This is a Scope of Work attachment for an Invitation to Quote issued by the City of Little Rock for the Rhino Barn Gates and Interior Fencing project in Arkansas. The project encompasses demolition and replacement of interior poles and gates on the south side of the Rhino Barn at the Little Rock Zoo. The scope requires removal of existing concrete footings (18" wide), poles, and related materials, with replacement of five new 12"x4" square schedule 40 steel posts set to 4' depth and finished flush with the existing concrete floor. The project also includes installation of three replacement panels and two replacement gates, all constructed from 2" schedule 40 steel tubing with specific dimensional requirements. Panel 1 measures 66" wide x 6' tall with 6 vertical bars spaced at 9" intervals; Panel 2 measures 74" wide x 6' tall with 7 vertical bars spaced at 9" intervals; Panel 3 measures 70" wide x 6' tall with 6 vertical bars spaced at 9" intervals. Gates 4 and 5 each measure 37" wide x 52" tall with 3 vertical bars spaced at 7" intervals and must be equipped with SHUTIT BADASS ORIGINAL HINGES Model # C13000. A mandatory Pre-Bid Meeting is scheduled for January 21, 2026 at 10:00 AM, during which contractors must obtain field measurements at the work site.

All metal components must be painted with Sherwin Williams direct-to-metal oil-based paint branded "SW BRZ3 Chestnut Bronze" as rust preventative. The vendor is responsible for mandatory removal and hauling of all demolition materials, including old concrete, dirt, metal poles, panels, and miscellaneous scrap or hardware as approved by Zoo staff. All work must comply with referenced drawings for proper spacing and height of posts, panels, and gates. Gates 4 and 5 must align and lock to existing angle iron attached to the wall. The scope of work does not include pricing terms, set-asides, funding sources, or contract award information.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

City of Little Rock Invitation to Quote – Little Rock Zoo – Rhino Barn Gates and Interior Fencing

Attachment C – Scope of Work – Interior Poles and Gate

Rhino Barn – South Side: Demolition of existing poles and panels with gates.

Scope consists of cutting and removing the concrete - 18” wide.

Thereafter, removal of existing poles. Re-work the footing to 4’ depth.

Mandatory removal and hauling by vendor: All old concrete, dirt, metal poles, panels and any related miscellaneous scrap or hardware, as approved by Zoo staff.

Replacements shall be five (5) new 12’X4” square schedule 40 steel posts. New footing must be poured to meet the existing concrete floor; shall be slick finished, poles must be filled with concrete. Vendor must mound to the top and shall finish smoothed. Refer to drawings for spacing and height of the new posts.

Replace three (3) panels. All panels shall have vertical bars and be made from 2 ½” schedule 40 steel tubing. Panels shall be 4” off of the floor. Refer to drawings for spacing and height of the new panels.

Replace two (2) gates. All gates shall have vertical bars and be made from 2 ½” schedule 40 steel tubing. Gates shall be 4” off the floor. Hinges shall be branded “SHUTIT BADASS ORIGINAL HINGES Model # C13000”. Refer to drawings for spacing and height of the new gates.

Gates 4 and 5 will need to match up and lock to the existing angle iron that is attached to the wall.

Panel 1: shall be 66” wide X 6’ tall with 6 vertical bars spaced at 9 ¾” inside dimension.

Panel 2: shall be 74” wide X 6’ tall with 7 vertical bars spaced at 9 ¾” inside dimension.

Panel 3: shall be 70” wide X 6’ tall with 6 vertical bars spaced at 9 ¾” inside dimension.

Gate 4: shall be 37” wide X 52” tall with 3 vertical bars spaced at 7 ½” inside dimension.

Gate 5: shall be 37” wide X 52” tall with 3 vertical bars spaced at 7 ½” inside dimension.

All metal shall be painted with rust preventative and painted with Sherwin Williams direct to metal oil-based paint. Branded “SW BRZ3 Chestnut Bronze”.

Contractors shall arrive to work-site for proper field measurements at the Mandatory Pre-Bid Meeting on 01/21/2026 at 10AM.