requirements (i.e.) list of unique requirements set forth in the contract)?
C. APPROVAL, CONDITIONAL APPROVAL, OR DISAPPROVAL
The system is recommended for: 1. Approval
2. Conditional Approval
(see attached discrepancies)
3. Disapproval
(see attached discrepancies)