QUESTIONS AND ANSWERS 2.docx
DOCX document 14 KB Posted
- Solicitation number
- 70US0920Q70090163
View the file
Other files
| File | Type | Posted |
|---|---|---|
| QUESTIONS AND ANSWERS 4.docx | DOCX document | |
| QUESTIONS AND ANSWERS 3.docx | DOCX document | |
| Amended solicitation_70US0920Q70090163.pdf | ||
| QUESTIONS AND ANSWERS 1.docx | DOCX document | |
| Sol_70US0920Q70090163_approved.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS AND ANSWERS 2
AK-47 and Parts
1. The solicitation states under Section B (Product samples) that the rifles (3ea) must be delivered by June 1st. Considering the compressed timeline of this solicitation, can accessories such as the removable blank only barrel assembly developed for this solicitation, is there the opportunity to deliver accessories past the June 1 timeline.
Answer:
Due to the need for product samples, the solicitation due date will be extended to 1 July 2020.
2. Are the three product samples rifles and 15 magazines to be delivered on June 1st purchased by the government? If so, what are the payment terms?
Answer:
Reference ‘Offerors Instructions’ portion of the solicitation.
Submitted sample rifles/items will not be purchased by the Government, before nor at conclusion of the Testing and Evaluation phase. All sample rifles/items will “be returned at the offeror’s request and expense”.