NEW 1 UNITS FEMA HOUSE MISCELLANEOUS COST BREAKDOWN FORM.xlsx

XLSX spreadsheet 22 KB Posted

Attached to
PHC Housing Construction -Saipan
Solicitation number
70FBR922R00000004
Issued by

About this file

This document contains a cost breakdown form and contract breakdown for the construction of FEMA housing in Saipan, CNMI. The cost breakdown form lists miscellaneous costs for a project to construct one new FEMA house, including items such as design civil works, special inspection, quality assurance testing, surveying, permitting, material and labor cost increases due to COVID-19 and fuel prices. The contract breakdown specifies the contract amount for the construction of two new FEMA houses under contract number 70FBR922R0000004, awarding fixed prices for construction of homes, key personnel, and profit, as well as general and administrative costs, equipment, and miscellaneous costs itemized in the cost breakdown form. The related federal contract opportunity posting is seeking to procure the construction of one to six housing projects in Saipan through a best value trade off solicitation. Interested small businesses located in CNMI must be licensed for residential construction and submit proposals by August 8, 2022 for consideration by the Federal Emergency Management Agency Region 9.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Miscellaneous

PROJECT: CONSTRUCTION OF FEMA 1 NEW HOUSES PROJECT, SAIPAN, CNMI
SUBJECT: MISCEALLANEOUS COST BREAKDOWN

Item no. Description Qty. Unit Unit Cost Amount Remarks

ADESIGN CIVIL WORKS1.00lot$ - 0$ - 0
BSPECIAL INSPECTOR1.00lot$ - 0$ - 0
CQUALITY ASSURANCE TESTING1.00lot$ - 0$ - 0
DSURVEYING & AS-BUILT WORKS1.00lot$ - 0$ - 0
EPERMITING1.00lot$ - 0$ - 0
FMATERIALS INCREASE DUE TO COVID -19 & FUEL INCREASE1.00lot$ - 0$ - 0
GLABOR INCREASE DUE TO CW-1 RATE INCREASE1.00lot$ - 0$ - 0
HSITE CONDITION ( ARCHEOLOGICAL )1.00lot$ - 0$ - 0
ISHIPPING1.00lot$ - 0$ - 0
J5% BGRT1.00lot$ - 0$ - 0

Total Cost $ - 0

Contract Breakdown

PROJECT: CONSTRUCTION OF FEMA 2 NEW HOUSES PROJECT, SAIPAN, CNMI
CONTRACT NO. 70FBR922R0000004
SUBJECT: FEMA CONTRACT AMOUNT BREAKDOWN
CLINDESCRIPTIONQTYUNITRATEAMOUNT
CLIN 0001ACONSTRUCTION OF 1 HOMES1LS$ - 0$ - 0
CLIN 0001BKEY PERSONNEL FOR 1 HOMES1LS$ - 0$ - 0
CLIN 0001CPROFIT FOR THE CONSTRUCTION OF 1 HOMES1LS$ - 0$ - 0
CLIN 0002MISCELLENAEOUS
AG&A1LS$ - 0$ - 0
BEQUIPMENT1LS$ - 0$ - 0
CMISCELLENAEOUS (from GPPC's Cost Breakdown worksheet)
DESIGN CIVIL WORKS$ - 0
SPECIAL INSPECTOR$ - 0
QUALITY ASSURANCE TESTING$ - 0
SURVEYING & AS-BUILT WORKS$ - 0
PERMITING$ - 0
MATERIALS INCREASE DUE TO COVID -19 & FUEL INCREASE$ - 0
LABOR INCREASE DUE TO CW-1 RATE INCREASE$ - 0
SITE CONDITION ( ARCHEOLOGICAL )$ - 0
SHIPPING$ - 0
5% BGRT$ - 0
SUB-TOTAL C$ - 01LS$ - 0$ - 0

TOTAL CONTRACT AMOUNT $ - 0