North Yard Storage Electrical Infrastructure Project Special Provisions

This document comprises special provisions for the North Yard Storage Electrical Infrastructure Project (Project No. 269-2026-2033), a re-bid project managed by the City of Charlotte for the North Yard Storage facility. The special provisions cover twelve detailed specification sections addressing all electrical infrastructure components required for the facility, which will function as a secured storage yard with access control, security lighting, CCTV cameras, fencing, and power supply capable of providing climate control measures. The scope encompasses closeout procedures, electrical system general requirements, conductors and cables, supporting devices, hangers and supports, electrical boxes, raceways and boxes, electrical distribution panels, grounding and bonding, tags and locks, and underground duct work. All work must comply with the North Carolina Building Code (incorporating the 2020 National Electrical Code), NFPA 70 requirements, and applicable NEMA, UL, and NECA standards. Materials specified include copper conductors rated for wet locations, schedule 40 PVC conduit, cast aluminum or galvanized steel electrical boxes, and equipment listed by Underwriters Laboratories or equivalent testing agencies.

The specification requires all costs associated with work to be incidental to the electrical infrastructure contract with no separate measurement or payment for individual sections. All materials must be new, premium name-brand U.S. components with full UL traceability and certification; counterfeit components are prohibited and must be replaced at the contractor's expense. Contractor submittals must include manufacturer pre-approval within 30 to 60 days after Notice to Proceed, complete technical data, shop drawings, and qualification data for installation supervisors and field inspectors. Pre-installation requirements include site surveys, verification of field measurements, and coordination with other trades, while post-installation obligations include comprehensive testing (ground resistance, insulation resistance, continuity), final cleaning, repair of defects, and delivery of marked-up project record documents prior to substantial completion. Ground resistance testing must not exceed 25 ohms, and all grounding connections must be exothermically welded in accordance with manufacturer specifications, with additional ground rods installed if necessary to meet resistance requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No. 269-2026-2033 North Yard Storage Electrical Infrastructure Project Re-Bid

SPECIAL PROVISIONS

August 22, 2025

CONTENTS

SP-01 SECTION 01 77 00 CLOSEOUT PROCEDURES

SP-02 SECTION 26 01 01 ELECTRICAL SYSTEM GENERAL

SP-03 SECTION 26 05 19 CONDUCTORS AND CABLES

SP-04 SECTION 26 05 29 SUPPORTING DEVICES

SP-05 SECTION 26 05 30 HANGERS AND SUPPORT FOR ELECTRICAL SYSTEMS

SP-06 SECTION 26 05 33 ELECTRICAL BOXES

SP-07 SECTION 26 05 34 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

SP-08 SECTION 26 24 16 ELECTRICAL DISTRIBUTION PANELS

SP-09 SECTION 27 00 01 REFERENCES AND STANDARDS

SP-10 SECTION 27 05 26 GROUND AND BONDING

SP-11 SECTION 34 42 66 TAGS, LOCKS, AND KEYS

SP-12 SECTION 34 42 69 UNDERGROUND DUCT WORK

North Yard Storage Electrical Infrastructure Project

Special Provisions 2

SP-01 SECTION 01 77 00 CLOSEOUT PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following:

1. Substantial Completion procedures.

2. Final completion procedures.

3. Warranties.

4. Final cleaning.

5. Repair of the Work.

1.2 RELATED SECTIONS

Not Used.

1.3

ACTION SUBMITTALS

1.4

CLOSEOUT SUBMITTALS

1.5

MAINTENANCE MATERIAL SUBMITTALS

A. Schedule of Maintenance Material Items: Specified in other sections.

1.6 SUBMITTAL OF PROJECT WARRANTIES

A. Time of Submittal: Submit written warranties on request of City's Representative for designated portions of the Work where commencement of warranties other than date of Substantial Completion is indicated, or when delay in submittal of warranties might limit City's rights under warranty.

B. Organize warranty documents into an orderly sequence based on the table of contents of Project

Manual.

1. Warranty Electronic File: Scan warranties and bonds and assemble complete warranty and bond submittal package into a single indexed electronic PDF file with links enabling navigation to each item. Provide bookmarked table of contents at beginning of document.

C. Provide additional copies of each warranty to include in operation and maintenance manuals.

PART 3 - EXECUTION

3.1 FINAL CLEANING

A. General: Perform final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

B. Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean each surface

Special Provisions 3 or unit to condition expected in an average commercial building cleaning and maintenance program.

Comply with manufacturer's written instructions.

1. Complete the following cleaning operations before requesting inspection for certification of

Substantial Completion for entire Project or for a designated portion of Project:

a. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.

b. Sweep paved areas broom clean. Remove petrochemical spills, stains, and other foreign deposits.

c. Rake grounds that are neither planted nor paved to a smooth, even-textured surface.

d. Remove tools, construction equipment, machinery, and surplus material from Project site.

e. Remove snow and ice to provide safe access to building.

f. Clean exposed exterior and interior hard-surfaced finishes to a dirt-free condition, free of stains, films, and similar foreign substances. Avoid disturbing natural weathering of exterior surfaces. Restore reflective surfaces to their original condition.

g. Remove debris and surface dust from limited access spaces, including roofs, plenums, shafts, trenches, equipment vaults, manholes, attics, and similar spaces.

h. Sweep concrete floors broom clean in unoccupied spaces.

i. Remove labels that are not permanent.

j. Wipe surfaces of mechanical and electrical equipment and similar equipment. Remove excess lubrication, paint and mortar droppings, and other foreign substances.

k. Clean light fixtures, lamps, globes, and reflectors to function with full efficiency.

l. Leave Project clean and ready for occupancy.

3.2 REPAIR OF THE WORK

A. Complete repair and restoration operations before requesting inspection for determination of

Substantial Completion.

B. Repair or remove and replace defective construction. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment. Where damaged or worn items cannot be repaired or restored, provide replacements.

Remove and replace operating components that cannot be repaired. Restore damaged construction and permanent facilities used during construction to specified condition.

1. Remove and replace chipped, scratched, and broken glass, reflective surfaces, and other damaged transparent materials.

2. Touch up and otherwise repair and restore marred or exposed finishes and surfaces. Replace finishes and surfaces that that already show evidence of repair or restoration.

a. Do not paint over "UL" and other required labels and identification, including mechanical and electrical nameplates. Remove paint applied to required labels and identification.

3. Replace parts subject to operating conditions during construction that may impede operation or reduce longevity.

4. Replace burned-out bulbs, bulbs noticeably dimmed by hours of use, and defective and noisy starters in fluorescent and mercury vapor fixtures to comply with requirements for new fixtures.

Special Provisions 4

PART 4 - MEASUREMENT AND PAYMENT

4.1 GENERAL

A. Work included in this Section shall be incidental to Work of technical Sections in Divisions 26 through

34 and will include Contractor's means and methods with no separate measurement and payment.

4.2 MEASUREMENT

A. There will be no separate measurement or payment for items listed below. All costs associated with this Section, including time, equipment, labor, overhead, profit, and material shall be considered incidental and included in the Work of technical Sections in Divisions 26 through 34.

4.3 PAYMENT

A. Payment for the work of this Section will be incidental to Work of technical Sections in Divisions 26 through 34.

4.4 PAYMENT ITEMS

Not Used

END OF SECTION 01 77 00

Special Provisions 5

SP-02 SECTION 26 01 01 ELECTRICAL SYSTEM GENERAL

A. This section includes the general requirements for the electrical work required at the North Yard Storage Facility.

Not used

1.3 REFERENCES

A. Section 27 00 01 - REFERENCES AND STANDARDS

B. NCBC: North Carolina Building Code

1.4 SUBMITTALS

A. Submittal of Shop Drawings, Product Data, and Samples will be accepted only when submitted by the

Contractor. Data submitted by subcontractors and material suppliers directly to the City’s Representative will not be processed.

B. Submit Product Data for specified materials and equipment, regardless of whether specific manufacturers and models or only general design requirements and reference standards are indicated.

C. Submit drawings of any other materials or equipment requiring filing or coordination with other trades, as well as any operating equipment specified elsewhere.

D. Project Record Documents:

1. Provide project record documents associated with the work for relevant provisions of these specifications.

2. Throughout progress of the electrical work, maintain an accurate record of changes in the contract documents that apply to the work completed.

3. Delegate the responsibility for maintenance of project record documents to one person on the Contractor's staff as approved by the City’s Representative.

4. Accuracy of Records

a. Thoroughly coordinate changes within the Project Record Documents, making adequate and proper entries on each page of specifications and each sheet of drawings and other documents where such entry is required to show the change properly.

b. Accuracy of records shall be such that a future verification of items shown in the contract documents may rely reasonably on information obtained from the approved project record documents.

2. Maintain the job set of project record documents completely protected from deterioration and from loss and damage until completion of the Work and transfer of all recorded data to the final edition of project record documents.

Special Provisions 6

3. Project Record Documents (Final Edition)

a. The purpose of the final edition of the project record documents is to provide factual information regarding all aspects of the work, both concealed and visible, to enable future modification of the work to proceed without lengthy and expensive Site measurement, investigation, and examination.

b. Deliver one complete set of marked-up Contract Documents, containing all of the above record information, to the City’s Representative prior to the date of substantial completion.

1.5 SYSTEM DESCRIPTION

1.6 QUALITY ASSURANCE

A. Testing shall show the proper functioning of all detection, alarm, and signaling equipment. Wiring shall be tested for proper connections, short circuits, and grounding using suitable testing instruments.

Lubrication of all rotating equipment and direction of rotation of all motors shall be checked.

PART 2 - PRODUCTS

2.1 MATERIALS

A. As specified in individual specification sections.

2.2 FABRICATION

A. As specified in individual specification sections.

2.3 INSPECTION AND TESTING

A. All electrical equipment shall bear approval labels from Underwriter’s Laboratories (UL) or other testing firm acceptable to the authority having jurisdiction where certification or listing is furnished for the particular type of equipment.

2.4 DELIVERY, STORAGE, AND HANDLING

A. Accept and store equipment and materials on site and inspect for damage, unless off-site storage is authorized in writing. Protect from corrosion and entrance of debris by storing above grade. Provide appropriate covering to protect stored equipment from damage and exposure to weather.

B. Protect all equipment against damage during transit and storage. All equipment shall be braced, blocked, and tied down to prevent distortion or other damage during transportation.

C. All equipment shall be delivered to the worksite with specified factory finish. If the finish is damaged in transit, handling, or installation, it shall be finished to present a neat workmanlike appearance to the satisfaction of the City’s Representative.

D. Deliver products to the Work site properly identified with names, model numbers, types, grades, compliance labels, and similar information needed for distinct identification.

Special Provisions 7

E. Coordinate deliveries of materials and equipment to minimize Work site congestion. Limit each shipment of materials and equipment to the items and quantities needed for efficient flow of installations.

2.5 WARRANTY

A. Comply with the requirements specified in Section 01 77 00 - CLOSEOUT PROCEDURES for administrative and procedural requirements pertaining to warranties.

B. Refer to individual specification sections for specific warranty requirements.

C. Provide complete warranty information for each item including:

1. Product or equipment,

2. Date of beginning of warranty or bond,

3. Duration of warranty or bond,

4. Addresses, telephone numbers, and procedures for filing a claim and obtaining warranty services.

3.1 GENERAL

A. All Work shall conform to the North Carolina Building Code (NCBC), its adopted subcodes, and their referenced standards, whether or not specified herein, including, but not limited to the following:

1. NCBC Electrical Subcode, (2020 NEC, as amended).

2. National Electrical Manufacturer’s Association (NEMA) standards.

3. Listing requirements of Underwriter’s Laboratories (UL) or other testing firm acceptable to the authorities having jurisdiction.

4. National Electrical Contractor’s Association (NECA) Standard of Installation.

B. Specific requirements of the NCBC and its adopted subcodes shall supersede conflicting requirements of other documents specified herein, except that whenever Contract documents require materials, workmanship, arrangements, or construction of a higher standard or larger size than is required by codes and regulations, the Contract documents shall take precedence.

C. Provide products that are compatible within systems and other connected items.

D. Sequence, coordinate, and integrate installation of electrical materials and equipment for efficient work flow.

E. Arrange for chases, slots, and openings to allow for electrical installations.

F. Coordinate the installation of required supporting devices and sleeves to be set in cast-in-place concrete and other structural components as they are constructed.

G. Coordinate the cutting and patching of components to accommodate the installation of electrical equipment and materials. Patching shall be performed by the trade most proficient at repairing the particular materials and/or surfaces damaged.

Special Provisions 8

H. Data indicated on the Drawings and in these Specifications are as exact as could be secured, but their absolute accuracy is not warranted. The exact locations, distances, levels, and other conditions will be governed by actual construction and the drawings and specifications shall be used only for guidance in such regard.

I. Where items such as boxes, switches, and control panels are not specifically located on the drawings, locate as determined in the field by the City’s Representative. Where such items are installed without such specific direction, relocate as directed by the City’s Representative and at the full expense of the Contractor.

J. Make connections to existing facilities in accordance with details as shown or as approved by the City’s

Representative. Where material specified under this contract differs from material in place, provide adapters, dielectric fittings, or special connectors as required. Use the requirements of applicable codes and recommendations of material manufacturers as a basis for determining exact type of adapters and fittings to be provided under this contract.

K. Connect new work provided under this contract to work installed under other contracts or required for equipment furnished by other contractors. Make all required connections of this contract to work by others in a proper and workmanlike manner. Refer to the drawings and specifications for other contracts as referenced.

L. Existing Utilities and Temporary Services for Construction

1. Verify the location and capacity of existing utility services pertaining to work required.

2. Provide temporary services in strict accordance with the provisions of these specifications.

M. The Contractor shall be responsible for obtaining markouts (utility locations), permits, and approvals from the utility company and any other authorities having jurisdiction. The Contractor shall pay any fees required by the utility company.

N. If it is determined that, in order to make proper connections to existing conduits, support systems, and structures, existing facilities must be altered, make such alterations as approved and directed by the City’s Representative, using materials compatible with existing materials and as approved.

1. Coordinate work to minimize cutting and patching work.

2. Prior to cutting or coring, submit a written request to the City’s Representative for permission to proceed with cutting.

3. Perform cutting and demolition by methods which will prevent damage to other portions of the work and provide proper surfaces to receive installation of new work and/or repair.

4. Perform fitting and adjusting of products to provide finished installation complying with the specified tolerances and finishes.

5. The contractor shall provide all core-drilling of holes. Where sleeves and/or blockouts are required, they shall be cut or provided by the contractor at locations required. Upon completion of this work or as work progresses, make all repairs and do all patching required as a result of work under this contract. All patching shall be performed in a manner that will restore the surrounding work to its original condition to the satisfaction of the City’s Representative.

6. Where openings are cut through masonry walls, provide lintels or structural supports to protect the remaining masonry. Adequate support shall be provided during the cutting operation to prevent any damage to the affected masonry.

Special Provisions 9

3.2 PRE-INSTALLATION

A. Prior to the initiation of any work, a field inspection of the existing electrical system shall be performed by the Contractor. The inspection shall pertain to all electrical wiring that is relevant to the Work specified herein. All findings shall be recorded and submitted to the City’s Representative.

B. Verify that field measurements are as shown on the Drawings. No additional compensation will be allowed because of differences between work shown on the drawings and actual dimensions and distances at the Work site.

C. Verify routing and termination locations of circuits prior to rough-in.

D. Cooperation with other trades:

1. The Contractor shall cooperate with all other trades whose work might in any way affect his installation and arrange his work within all practical limits so that there will be no interference with the work of the various trades.

2. Where the work of his trade is concealed, the Contractor shall be responsible for advance planning of his installation to prevent projections beyond finished surfaces.

3. The Contractor shall assume full responsibility for damage caused to the work of other trades during the execution of this Contract.

4. Although such work is not specifically indicated, furnish and install all supplementary or miscellaneous items, appurtenances and devices incidental to or necessary for a sound, secure, and complete installation.

5. Coordinate accepted equipment changes from those scheduled or specified with other trades affected. Additional compensation to other trades for equipment changes are the responsibility of the contractor making the change.

3.3 INSTALLATION

A. Coordinate the installation of electrical materials and equipment with structural components and mechanical systems.

B. Where mounting heights are not detailed or dimensioned, install electrical services and overhead equipment to provide the maximum headroom possible.

C. Where electrical items are shown in conflict with locations of structural members and other equipment, include labor and materials required for extensions, offsets, and supports to clear the encroachment.

D. Install electrical equipment to facilitate maintenance and repair or replacement of electrical components. As much as practical, connect equipment for ease of disconnecting, with minimal interference with other installations.

E. Upon completion of the work and prior to testing and final inspection, thoroughly clean all exposed portions of the electrical systems; removing all traces of soil, labels, grease, oil, and other foreign material; and using only the type of cleaner recommended by the manufacturer of the item being cleaned.

Special Provisions 10

3.4 FIELD QUALITY CONTROL

A. Before an application for final acceptance of the Electrical Work will be considered, all tests deemed necessary to show proper execution of the Work or required by code shall be performed by the Contractor at his full expense and witnessed by the City’s Representative. Scheduling of all testing procedures shall be submitted to the City’s Representative for approval.

B. Where equipment supplied by other trades is energized, controlled, or otherwise made operative by electric wiring systems, the testing that will prove proper functional performance shall be conducted specifically by the trade responsible for the mechanical equipment.

C. Perform all tests and inspections of equipment, material, and wiring to determine whether all provisions of these Specifications and Drawings have been fulfilled. Wiring shall be tested for proper connections, short circuits, and grounds using suitable testing instruments. Lubrication of all rotating equipment and direction of rotation of all motors shall be checked.

4.1

A.

GENERAL

No separate measurement or payment will be made for the Work required under this Section. Cost for providing Work of this Section shall be incidental to Communications Work.

4.2 MEASUREMENT

A. No specific measurement will be made for the Work of this Section as specified herein and as shown on the Contract Drawings.

4.3 PAYMENT

A. Payment for the Work of this Section will be included in Work identified as Communications.

END OF SECTION 26 01 01

Special Provisions 11

SP-03 SECTION 26 05 19 CONDUCTORS AND CABLES

1.1

SUMMARY

This Section specifies requirements for design, procurement, installation, and testing of conductors and cables for the electrical work being done at the North Yard. This section addresses copper cabling.

1.2 RELATED SECTIONS

A. Section 26 01 01 - ELECTRICAL (GENERAL)

B. Section 27 00 01 - REFERENCES AND STANDARDS

1.3 REFERENCES AND STANDARDS

Not Used.

1.4 SUBMITTALS

B. The Contractor shall submit specifications for all required types of conductors and cables used in the North Yard Storage Project for Engineer approval. This shall include UL listing (or the appropriate governing standards organization) information.

C. Submittals

1. Product Data: For each type of product.

2. Shop Drawings

a. System Labeling Schedules: Electronic copy of labeling schedules that are part of the cabling and asset identification system.

b. Cabling administration drawings and printouts.

c. Wiring diagrams to show typical wiring schematics.

D. Informational Submittals

1. Qualification Data: For installer, qualified layout technician, installation supervisor, and field inspector.

2. Source quality-control reports.

3. Field quality-control reports.

A. Design Requirements

1. The Contractor shall submit, for review and approval by the City’s Representative, specifications for all Conductors and Cables required.

Special Provisions 12

B. Performance Requirements

1. The Contractor shall provide and install all cabling and wiring, connectors, tagging, labeling, cable fasteners and grounding required by the physical cabling system for all requirements.

A. All materials used in the construction shall be new and selected as the best available for the intended purpose, considering long life and best Engineering practices. Only heavy-duty industrial components rated to operate within the applicable temperature ranges and other environmental conditions shall be used.

B. All cables shall be manufactured by premium name-brand U.S. companies.

C. Use of any counterfeit cable shall not be permitted. The typical deficiencies include, but are not limited to, the following sub-standard substitutions:

1. No aluminum, copper-clad aluminum or copper-clad steel conductors, instead of pure copper conductors.

2. No jackets made with less insulating materials than claimed.

3. No cable constructed with reduced conductor size from stated American Wire Gauge (AWG).

4. No connectorized cables with gold flash on contacts instead of 30 or 50 micro-inches of gold.

5. False UL labeling.

D. The contractor is responsible for replacing any counterfeit or bogus system components, at the

Contractors expense.

E. All cabling and wiring shall be UL listed (or appropriate governing standards organization).

F. Contractor shall maintain UL traceability from the manufacture for each cable type used. To ensure traceability:

1. If the UL label is affixed to outer wrapping, immediately copy for record and staple or otherwise affix the tag with the UL label to the wire reel upon removal of the wrapping.

2. Reject spools of wire that do not have UL labels attached during incoming inspection.

3. Communicate wire traceability requirements to personnel handling wire.

G. Standards Compatibility. Contractor's materials, design, installation, and testing shall comply with all applicable References and Standards as listed in Section 27 00 01 - REFERENCES AND STANDARDS.

H. Associated Electrical Components, Devices, and Accessories:

1. Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use.

I. Comply with NFPA 70.

A. General Performance Requirements - Conductors and Cabling systems

Special Provisions 13

1. The Contractor shall ensure that the system components conform to the performance requirements, as defined in the Contract Documents.

B. Conductors and Cabling Subsystems

1. General

a. Conductors, bare or insulated, shall be all copper construction.

b. Connectors used with conductors shall be rated for connecting copper conductors.

c. All cables used for outdoor or underground applications shall be rated for use in wet conditions, i.e. typically 75° C, rated for wet locations, based upon the actual insulation type.

d. All cables used for indoor applications shall be rated for use in dry conditions, i.e.

typically 90° C, rated for dry locations, based upon the actual insulation type.

e. For the applications on this project the majority of all wiring shall be rated for outdoor, wet locations.

f. Dual-rated cables are acceptable, use NEC article 310.13 for proper compliance.

C. Ground Conductors

a. Ground conductor shall be sized as noted in the Contract Documents. Where not specifically sized, NEC Article 250 shall be used as a minimum size.

b. Conductors used for grounding and bonding jumpers shall have green insulation. Where identified to be bare conductors, several wraps of green tape at the exposed end shall be used.

c. Bare grounding conductors shall be medium hard drawn (MHD) copper to facilitate the use of exothermic fastening methods, where used, in place of compression lugs and mechanical connecting means.

d. Ground Taps:

1) Conductor size: #2 AWG, stranded, MHD copper conductor

2) Number of Conductors: 1

3) Insulation: Bare copper

D. Single Conductor Wiring

1. Single conductors used for general wiring shall meet the following specification:

a. General

1) UL Listed - flame-retardant, heat resistant thermoplastic or moisture and heat resistant thermoplastic, if dual rated conductor type

b. Electrical

1) Rated 600V, 75°C for wet application, 90°C for dry or dual rated

c. Mechanical

1) Number of conductors: 1 (single);

2) Conductor type: 14 - 4/0 AWG stranded, soft drawn copper, sized per application;

Special Provisions 14

3) Insulation type: Thermoplastic, i.e. THHN, THWN, or THWN-2;

4) Insulation thickness: Thickness as defined in mil for given cable type and size per NEC

Article 310.13(A);

5) Jacket type: Nylon

2. Larger single conductors used for general wiring shall meet the following specification:

a. General

1) For application of larger conductors providing greater flexibility;

2) UL Listed - moisture resistant, flame-retardant

b. Electrical

1) Rated 600V, 75°C for wet application, 90°C for dry or dual rated

c. Mechanical

1) Number of conductors: 1 (single);

2) Conductor type: 250 and larger kcmil stranded, soft drawn copper, sized per application;

3) Insulation type: Thermoset (Rubber or ethylene propylene rubber compound), i.e.

RHH, RHW, or RHW-2

4) Insulation thickness: Thickness as defined in mil for given cable type and size per NEC

Article 310.13(A);

5) Jacket type: N/A for this insulation type.

E. Multi-conductor Cables

a. Multi-conductor cables are defined as cables containing paired conductors or two conductors and a ground. These may be shielded, unshielded, armored, or non-armored, as required for given application. More than a single pair of multiple conductors may be used.

b. Multi-conductor cables are required in multiple configurations. Cabling shall be required to be applied based upon use in given locations or applications:

1) Power applications - Armored and non-armored, wet location, 600V rated;

2) Control applications - Armored and non-armored, wet location, 600V and 300V rated.

c. Cabling rated 600V shall be required for all applications that are routed within a common raceway containing other cabling rated 600V.

2. Multiple-conductor cables, in non-armored styles, shall be required for use when cabling is:

a. Routed within conduit raceway systems or within structures and may be rated 300V or 600V pending application;

Special Provisions 15

F. Premise Connection Devices

1. Type 66 Connector Blocks to be used for terminating and cross-connecting unshielded twisted pair cable, up to and including Category 5, shall meet the following specifications:

a. Capacity: 25 pair

b. Conductor range: 26-22 AWG solid

c. Connections: Gas-tight insulation displacement connection (IDC)

d. Clip material: Tin plated copper alloy

e. Pigtail: Factory installed 22 AWG copper

2. RJ-11 Jacks, where required, shall meet the following specifications:

a. Pinout: Complies with Universal Service Ordering Code (USOC) configuration

b. Configuration: Wall plate with single position RJ-11 jack

c. Conductor range: 26-22 AWG solid

d. Connections: Insulation displacement

e. Contacts: Beryllium copper with minimum 50 micro-inch gold plating on contact

3. 8P8C (RJ-45) Jacks, where required, shall meet the following specifications:

a. Pinout: Complies with TIA/EIA568C configuration for 10BASE-T (IEEE 802.3)

b. Configuration: Surface or flush wall plate with single position RJ-45 jack

c. Conductor range: 26-22 AWG solid

d. Connections: Insulation displacement

4. Four-Gang Receptacles shall meet the following specifications:

a. Capacity: 4 duplex outlets

b. Conductor range: Receptacle and conductors shall be rated for the amperage of the dedicated circuit it is wired on. (Typically 20A for this project)

c. Connections: Insulation displacement

d. Grounding: #6 AWG Ground wire. Provide ground fault detection for all receptacles located in wet areas.

5. Conductor termination on devices:

a. Device terminals and terminal blocks shall utilize screw terminals accepting conductors with insulated, tinned copper, ring tongue crimp connectors, appropriately sized for the application. Properly sized crimping tools shall be used to install connector.

b. Larger conductors terminating on larger equipment and/or large breakers shall use tinned copper, one or two bolt, long barrel compression lugs as applicable for the equipment termination configuration. Properly sized dies shall be used with the crimping tool to install connector. Straight, long barrels shall be used unless Engineer approves use of short-barrel and/or 45° or 90° angled lug for special applications.

Special Provisions 16

A. The Contractor shall perform acceptance testing.

B. All test results shall be provided to the Engineer.

2.4 WORK PERFORMED BY OTHERS

A. The Contractor shall work with other Contractors to accomplish the successful implementation of the system.

B. The Contractor shall work with other Contractors to coordinate and schedule processes in a timely and efficient manner.

2.5 WARRANTY

A. Comply with requirements specified in Section 01 77 00 - CLOSEOUT PROCEDURES for administrative and procedural requirements pertaining to warranties.

B. See Section 26 01 01 - ELECTRICAL (GENERAL) and for information pertaining to warranty requirements.

The Contractor shall furnish and install equipment, hardware/software, enclosures, transmission media, interconnecting cables, power connections and backup systems required to complete the integration of a fully functional system as specified by the contract documents.

A. The Contractor shall adhere to the installation instructions provided by the manufacturers of the equipment. Deviations shall be justified by the Contractor and shall be pre-approved.

B. Contractor shall adhere to the stricter of the applicable specification, local, city/county, State, or

Federal codes. The Engineer shall provide ruling over disputes.

C. The Contractor shall fully cooperate with other Contractors and the Engineer to facilitate the system installation, integration, and testing.

D. Feeders: Copper for feeders smaller than No. 4 AWG; copper or aluminum for feeders No. 4 AWG and larger. Solid for No. 10 AWG and smaller; stranded for No. 8 AWG and larger.

E. Branch Circuits: Copper. Solid for No. 10 AWG and smaller; stranded for No. 8 AWG and larger.

A. The Contractor shall perform pre-installation configuration verification.

B. Before installation, the Contractor shall conduct the necessary site surveys to verify site readiness.

C. Before installation, the Contractor shall pre-assemble, test, and certify operational, system components.

Special Provisions 17

1. Test results shall be provided to the Engineer for evaluation.

2. Any deficiencies shall be corrected and components shall be retested.

D. Any conditions that are beyond the Contractor's control that will impede the installation by the

Contractor shall be reported to the Engineer using the Problem Notification Report (PNR).

A. Installation of all specific cabling system components shall be in accordance with the contract documents.

B. All installations shall be in compliance with the latest revision of the National Electric Code NFPA-70.

C. All installations shall be in compliance with ANSI/TIA/EIA 568-B.2-1 "Commercial Building

Telecommunications Wiring Standard."

D. All installations shall be in compliance with EIA/TIA 569 "Commercial Building Standard for Telecommunications Pathways and Spaces."

E. All installations shall be in compliance with TIA/EIA-606, "Administration Standard for the

Telecommunications Infrastructure of Commercial Buildings."

F. All installations shall be in compliance EIA/TIA-607,"Commercial Building Grounding and Bonding Requirements for Telecommunications."

G. All installations shall be in compliance BICSI Telecommunications Distribution Methods Manual.

H. All exposed cabling shall be enclosed in conduit or raceways.

I. Cables pulled through conduit shall be installed with extra pull lines to facilitate replacement or expansion. Pull lines shall be plastic or nylon with a minimum test rating of 200 lb. pulling tension.

J. All cabling shall meet applicable UL safety specifications.

K. All cabling shall be labeled and secured in accordance with standard industry practices as specified in TIA/EIA-606, "Administration Standard for the Telecommunications Infrastructure of Commercial Buildings."

L. Contractor shall ensure to adhere to cable minimum bend radius and maximum allowable pulling tension when handling and installing cables.

M. Connections:

1. Tighten electrical connectors and terminals according to manufacturer's published torque-tightening values. If manufacturer’s torque values are not indicated, use those specified in UL 486A and UL 486B.

2. Make splices and taps that are compatible with conductor material and that possess equivalent or better mechanical strength and insulation ratings than unspliced conductors.

3. Use oxide inhibitor in each splice and tap conductor for aluminum conductors.

Special Provisions 18

4. Wiring at Outlets: Install conductor at each outlet, with at least 6 inches of slack.

A. Testing Agency: Engage a qualified testing agency to perform tests and inspections.

B. Manufacturer’s Field Service: Engage a factory-authorized service representative to test and inspect components, assemblies, and equipment installations, including connections.

C. Perform the following tests and inspections:

1. Ground System Testing

2. Insulation Resistance Testing

3. Continuity Testing

D. Records

1. Contractor shall supply to the Engineer a plan for management of cabling related information to Engineer for approval.

2. Copies of all field generated hardcopy documents shall be maintained daily.

E. Test Reports: Prepare a written report to record the following:

1. Test procedures used.

2. Test results that comply with requirements.

3. Test results that do not comply with requirements and corrective action taken to achieve compliance with requirements.

F. Remove and replace malfunctioning units and retest as specified above.

3.5 TRAINING

providing Work of this Section shall be incidental to Electrical Infrastructure Work.

4.2 MEASUREMENT

A. No specific measurement will be made for the Work of this Section as specified herein and as shown on the Contract Drawings.

4.3 PAYMENT

A. Payment for the Work of this Section will be included in Work identified as Electrical.

4.4 PAYMENT ITEMS

END OF SECTION 26 05 19

Special Provisions 19

SP-04 SECTION 26 05 29 SUPPORTING DEVICES

1.1

This section specifies furnishing and installing mounting and supporting devices for electrical and communications equipment and materials.

1.2 RELATED SECTIONS

A. This section relates to all other applicable electrical sections.

1.3 REFERENCES AND STANDARDS

A. Section 27 00 01 – REFERENCES AND STANDARDS

1.4 SUBMITTALS

A. Samples and/or catalog-cut sheets of proposed devices shall be submitted to the City’s Representative for approval.

1.5 SYSTEM DESCRIPTION

Not Used

1.6 QUALITY ASSURANCE

A. Supporting devices, of types and sizes required, shall have been satisfactorily used for purposes similar to those intended herein for not less than ten (10) years.

2 .1 MATERIALS

A. Furnish all inserts and fastenings necessary for the rigid and secure installation of all equipment.

B. Provide supporting hardware including stainless steel bolts, nuts, washers, lock-washers, and screws.

Use wood screws or lag screws of appropriate length to securely fasten equipment to wood.

C. Use insert drop-in anchors, expansion bolts, or self-drilling type anchors and drive pins for fastening to masonry. Provide inserts of the type to receive machine bolts after installation.

D. Provide channel inserts not lighter than 12-gauge steel and channel not smaller than 1-1/2 inches by

1-1/2 inches with a continuous 7/8 inch wide slot. All channel inserts shall be hot dip galvanized after fabrication in accordance with ASTM A123. Cover inserts with a zinc chromate solution.

1. Provide surface mounted channel inserts with a 3/8 inch by 3 inch base slot on 4 inch centers.

Galvanize inserts for surface mounting on concrete surfaces or for installation in damp areas.

2. Concrete embedded channel inserts shall have a solid base. Concrete anchors shall be welded to the base during fabrication and before galvanizing.

3. Provide channel insert assemblies with a pull-out load rating of not less than 4,500 pounds per linear foot, uniformly distributed. Fill the channel with Styrofoam in a manner which will prevent concrete from entering into channel during installation.

Special Provisions 20

4. Spot inserts shall be rated at 800 pounds with a safety factor of five. Inserts shall be fabricated from steel, hot dip galvanized after fabrication in accordance with ASTM A123. Inserts shall be covered in a manner which will prevent concrete from entering during installation.

E. Hangers shall be stainless steel. Provide hangers consisting of two or more stainless steel rods, a steel horizontal member and U-bolts, clamps, and other attachments necessary for securing hanger rods and conduits. Furnish hanger rod not smaller than 3/8 inch diameter, threaded either full length or for a sufficient distance at each end to permit at least 1-1/2 inches of adjustment. Provide hangers capable of supporting a load equal to 200 pounds plus the sum of the weights of the conduit, cable tray, conductors, and hangers.

F. Furnish miscellaneous stainless steel consisting of supports, angles, flats, and channels for the proper spacing and support of control equipment, disconnect switches, panelboards, and switchboards, wall mounted transformers, and other electrical equipment.

A. Various miscellaneous brackets shall be required for mounting or securing of components. Contractor shall provide as indicted in the Contract Drawings.

2.4 WARRANTY

A. Equipment supplied by but not manufactured by the seller shall be subject to the original equipment manufacturers standard warranty.

B. Communications Systems equipment warranties for supportive devices shall be for a period of not less than 3 years from the date of revenue service.

2.5 DELIVERY, STORAGE, AND HANDLING

A. All materials shall be delivered in the manufacturer’s original, unopened, protective packaging and handled in a manner to prevent damage to finished surfaces.

B. Materials shall be stored in a clean, dry space and protected from weather.

A. The Contractor shall examine and verify that electrical installations and other related Work satisfy the requirements for performance of the Work of this Section and in accordance with Contract Documents.

B. The Contractor shall immediately report to the City’s Representative any electrical, structural, or related construction defects in areas where supporting devices are to be installed. The Contractor shall not attempt to rectify any defect unless instructed to do so by the City’s Representative.

Special Provisions 21

A. The Contractor shall investigate the site condition to determine what preparatory work, if any, will be required prior to the installation of supporting devices.

A. Install all fasteners, supports and devices as necessary for the installation requirements of the electrical equipment and material.

B. Exposed conduit shall be fastened to structures acceptable to the City’s Representative by clamps, straps, or hangers spaced at intervals not more than 10 feet when fastened to steel structures and not more than 7-1/2 feet when fastened to concrete. Do not support or fasten conduit by welding directly to equipment or to the building structure. Do not use C clamps as a permanent method of supporting vertical conduit risers. In conduit runs with expansion joints, install clamps within 3 feet, but not closer than 6 inches, to couplings, boxes, and fittings. Install exposed raceways parallel to or perpendicular to walls and structural members, and parallel to intersections of vertical plans and ceilings. Provide all conduit straps and clamps with base fittings or back plates that provide an air space of 1/4 inch minimum between the conduit run and supporting surfaces. Do not use perforated iron or wood plugs and nailing as methods of attachment. Make fastenings to steel members with granular flux filled welded studs.

C. Locate cable tray supports on centers not greater than 8 feet to ensure a rigid installation. Interconnect sections for a rigid mechanical assembly. Provide cable tray supporting components comprised of clamps, clips, concrete inserts, hanger rods, insulators, racks, frames, trapezes, beams, structural steel clamps, U-bolts, slotted angles and fittings, machine screws, wall anchors, and similar items. Ensure that components of dissimilar metals are compatible with the equipment that they support, such as raceway, cable tray, and cable equipment.

D. In damp or wet locations, do not mount electrical equipment (including boxes, starters, panels, and conduit) so that it touches the walls. Provide 1/2 inch or more of air space between wall and equipment. If strips or channels are used for standoffs, mount them vertically, so they will not collect moisture.

providing Work of this Section shall be incidental to Electrical Work.

4.2 MEASUREMENT

A. No specific measurement will be made for the Work of this Section as specified herein and as shown on the Contract Drawings.

Special Provisions 22

4.3 PAYMENT

A. Payment for the Work of this Section will be included in Work identified as Electrical.

END OF SECTION 26 05 29

Special Provisions 23

SP-05 SECTION 26 05 30 HANGERS AND SUPPORT FOR ELECTRICAL SYSTEMS

A. This Section includes the following:

1. Hangers and supports for electrical equipment and systems.

2. Construction requirements for concrete bases.

1.2 RELATED DOCUMENTS

A. See Section 27 00 01 REFERENCES AND STANDARDS for additional references.

B. American Society for Testing and Materials (ASTM)

1. ASTM A325 - Standard Specification for Structural Bolts, Steel, Heat Treated, 120/105 ksi

Minimum Tensile Strength

2. ASTM A780 - Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip

Galvanized Coatings

3. ASTM A36/A36M - Standard Specification for Carbon, Structural Steel

C. Manufacturers Standardization Society (MSS)

1. MSS SP-58 - Pipe Hangers and Supports - Materials, Design, Manufacture, Selection, Application, and Installation

D. Metal Framing Manufacturers Association (MFMA)

1. MFMA-4 - Metal Framing Standards Publication

E. National Electrical Contractors Association (NECA)

1. NECA 1 - Standard Practice of Good Workmanship in Electrical Construction (ANSI)

2. NECA 101 - Standard for Installing Steel Conduit (Rigid, IMC, EMT) (ANSI)

F. National Fire Protection Association (NFPA)

1. NFPA 70 - National Electrical Code

G.

H.

Society for Protective Coatings Painting Application (SSPC-PA)

SSPC-PA 1 - Shop, Field, and Maintenance Painting of Steel

1.4

SUBMITTALS

A. Product Data: For the following:

Special Provisions 24

1. Steel slotted support systems.

1.5

SYSTEMS DESCRIPTION

A. Design equipment supports capable of supporting combined operating weight of supported equipment and connected systems and components.

B. Rated Strength: Adequate in tension, shear, and pullout force to resist maximum loads calculated or imposed for this Project, with a minimum structural safety factor of five times the applied force.

1.6

QUALITY ASSURANCE

A. Comply with NFPA 70.

B. Coordinate size and location of concrete bases. Cast anchor-bolt inserts into bases. Concrete, reinforcement, and formwork requirements are specified together with concrete Specifications.

PART 2 – PRODUCTS

A. Support, Anchorage, and Attachment Components:

1. Steel Slotted Support Systems: Comply with MFMA-4, factory-fabricated components for field assembly.

a. Metallic Coatings: Hot-dip galvanized after fabrication and applied according to MFMA-

4.

b. Painted Coatings: Manufacturer's standard painted coating applied according to

MFMA-4.

c. Channel Dimensions: Selected for applicable load criteria.

2. Raceway and Cable Supports: As described in NECA 1 and NECA 101.

3. Mounting, Anchoring, and Attachment Components: Items for fastening electrical items or their supports to building surfaces or freestanding equipment enclosures include the following:

a. Verify suitability of fasteners in subparagraph below for use in lightweight concrete or concrete slabs less than 4 inches thick.

b. Clamps for Attachment to Steel Structural Elements: MSS SP-58, type suitable for attached structural element.

c. Through Bolts: Structural type, hex head, and high strength. Comply with ASTM A 325.

d. Toggle Bolts: All-steel springhead type.

e. Hanger Rods: Threaded steel.

B. Fabricated Metal Equipment Support Assemblies:

1. Description: Bolted, structural-steel shapes, shop or field fabricated to fit dimensions of supported equipment.

2. Materials: Comply with ASTM A36/A36M for steel shapes and plates.

Special Provisions 25

A. Factory-fabricated support, anchorage, and attachment components, and structural-steel.

2.3 WARRANTY

A. Comply with requirements specified in Section 01 77 00 CLOSEOUT PROCEDURES for administrative

A. Comply with NECA 1 and NECA 101 for application of hangers and supports for electrical equipment and systems except if requirements in this Section are stricter.

A. Coordinate all equipment weights and arrangement prior to assembling site-fabricated metal supports.

A. Spring-steel clamps designed for supporting single conduits without bolts may be used for 1-1/2-inch and smaller raceways serving branch circuits and communication systems above suspended ceilings and for fastening raceways to trapeze supports.

B. Comply with NECA 1 and NECA 101 for installation requirements except as specified in this Article.

C. Strength of Support Assemblies: Where not indicated, select sizes of components so strength will be adequate to carry present and future static loads within specified loading limits. Minimum static design load used for strength determination shall be weight of supported components plus 200 lb.

D. Mounting and Anchorage of Surface-Mounted Equipment and Components: Anchor and fasten electrical items and their supports to building structural elements by the following methods unless otherwise indicated by code:

1. To Light Steel: Sheet metal screws.

2. Items Mounted on Hollow Walls and Nonstructural Building Surfaces: Mount cabinets, panelboards, disconnect switches, control enclosures, pull and junction boxes, and other devices on slotted-channel racks attached to substrate by means that meet seismic-restraint strength and anchorage requirements.

E. Drill holes for expansion anchors in concrete at locations and to depths that avoid reinforcing bars.

F. Installation Of Fabricated Metal Supports:

1. Cut, fit, and place miscellaneous metal supports accurately in location, alignment, and elevation to support and anchor electrical materials and equipment.

G. Concrete Bases:

1. Construct concrete bases of dimensions indicated but not less than 4 inches larger in both

Special Provisions 26 directions than supported unit, and so anchors will be a minimum of 10 bolt diameters from edge of the base.

2. Use 3,600-psi, 28-day compressive-strength concrete.

3. Anchor equipment to concrete base.

a. Place and secure anchorage devices. Use supported equipment manufacturer's setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.

b. Install anchor bolts to elevations required for proper attachment to supported equipment.

c. Install anchor bolts according to anchor-bolt manufacturer's written instructions.

H. Painting:

1. Touchup: Clean field welds and abraded areas of shop paint. Paint exposed areas immediately after erecting hangers and supports. Use same materials as used for shop painting. Comply with SSPC-PA 1 requirements for touching up field-painted surfaces.

a. Apply paint by brush or spray to provide minimum dry film thickness of 2.0 mils.

2. Galvanized Surfaces: Clean welds, bolted connections, and abraded areas and apply galvanizing- repair paint to comply with ASTM A 780.

3.4

FIELD QUALITY CONTROL

Comply with administrative and procedural requirements of Section 01 45 00 QUALITY CONTROL.

3.5

TRAINING

A. Refer to Section 01 79 00 DEMONSTRATION AND TESTING for administrative and procedural requirements pertaining to demonstration and training.

No separate measurement or payment will be made for the Work required under this Section. Costs for providing Work of this Section shall be incidental to the item or items to which they pertain.

4.2

MEASUREMENT

No specific measurement will be made for the Work…