7-Contract No. 25-10 - Gas Turbine Generator Maintenance Technical Specs FINAL.pdf

PDF 160 KB Posted

Attached to
Turbine Generator Maintenance, Inspection, and As-Need Repair & Replacement Parts
Solicitation number
BCUA-BID-25-10
Issued by
Bergen County, New Jersey

About this file

This is a Technical Specifications document for BCUA Contract No. 25-10 issued by the Bergen County Utilities Authority (BCUA) in New Jersey for turbine generator maintenance, inspection, and as-needed repair and replacement parts. The contract seeks a fully authorized Original Equipment Manufacturer (OEM) contractor to provide technical service, maintenance, repairs, and OEM replacement parts on an as-needed basis for three Siemens/Rolls Royce 501 KB Engines (Serial Numbers ASP-652, ASP-654, and ASP-583). The scope includes annual inspections of all three gas turbine generator units, with required work encompassing complete mechanical and electrical inspections, internal borescope inspections, fuel nozzle removal and inspection, thermocouple and electrical harness checks, magnetic chip detector inspection, air and fuel filter service, exhaust system inspection, test runs, and functional testing of control systems and annunciators. Service technicians must respond to requests within five work days and arrive onsite within that timeframe; emergency response is required within 24 hours of notification. The contract will commence upon execution and continue for two years with two one-year renewal options, or until expenditures reach the awarded amount.

Replacement parts must be OEM-approved equivalents with a minimum 30-day warranty and shall be billed at the contractor's cost plus a material markup not to exceed 15%, with the contractor required to provide cost documentation. All parts shipments must be F.O.B. destination freight prepaid, with freight costs reimbursed with no markup. Regular hourly labor rates apply for work Monday through Friday, 7:00 AM to 5:00 PM, with separate emergency hourly rates for work outside normal business hours and weekends. Contractors delayed beyond the five-work-day response time incur a 5 percent billing rate reduction for each work day late. Service technicians must maintain job tracking records and provide daily activity reports verified by an Authority representative before payment authorization. The contract does not guarantee specific parts quantities, labor hours, or total expenditure amounts, as all orders are placed on an as-needed basis only with payment limited to parts actually ordered, freight actually expended, and hours actually worked.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Turbine Generator Maintenance, Inspection, and As-Need Repair & Replacement Parts BCUA Contract No. 25-10

01000-1

SECTION 01000

SCOPE OF WORK

1.0 SCOPE OF WORK

The intent of this bid is to secure a contractor who will provide technical service, maintenance and repairs, on an "as needed" basis, various new and unused Original

Equipment Manufacturers (OEM) replacement parts and components for the Authority's

Siemens/Rolls Royce 501 KB Engines. Contractors must be a fully authorized contractor of the OEM and able to supply all replacement parts, materials and supplies as listed in the manufacturer parts books of the equipment listed below, as well as to provide service on an "as needed" basis.

2.0 EQUIPMENT

Siemens/Rolls Royce 501 KB Engines:

Serial #ASP-652 - Engine #2

Serial #ASP-654 - Engine #3

Serial #ASP-583- Engine #4

3.0 PARTS

A. QUALITY

All parts must be OEM replacement parts or approved equivalent. Equivalent means parts that are equal or superior in every aspect including, but not limited to, criteria of performance, reliability, serviceability, and interchangeability.

All parts shall carry a minimum of thirty (30) day warranty for defects in materials and workmanship. Any standard Manufacturer's warranty, if longer than thirty

(30) days, shall apply.

In the case of rebuilt or reconditioned component OEM parts that may customarily carry a longer term of guarantee for workmanship or materials, the usual terms and conditions shall apply.

B. BILLING AND DELIVERY TIME

All parts shall be considered not readily available. Upon request, the Contractor shall provide a detailed quote that includes the estimated lead time for the required parts within five (5) business days. All requests for quotes for as-needed services shall be

Turbine Generator Maintenance, Inspection, and As-Need Repair & Replacement Parts BCUA Contract No. 25-10

01000-2 provided at no additional cost to the Authority. The Authority may or may not authorize the work proposed in the quote at its sole discretion.

For parts that are authorized by the Authority, deliveries must be made within the lead time specified in the approved quote. Parts shall be billed at the Contractor's cost, plus the % Material Markup agreed upon under this Contract (not to exceed 15%). That is:

BP = CP + (CP x MM)

Or equivalently:

BP = CP x (1 + MM)

Where:

BP = Billing Price (amount charged to the Authority)

CP = Cost Price (actual cost paid by the Contractor for the part)

MM = % Material Markup (expressed as a decimal, e.g., 15% = 0.15)

For all invoices relating to the furnishing and delivery of replacement parts, the

Contractor shall attach documentation providing proof of the actual cost paid by the

Contractor for said parts. This documentation may include, but is not limited to, supplier invoices, purchase orders, or receipts. This requirement is to enable the

Authority to verify the accuracy of the % Material Markup applied in accordance with the terms agreed upon under this Contract.

C. FREIGHT COSTS

All parts shipments must be F.O.B. destination, freight prepaid and charged back.

The contractor must utilize standard shipping methods and all charges shall be in accordance with the area's customary freight charges. Overnight, air freight, or next day shipment must be specifically authorized by the Authority.

Freight costs shall be considered a direct expense to the contractor that will be reimbursed to the contractor with no mark up. Freight costs must be substantiated with written freight invoices and will be charged against the freight allowance given in the bid proposal. The Authority will only pay what is listed on the supplied freight invoice. The amount of the freight allowance given in the bid proposal is neither a maximum nor a minimum of what may be charged for freight costs. It is an arbitrary allowance that was assigned for the purpose of obtaining consistency in the bids received.

4.0 SERVICE TECHNICIANS

Turbine Generator Maintenance, Inspection, and As-Need Repair & Replacement Parts BCUA Contract No. 25-10

01000-3

A. QUALIFICATIONS

Repair and service technicians performing requested work shall have documented manufacturer training on the types and kind of equipment listed and proof of such documented training shall be requested from time to time. The contractor shall provide all necessary tools, equipment, parts and materials incidental to the performance of the required work. All work performed on Authority equipment or component parts shall be guaranteed as customary and usual for the services provided.

B. HOURLY LABOR RATES

1. REGULAR HOURLY RATE

The contractor shall provide a fixed per man-hour labor rate for the duration of this contract for such technical service, maintenance or repair work that may be requested beyond that covered by the unit warranty at the

Authority's facility The regular hourly rate shall be the cost of a single technician working onsite Monday through Friday. excluding holidays, during the hours of 7:00 AM through 5:00 PM or up to eight (8) hours daily and shall include all costs for performing the requested work along with all associated costs for tool usage and/or rental costs, travel time to and from site, mileage, and environmental or casual charges that may result from the performance of the requested task. Payment will be made only for the number of hours onsite working at the bid amount. No separate payment will be made for associated costs such as travel time, vehicle mileage costs, tolls, tool usage and/or rental costs etc.

2. EMERGENCY RESPONSE RATE

The contractor shall initiate work within twenty-four (24) hours after notification from Authority staff of the emergent event. The cost is based on hourly rate for repairs/maintenance outside of normal business hours

(including weekends and holidays) and outside of the regular hourly rate. The emergency hourly rate shall be the cost of a single technician working onsite and shall include all costs for performing the requested work along with all associated costs for tool usage and/or rental costs, travel time to and from site, mileage, and environmental or casual charges that may result from the performance of the requested task. Payment will be made only for the number of hours performed onsite working at the emergency hourly bid amount. No separate payment will be made for associated costs such as travel time, vehicle mileage costs, tolls, tool usage and/or rental costs etc. The contractor shall also provide the Authority with a 24-hour emergency telephone number that will serve as the notification and dispatch center for service calls from the

Authority.

C. BILLING AND SERVICE RESPONSE TIME

Turbine Generator Maintenance, Inspection, and As-Need Repair & Replacement Parts BCUA Contract No. 25-10

01000-4

The contractor's qualified technician must arrive onsite within five (5) work days

(calendar days excepting Saturdays, Sundays, and Authority holidays) of e- mail notification. Service work that is initiated within five (5) work days of notification is to be billed at the hourly rate bid. Service that is initiated beyond the five (5) work day response time shall be provided at a unit rate reduced by an amount of five percent (5%) for each and every work day beyond the five (5) work day response time that service work begins. This is:

• For service work that is started within the specified five (5) work day response time:

BR=HR

• For service work that is started beyond the specified five (5) work day response time:

BR=HR-(HR x 0.05 x DW)

BR = Billing Rate

HR = Hourly Rate given in the bid proposal

DW = Work days that the start of service work is late beyond the specified five (5) work day response time.

Note also that it is the intention of this contract that, once begun, service work is to be provided, until completed, on consecutive work days (calendar days excepting

Saturdays, Sundays and Authority holidays). After starting work, should the responding technician vacate the site for more than two (2) consecutive work days

(calendar days excepting Saturdays, Sundays and Authority holidays), the technician's return shall be treated, for billing purposes, as a separate service request subject to the billing reduction given below.

BR=HR-(HR x 0.05 x DA)

BR = Billing Rate

HR= Hourly Rate given in the proposal

DA= Work days that the contractor's technician is absent from the site once work had been started, beyond two (2) consecutive work days.

Performance of Work - To be limited to that included in service request.

D. WORK RECORDS

Turbine Generator Maintenance, Inspection, and As-Need Repair & Replacement Parts BCUA Contract No. 25-10

01000-5

The contractor shall maintain a job tracking system that, at a minimum, records:

i. The date and time a request was received by the Contractor;

ii. The date and time a crew was dispatched to the site;

iii. The date and time the crew arrived at the site;

iv. A description of the problem and corrective work required;

v. The amount of time spent on the site by the Contractor's personnel;

vi. The materials and spare parts used by the contractor; and

vii. The date and time the work or repair was accepted by the Authority.

The contractor shall provide the Authority with a report that summarizes all such activity on a daily basis or prior to any payment being made. No payments can be made without said report signed as verified by an

Authority representative.

5.0 BID QUANTITIES

This contract does not guarantee that a specific number of parts will be ordered, or that a specific number of labor hours will be requested, or that a specific total dollar amount will automatically be expended. The parts value and labor hours listed on the Bid Form will be used in the evaluation of the bids.

All parts, quantities, freight, and labor will be ordered on an "as needed" basis only.

Payment will only be made for the parts that are ordered and received, for freight costs actually expended and for hours actually worked onsite to complete the requested repairs.

6.0 SUBMITTALS (WITH BID)

A. APPROVED EQUIVELANT (ONLY IF APPLICABLE)

If a bidder would like to propose approved equal retail parts, the bidder must furnish a price listing for the corresponding Siemens/Rolls Royce Engines catalog equivalents with your bid submission.

B. CONTACT INFORMATION

The contractor shall provide the name, telephone number and e-mail address of the person(s) responsible for satisfying parts and service requests. Parts delivery and service response times shall be marked as beginning once the Authority makes contact with the given person(s). Should the submitted contact information change, the Authority must be immediately provided with the updated Authority information.

7.0 ANNUAL SERVICE

Turbine Generator Maintenance, Inspection, and As-Need Repair & Replacement Parts BCUA Contract No. 25-10

01000-6

The intent of this annual service is to have qualified technicians inspect all aspects of our

Rolls-Royce® 501KB Turbine Power System Allison Power Generators, as follows:

1. Unit #2 501K-722 ASP-652

2. Unit #3 501K-723 ASP-654

3. Unit #4 501K-724 ASP-583

4. (Note Unit #1 is not currently installed)

The work under this contract consists of performing all work required for the evaluation, analysis and service of the Gas Turbine Generator in accordance with the scope of work detailed below.

The Scope of Work for this contract consists of the following:

7.1 Annual Inspection

1. Perform a complete mechanical and electrical inspection of the Gas Turbine

Generator System.

2. If the inspection reveals the need for additional parts and/or labor, promptly notify and provide a quotation (including lead-time) to the Authority Engineer or his designated contact for the additional work. Owner must authorize any additional work prior to any provision of work.

3. Perform an internal engine borescope inspection of the engine compressor and turbine section in accordance with applicable OEM specifications. Provide photographs in the Inspection Report.

4. Remove and inspect all fuel nozzles, check combustion liner components.

Provide photographs in the Inspection Report.

5. Visual check of all thermocouples, igniter/exciter leads & electrical harnesses.

Provide photographs in the Inspection Report.

6. Check magnetic chip detector for debris, clean as required. Provide photographs in the Inspection Report of the chip detector prior to cleaning.

7. Check, air bleed system & filter, manifold drain valve, G/T Low Pressure Fuel

Filter (supply and change filters as required).

8. Visually inspect fuel plumbing.

9. Inspect air filter and intake system (supply and change filters as required).

10. Inspect complete exhaust system.

11. Perform test run and turbine crank.

12. Record and verify the unit is running with proper temperature, pressure and engine speed. Provide documentation of the values in the Inspection Report.

13. Check engine operation noting any unusual conditions or performance in the

Inspection Report.

14. Functional testing of annunciator.

15. Functional testing of the turbine engine generator control system, including shutdowns, alarms and crank cycling.

16. Perform normal start of the turbine.

Turbine Generator Maintenance, Inspection, and As-Need Repair & Replacement Parts BCUA Contract No. 25-10

01000-7

8.0 PAYMENT

Payment shall only be made after the submittal of properly executed Purchase Order, Voucher, and the corresponding Service Reports by the contractor.

9.0 DELIVERY

Products shall be delivered to the Authority after the contractor's receipt of a Purchase

Order to:

Bergen County Utilities Authority

98 Empire Blvd., Moonachie, NJ 07074

Delivery shall be between the hours of 6:30 AM and 2:00 PM, Monday through

Friday, except Authority holidays.

10.0 CONTRACT DURATION

This contract will commence upon the execution of the Agreement by both parties and shall continue in effect for a two (2) year period with two (2) one-year options to renew at the sole discretion of the Authority or when expenditures reach the awarded contract amount.

11.0 SAFETY

The contractor shall provide the Authority with their Health and Safety Plan.

Contractor must submit the Health and Safety Plan to the Authority's Safety

Director. The contractor is responsible for safety and security precautions during any work performed at the Authority.

END OF SECTION