This pre-solicitation notice describes a requirement for progressive structural inspection and depot level maintenance services for C-130H and C-130J aircraft. The U.S. Coast Guard Aviation Logistics Center intends to award an indefinite-delivery indefinite-quantity time and materials contract with firm fixed price contract line items to provide inspection, maintenance, and logistics support services. The contract will include labor hour task orders and require services such as progressive structural inspection, depot repairs, inspection extension, unscheduled depot level maintenance, field team support, parts procurement and management, aircraft storage, and engineering support. The period of performance includes one base year and four option years. Responses are due by March 2018 and award is anticipated for the same month. The notice provides labor categories, place of performance, delivery terms, and point of contact information.
Questions and Reponses
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_0004.pdf | ||
| Q&A_Amend_0004_RFP_70Z03818RH0000002.pdf | ||
| Amendment_0003_RFP_70Z038RH0000002.pdf | ||
| FBO_RFP70Z03818RH0000002_Page_33_Amend_0003.docx | DOCX document | |
| WD_2015-4405_Rev_6.pdf | ||
| FBO_RFP70Z03818RH0000002_Amend_0002.docx | DOCX document | |
| Amendment_0002_70Z03818RH0000002.pdf | ||
| FBO_ATTACHMENT_B_SOW_Amend_0002_70Z03818RH0000002.docx | DOCX document | |
| Q&A_Amend_0002_70Z03818RH0000002.doc | DOC document | |
| Amendment_0001_70Z03818RH0000002.pdf | ||
| ATTACHMENT_B_SOW_70Z03818RH0000002_Amend_0001.docx | DOCX document | |
| RFP70Z03818RH0000002_USCG_Amend_0001.docx | DOCX document | |
| ATTACHMENT_A_Schedule_70Z03818RH0000002.xlsx | XLSX spreadsheet | |
| SOW_Table_of_Contents.pdf | ||
| RFP70Z03818RH0000002_USCG_FBO.docx | DOCX document | |
| ATTACHMENT_C_PPQ_70Z03818RH0000002.doc | DOC document | |
| Wage_Determination_2015-4405_Rev_5_12-26-2017.pdf | ||
| ATTACHMENT_B_SOW_70Z03818RH0000002.docx | DOCX document |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions - Request for Proposal 70Z038RH0000002 USCG C-130H/J Progressive Structural Inspection (PSI)/Depot Level Maintenance (DLM)
| Question Number |
| RFP or SOW |
Pg Number Section/
Paragraph
| Question |
| Answer |
| 1 |
| RFP |
Page 32 Inquiries
Answers to questions may impact a Company's proposal; therefore, it would be beneficial to Offerors if USCG would provide answers to questions periodically, i.e., interim response on/about January 31st, by Amendment posted in FedBizOps.
Responses to questions will be posted periodically up until the cutoff date of February 15. USCG anticipates a high volume of questions at the beginning of the submission period and plans to begin publishing responses the week of January 15.
| 2 |
| RFP |
Factor 2, (1.2.1) Sub-factor A: subsection b,
| …Review of the document reveals there is no paragraph 1.2.1(a). Can the government clarify the requirements regarding the processes and procedures for implementing the critical items? |
| Sub-factor A: Planned Approach should be labeled 1.2.1. Refer to the submission requirements. See corrected copy of RFP attached to Amendment 0001. |
| 3 |
| SOW |
11.0 PAINT
| Can the government clarify whether the airport must meet the requirements of FAA Federal Aviation Regulation Part 139 Certification of Airports, Sub Part D, Operations? |
| The airport does not have to be FAA Part 139 certified, but does need to be compliant and maintain other certifications as specified in the SOW. See corrected copy of the SOW attached to Amendment 0001. |
| 4 |
| RFP |
1st paragraph It appears the government requirement is for the Offeror to send a PPQ to each reference for each contract submitted as a past performance contract. Can the government please clarify the requirements?
Does the Government expect two, no more than three, references for each individual contract or for the three contract references overall?
The Government expects two, no more than three, references overall, not two to three references for each individual contract. This applies to Prime and subcontractors.
| 5 |
| RFP |
Page 33-34
Proposal Submission Can the government clarify it is requiring Offerors to provide The Schedule of Supplies/Services as part of the Technical Volume or only include it in the Price Volume?
Offerors shall submit proposed pricing using the Schedule of Supplies/Services provided as Attachment A in the Volume II Pricing Proposal only. Pricing information should not appear in Volume I.
| 6 |
| RFP |
1.2.2, last bullet
| Can the Government clarify or more clearly define the requirement? |
| Explain what labor categories will be utilized and how they will be allocated to fully staff the backshops. |
| 7 |
| SOW |
Attachments 1, 2, 3 Does the government have an HC-130H/J Progressive Structural Inspection (PSI) and Depot Level Maintenance (DLM) Specification and if so, can it be provided to the Offerors?
Please provide the associated Depot Level Maintenance Procedure Cards (DMPC) for C-130H PSI, C-130J PSI, and PSI Extension Inspection (PEI).
DMPCs, PEI Cards, and Paint drawings will be made available by written (email) request to Victoria Kocher at victoria.h.kocher@uscg.mil.
Card decks and drawings are the property of the U.S. Coast Guard and may be used for proposal preparation only. Reproduction and distribution for any other use is strictly prohibited.
| 8 |
| SOW 5.2.5 |
Is it the government’s intent for Offerors to submit resumes for three C-130 Cell Supervisors and at least two qualified Structural Specialists?
Additionally, paragraph 5.2.5 of the SOW requires at least one Aircraft Lead Mechanic per aircraft in PSI/UDLM. Please clarify the number of Lead Mechanic resumes required to be submitted with the proposal.
Resumes should be submitted for at least the minimum number of personnel required for the labor category as specified in the SOW. RFP 1.2.2, bullet 2 - Offerors may propose a primary and an alternate for all Key Personnel.
Refer to SOW 1.0 Scope for the estimated number of aircraft expected to be in work at any one time.
| 9 |
| RFP |
1.2.1 para 2
| Will the government consider eliminating the integrated master schedule from the proposal page count thus ensuring Offerors deliver a comprehensive integrated master schedule containing the discrete tasks required to accomplish an evaluation of the Offeror’s methodology? |
| An integrated master schedule is excluded from the proposal page count. |
| 10 |
| RFP |
1.1.1 Last sentence
Can the government clarify its intent / the requirement when it states, “The information shall be prepared in a format consistent with the SOW …”?
The information should be presented in a logical order consistent with the sections described in the SOW.
| 11 |
| RFP |
Pricing Proposals
| Does the Government want CDs for either the Technical or Cost Volume? |
| No – The Volume II pricing proposal should be submitted as a hard copy and as an MS Excel file to the email address in the RFP. |
| 12 |
| SOW |
Attachment 10
| The Attachment was provided, however there is no instructions for a bidder to complete this form (DD 254) at time of proposal submission. If this is to be completed with the proposal submission, is this excluded from the page count? |
| The DD254 is not required at time of proposal submission. |
| 13 |
| SOW |
Para 2.2.1
| First induction is to be 120 days after award, is the preinduction inspection going to be adjusted for the first aircraft? If not, please provide additional clarity. |
| The pre-induction inspection will be the responsibility of USCG personnel if one is required prior to start of contract performance. |
| 14 |
| RFP |
Para. 1.2.2 b Is it the Government's intent to request a transition plan and schedule immediately following contract award?
If this is not the intent, will the Government please consider expanding the page count and incorporating a contract transition requirement into the Final RFP's instructions and associated evaluation factor?
Does the Government intend for Offerors to recover any Transition Costs through their Overhead?
Item 4) “acceptability of phase-in plan” is deleted. A formal transition/phase-in plan is not required. Wording is changed to: 4) the Offeror’s proposed procedures for implementing full process management, parts procurement, and training of personnel in ALC Instructions and Policy in the period in order to be fully staffed and operational by the date required in the contract. (No later than 90 days after award IAW the SOW)
| 15 |
| RFP |
Page 15 Clauses &
SOW Page 62
| Will the Government please confirm the required certification and correct the affected reference? (AS 9100 or ISO AS 9110) |
| The correct certification should read AS9110. |
| 16 |
| RFP |
Para. 3 – not included in page limitation
Will the Government please consider eliminating the QCP cited in Factor 1, Sub-factor B, from page count?
Quality Program - The RFP Requires that we submit a Quality Control Plan (QCP) and current ISO Certification. Would the Government please clarify that the QCP and ISO Certifications should be included as attachments (and exempt from the stated page-count?)
Quality Control Plans and ISO Certifications have been added to the list of items not included in the proposal page limitation. See revised SOW attached to Amendment 0001
| 17 |
| SOW |
Section 2.5
| Are contractor support engineers (structural, mechanical, electrical) needed locally to develop and submit non standard repairs and drawings, etc. or is a remote engineering support group acceptable? |
| No - The USCG retains all Engineering and Airworthiness authority for all action performed under the contract. |
| 18 |
| RFP |
1.2.2
| Will the current USCG PSI schedule be made available for this period of performance? |
| USCG currently has 3 aircraft scheduled for PSI and 1 aircraft scheduled for PEI for the base period of performance. Schedule is subject to change. Refer to SOW 1.0 Scope for the estimated number of aircraft expected to be in work at any one time. |
| 19 |
| SOW Attachments |
| Please provide paint drawings and schemes that detail required paint, stencils, and decals. (SOW Attachment 14) |
| See question 7. |
| 20 |
| RFP |
Page 33-34, 37
| The structure outlined in FAR 52.212-1 -- Instructions to Offerors - Commercial Items is inconsistent with the structure outlined in FAR 52.212-2 Evaluation - Commercial Items. The naming of sections do not correlate. Will the Government provide consistency between the structures to ensure full compliance of how the document should be submitted? |
| The structure outlined on pages 33-34 for Technical Proposals and Pricing Proposal states the sections required in each volume and correlates with the Factors contained in the list of Evaluation Factors. (ex: Volume 1, section b Technical Capability, should contain information pertaining to Evaluation Factor 1, Technical Capability and its sub-factors.) . Offerors should include information sufficient to enable an in-depth understanding and evaluation by the Government technical staff and to demonstrate the Offeror's ability to perform the required effort. |
21 cont.
RFP
Technical Proposals.
Can the Government clarify where they would like Subcontracting Plans, Quality Control Plan, ISO Certifications submitted - as an attachment to Volume I Technical Proposal or Volume II Price Proposal?
Where does the Government want the Subcontracting Plan, Safety and Health Program Plan, and Airworthiness And Required Certifications placed in the proposal response?
These items shall be submitted in Volume I. See revision on page 33.
| 22 |
| RFP |
FAR 52.245-1
SOW
Para. 19
| Request revision to the SOW to update the date for FAR 45.245-1 to January 2017 and delete reference to Alt 1 in its entirety. |
| Corrected the date of FAR 45.245-1 to (Jan 2017) and deleted Alt 1 reference on page 15 of the RFP and page 60 of the SOW. See revised RFP and SOW attached to Amendment 0001 |
| 23 |
| SOW |
Paragraph 2.5 This SOW paragraph refers to a fixed-price engineering hourly rate in the RFP Schedule.
Request the Government revise the Schedule to include a CLIN for engineering hourly support.
References to Engineering support have been deleted. There is no CLIN for Engineering hourly labor. See revised SOW attached to Amendment 0001.
| 24 |
| SOW |
Paragraph 5.5.2
| Request Government confirmation that the reference to "subcontractors" applies only to subcontractors that will or may have access to the installation. |
| Sentence revised to include only subcontractors that will have access to the USCG base or Government computer systems. |
| 25 |
| RFP |
| Does the Government intend to add FAR 52.217-8, Extension of Services to the solicitation? |
| No |
| 26 |
| RFP |
| Will title pages, table of contents, acronym lists be exempt from page count? |
| No |
| 27 |
| RFP |
Para 1.2.3
| RFP Section 1.2.3 encourages respondents to provide sample reports to satisfy the EVR requirements; would the government please confirm that these reports are exempt from page-count limitations? |
| See instructions for technical proposals on page 33 of the RFP. |
| 28 |
| SOW |
Para 22.0 The FAR defines “Subcontractor as “any supplier, distributor, vendor, or firm that furnishes supplies or services to or for a prime contractor or another subcontractor”. Will the Government define the term subcontractor in this context?
See Question 24
| 29 |
| SOW |
Para 22.0 Given that the prime contractor is ultimately responsible for the overall quality of all processes, can the Subcontractor be deemed AS 9110 certified as long as all subcontractor (specifically depaint/paint) are monitored through the Prime’s Quality Management System assuming the Prime is AS 9110 certified?
LRS is awaiting response from ALC Business Office Division.
| 30 |
| SOW |
Attachments 1 & 2 DMPC card Attachment 1 and 2 provide Revision Dates to each card.
What constitutes a deviation from these cards when cards are revised?
Who is responsible for performing the contract attachment mod as DMPC cards are updated, added or revised?
Will the DMPC card deck be frozen for each task order at time of CG-103 issue in order to print and plan the DMPC work cards?
The Contractor shall evaluate and determine if there is any impact to the time required to perform the revised card. A request for modification shall be provided to the COR. Any increase in labor hours will be negotiated, and if necessary, a modification will be issued by the Contracting Officer.
The card deck will not be frozen at time of task order issuance.
| 31 |
| SOW |
Para 11.1 & 11.2
| Currently no painting of large areas are permitting within the HMF, will there be provisions provided to accomplish these requirements? |
| Yes, painting of large areas will be performed at the direction of USCG. |
| 32 |
| RFP |
Attachment A-Schedule
| How will task order allocated hours be separated from DMPC and non-recurring repairs that require approval prior to repair? Will these non-recurring repairs be PCL driven and will the non-recurring workup sheet need to be separated by PLCs? |
| All tasks will be performed at the hourly labor rates in the Schedule and within the ceiling price on the task order. |
| 33 |
| SOW page 3 2nd bullet |
| For aircraft undergoing PSI where the induction date is the first full day the aircraft is at the paint facility, will the USCG extend the 220 days for PSI if they decide to bring the aircraft earlier than the scheduled date, and/or if they do not pick it up immediately after de-paint is complete due to flight crew availability? |
| No - Extensions will be considered on a case by case basis and authorized by the Contracting Officer. |
| 34 |
| SOW page 4 paragraph 2.3 |
| What are the defined requirements in meeting the 60 day report? |
| See para 2.2.2 - The primary deliverable of the inspection effort is the final report of all discrepancies noted on the 60-day PSI Inspection Report. |
| 35 |
| SOW page 4 paragraph 2.3 |
| Once the inspections are completed the Contractor shall commence with repairs …” Does this mean that repair work cannot begin until the inspections have been completed? |
| Repairs may be initiated concurrently during the inspection phase. |
| 36 |
| SOW page 8 – 2.11 second paragraph |
| Will engineering be required under this contract? |
| No –See Question 17 |
| 37 |
| SOW page 8 – 2.11 second paragraph |
| Will technical writers be required under this contract? |
| No |
| 38 |
| SOW page 8 – 2.11 second paragraph |
| Will kit development/design be required to be performed without USCG support? |
Has kit fabrication been included with in the provided hours?
Will a kitting area/space be provided?
No – USCG will be responsible for kit development and fabrication. Referenced paragraph has been deleted. See revised SOW attached to Amendment 0001.
| 39 |
| SOW page 8 paragraph 3.0 |
| Parts order approval will be made by LRS Engineering or Contracting Officer Representative? |
| The COR will have authority to approve parts orders. Parts procurement from vendors not already approved by ALC will be approved by USCG Engineering. |
| 40 |
| SOW page 10 paragraph 3.2 |
| Can you please clarify these capabilities to the position qualifications listed with the SOW in regards to 3.2 Storage, Stocking of inventory, Inventory Control, Issue, and Shipping of Supply Parts and Aeronautical Equipment, two of the capabilities listed in this section are not typically associated with this area. 1) planning and scheduling 2) ground support services including, but not limited to, refueling and servicing of aircraft. |
| The Contractor is responsible for providing personnel to comply with SOW 3.2 and will determine which labor category should perform the tasks. |
| 41 |
| SOW page 11 paragraph 4.0 |
| Will USCG provide required OEM C-130 (JEDMICS) drawings? If so, which STINFO (Standardized scientific Information) levels of drawings would be provided and which will not be provided? |
| Contractors cannot have access to B statement drawings. Use and access will be coordinated by USCG. |
| 42 |
| SOW |
| Will engine run training and testing be provided by USCG and reimbursable? |
| No-this is not reimbursable. |
| 43 |
| SOW page 13 |
| Will Foreign Object Damage Damage (FOD) walk-downs be reimbursable? |
| FOD walkdowns will be performed during normal work hours and be reimbursed under the hourly labor rates specified in the contract. |
| 44 |
| SOW page 33 |
| Given that the contractor is responsible for conducting business between the hours of 0645-0100 at ALC, Monday thru Sunday will the government be available to support multiple shifts? |
| Government support will be provided at the HMF for all approved work hours. |
| 45 |
| SOW page 34 |
| Prior to a task order being issued, can additional period of performance be negotiated for identified plant shut downs and holidays? |
| No – extended shutdowns for extenuating circumstances will be considered on a case by case basis. |
| 46 |
| SOW page 39 paragraph 9.2 |
| “If the Contractor requesting GFM which is not listed on Attachment 4 and the GFM is approved by the onsite COR, the cost to the Government of the supplied GFM will be given as credit to the Government on the next invoice cycle.” Will this statement only apply to FFP tasks or Warranty repairs where the contractor is responsible for all materials required not on attachment 4? |
| No – GFM not listed on Attachment 4 is provided at the Government’s discretion and reimbursement requirement will be considered on a case by case basis. |
| 47 |
| Attachment A - Schedule |
| Can the offeror assume that materials under the FFP CLINS will be reimbursed under CLIN 51 the same way as travel is being reimbursed under CLIN 52? |
| See SOW 3.1 |
| 48 |
| SOW paragraph 5.4.2 |
| Can the government clarify how Offerors should price a Project Manager? |
Offeror’s should price labor categories in accordance with description provided in the SOW.
| 49 |
| SOW paragraph 5.3 |
| Is it the Government’s intent for the Contractor to notify the Contracting Officer prior to a change of non-key personnel? |
Yes – See SOW 5.3
50 cont.
SOW
Various SOW paragraph 5.3.10 titled Sr. Mechanical Technician (Aircraft Mechanic II) refers to SOW paragraph 5.5.8 however, 5.5.8 does not exist
SOW paragraph 5.2.9 titled C-130 Electrical/Avionics Leader refers to SOW section 2.1.2 however section 2.1.2 does not exist.
SOW paragraph 5.3.13 titled Aircraft Painter, Sr. refers to SOW 5.5.12 however, 5.5.12 does not exist
SOW paragraph 19.0 titled GOVERNMENT FURNISHED PROPERTY refers to SOW 5.6.3 however, 5.6.3 does not exist.
SOW 5.5.8 is changed to SOW 5.3.8
SOW paragraph 5.2.9 refers to SOW paragraph 2.12
SOW 5.5.12 is changed to SOW 5.3.12
SOW 5.6.3 is changed to SOW 5.4.3
See corrected copy of the SOW attached to Amendment 0001.
| 51 |
| RFP |
Para 1.2.2a. bullet 4
| If the offerors must be fully staffed and operational NLT 90 days after award yet the first aircraft is planned for induction into PSI NLT 120 days after award, is the USCG transitioning all INW PSI's and UDLM work to the new contract at the 90 day point after award? |
| Yes |
RFP
Attachment A, Schedule SOW Attachment 1 The RFP includes 1,920 hour per employee as an estimate per year. Based on the Executive Order to allow for 56 per year of sick-time for Service Contract Act covered employees, shouldn’t the estimated hours be adjusted from 1,920 to 1,864 to reflect a more accurate number of billable hours per year per employee?
The quantity of productive work hours in ‘Column C’ of the file estimates 1,920 productive work hours per FTE. If a FTE is representative of an individual employee, this estimate is non-compliant with the Service Contract Act (“SCA”) requirements for holiday, vacation, and of E.O. 13706 regarding sick leave. SCA requires a contractor to offer SCA employees 27 to 37 days of combined leave per year. Assuming a work year of 2,080 total hours, and that employees utilize their annual sick leave, E.O., 13706, establishes the maximum number of regular time hours per employee to be range from 1,784 up to 1,864 hours. Total days of combined leave is made up of: (1) 7 days sick leave, (2) 10 days federal holiday, and (3) 10 to 20 days of vacation, dependent on years of service. Years of service is based on the number of years supporting the program, independent of the prime contractor.
The FTE estimated 1,920 hours per year stated on Attachment A will not change for proposal evaluation purposes. Offerors are reminded that the hours stated in the Schedule are estimates only.
| 53 |
| RFP |
Attachment A, Schedule In order to effectively price SCA-mandated vacation based on the amount of time an employee has been on the job, will the Government provide demographic data illustrating how many years each of the FTEs has been on the job? If not, will the Government provide an average per labor category currently on the job?
USCG is not able to provide the information.
| 54 |
| RFP |
| The Government requires that Offerors use Times New Roman 12 point font for Technical and Pricing Proposals. Can Offerors use a smaller font in the Technical Proposal for tables, artwork, and other graphics as is required for the Pricing Proposal? |
| Yes – See Additional Information heading added to page 34 of the RFP. This applies to volumes I and II. |
| 55 |
| RFP |
| Does the Government intend that PPQs be included in the proposal submittal? If so, where? |
| Yes |
| 56 |
| SOW |
Para 3.2
| RFP states all removed parts will be stored at HMF or with the aircraft. The next paragraph states there is not room for all contractor procured material and offeror must provide climate controlled, off site storage. Does this include only replacement items ordered or is it the intent to store all removed parts at an offsite location? |
| The offsite location will not be used for storage of parts removed from the aircraft. |
| 57 |
| SOW |
5.0
| 2nd paragraph states: The USCG will only furnish desk space at the HMF for Contractor personnel specified under SOW 5.4 Key Personnel and SOW 5.5 Non Key Personnel. Will the government correct these references to SOW 5.2 Key Personnel and SOW 5.3 Non Key Personnel respectively? |
| SOW 5.4 Key Personnel and SOW 5.5 Non Key Personnel is changed to SOW 5.2 Key Personnel and SOW 5.3 Non Key Personnel. See corrected copy of the SOW attached to Amendment 0001. |
| 58 |
| SOW |
Para 5.2
RFP Attachment A
| The number of key personnel for C-130 PSI Structural Specialist and C-130 Aircraft Lead Mechanic based on Full Time Equivalent hours in RFP Attachment A differ from the quantities given in Paragraphs 5.2.4 and 5.2.5 respectively. Which is the correct quantity to use for key personnel resumes? |
| Resumes should be submitted for at least the minimum number of positions stated in the SOW. Offerors may propose a primary and an alternate for all Key Personnel. |
| 59 |
| SOW |
Para 5.2 2nd paragraph, 2nd sentence states: “Key personnel shall meet the basic requirements of SOW 5.3 and the minimum requirements for each position specified below.”
Will the Government correct this SOW reference to 5.1?
Key personnel shall meet the basic requirements of SOW 5.3 reference is changed to SOW 5.1. This has also been corrected for the basic requirements referenced in 5.3 Non-Key Personnel. See corrected copy of the SOW attached to Amendment 0001.
| 60 |
| SOW |
Para 5.2.5
| Aircraft Mechanic I (SOW 5.5.8) and Aircraft Mechanic II (SOW 5.5.10) - References should be SOW 5.3.8 and 5.3.10. |
| Aircraft Mechanic I (SOW 5.5.8) and Aircraft Mechanic II (SOW 5.5.10) are changed to Aircraft Mechanic I (SOW 5.3.8) and Aircraft Mechanic II (SOW 5.3.10). See corrected copy of the SOW attached to Amendment 0001. |
| 61 |
| SOW |
Para 5.3.14
| The SOW states a requirement for a Flight Line Attendant (GSE). The description of duties labor maps more closely to a GSE Mechanic per the SCA. Does the government want a GSE Mechanic or a flight line attendant? |
| Title remains the same – Aligns with Ground Support Equipment Mechanic (23380). RFP clause FAR 52.222 fill- in (page 15) is corrected. |
| 62 |
| SOW |
Para 20.0
| Local commuting for work performed within a 50 mile radius of the USCG ALC, Elizabeth City, NC will not be reimbursed at the hourly labor rate or as a travel expense under FAR 31.205-46. Please verify that this restriction does not apply to personnel on travel status at this or any other location? |
| Personnel commuting while on travel status while performing work under this contract will be reimbursed in accordance with the contract. Travel to USCG Air Station Elizabeth City, or an off-site storage facility would not be considered travel status. |
| 63 |
| RFP |
Page 32-24
Far 52.212-1 Using a page size is 11x17 for graphics is referred to under the Pricing Proposal instructions only. Please verify that Offeror's may use an 11x17 page for graphics in the Technical Proposal as well?
The use of a smaller font size for graphics is designated under the instructions for the Pricing Proposal only. Please verify that Offeror’s may use a smaller Sans Serif font type (e.g. Arial) for graphics in the Technical Proposal as well.
The reference to page and font size has been added to the Technical Proposal instructions. See corrected copy of the SOW attached to Amendment 0001.
| 64 |
| RFP |
Pricing Proposals
| Per the instructions on page 34, please verify that the Pricing Proposal is only the Schedule of Supplies/Services (Attachment A) MS Excel file, and no other documentation. |
| A hardcopy of the completed Schedule of Supplies/Services (Attachment A), as well as, an electronic (emailed) copy of the pricing proposal completed in Microsoft Excel is the minimum requirement. |
| 65 |
| SOW |
Attachment 11 RAPIDGate
Program
| SOW, Attachment 11, RAPIDGate Program, on page 3 of 4, paragraph number 3, states that there is a fee for a company's registration in the program. Will the Government please provide the cost of the registration? Additionally, the attachment also states that the time from company approval to employee credentialing is approximately two weeks. What is the time for company approval from time of request through the COR? |
| USCG does not administer the RAPIDGate program and does not set the cost. Contact the program at the phone number provided on the information sheet. Employees whose place of work is ALC will be authorized to receive a DHS Common Access Card. |
| 66 |
| Wage Determination (“WD”) No.: 2015-4406, Revision No. 5, Effective 12/26/2017 |
| Will the USCG please provide length of service on the program for the current workforce covered by SCA? Wage Determination (“WD”) No.: 2015-4406, Revision No. 5, Effective 12/26/2017, provides the required vacation days for SCA employees based on length of service. This information is necessary for price realism, as the length of service of the workforce will have a material impact on indirect expenses. |
| The workforce on the incumbent contract is not covered by the Service Contract Labor Standards statute. |
| 67 |
| SOW |
Pages 27-28, 42, 56
| Where should ODC's be captured (PPE, uniforms, scaffolding, IT, supplies, work space, etc.) Will these be handled separately in Task Orders or mods for each aircraft? |
| These items are not considered direct costs and should be included in the fully burdened hourly labor rates as overhead. |
| 68 |
| None |
| During the Industry Day, the hangar appeared to have fall restraint reels or lines hanging from the Rafters. Who is responsible for the recalibration or replacement of these fall restraint lines should a Contractor employee experience a fall? |
| The Government is responsible for maintenance and inspections for the fall restraint system. |
| 69 |
| RFP |
Para 1.2.3b
| Will the Government please verify that all data and information, in addition to that included in electronic reports, provided for conversion/entry into USCG systems be Microsoft Office 2007 compatible? |
| Yes |
| 70 |
| SOW |
Para 1.0 &
Para 8.9.1
| Will the Government please verify that an aircraft Weight and Balance is not required following De-painting and prior to ferry to the HMF? |
| Weight and Balance is not required after De-paint. |
| 71 |
| RFP |
Clause FAR 52.228-15
| Should the Contractors and their subcontractors assume that the minimums identified in 48 CFR 28.307-2 and applicable under HSAR 3052.228-70 (Pg. 16 of 46) are sufficient or does the USCG require additional kinds and/or amounts? |
| The USCG does not require any additional kinds and/or amounts other than those stated in the applicable clauses. |
| 72 |
| RFP |
HSAR 3052.247-72
| On page 16 of 46 HSAR 3052.247-72 Lists F.O.B as Destination, inferring Contractor responsibility for aircraft until return from paint to the aircraft home base. SOW Section 7.2, however, puts responsibility on the USCG. Should contractors assume that the SOW or Solicitation document is correct? |
| Final delivery is defined as acceptance of the aircraft documented in a signed Form DD250. Signature will normally take place at USCG ALC, the place of performance and considered Destination. |
| 73 |
| SOW |
Para 5.8 Will the Government provide necessary personnel to ensure work stoppage is avoided during night shift hours?
USCG will provide Government oversight for Contractor personnel if night shift hours are implemented.
| 74 |
| SOW 9.2 para. 2 |
| SOW 5.8 states, “…Contractor employees shall work the same hours/day/shift as those of the branch or shop supported at ALC within established hours of operation unless otherwise specified in the task order...” What circumstances dictate replenishment vs. non-replenishment? |
| No answered - “Replenishment” is not defined. |
| 75 |
| SOW 13.3 |
| PSI Inspection Report - Will this report be Contractor developed, or will the Government provide a form or template? |
| Contractor developed approved by the COR. |
| 76 |
| SOW |
Para 9.1
| A reference is made to “components listed in Attachment 3.(See SOW 3.0)” Shouldn’t the reference be made to Attachment 4? SOW 3.0 also makes reference appropriately to Attachment 4. |
| The para 9.1 reference is changed to SOW Attachment 4. See corrected copy of the SOW attached to Amendment 0001. |
| 77 |
| RFP |
Section 1.4
| The RFP requires we provide terms and conditions for Warranties within Factor Would the Government please confirm that respondents can include the Warranty terms outside of page-count requirements? |
| No – include in page count. |
| 78 |
| 11.3.2 & |
11.3.3
Is it the government’s intent to re-seal the aircraft following stripping and prior to the transport of the aircraft to HMF for PSI where the wings and other structural components may be removed as it appears the SOW is directing?
Any resealing required would be performed at the ALC HMF.