QnA 10-22-25.pdf

PDF 114 KB Posted

Attached to
CA FLAP MOD 258(1) Blue Lake Road
Solicitation number
6982AF25R000017
Issued by

About this file

This document is a Questions and Answers (Q&A) file for the CA FLAP MOD 258(1) Blue Lake Road project, with questions and official responses dated from September 24 to October 22, 2025. Key details include clarifications about bid specifications such as roadway aggregate and topsoil requirements, confirmation that there will be no scheduled site visit or pre-bid meeting, and instructions for submitting bid bonds to Eric Grosskreuz at the Federal Highway Administration's Central Federal Lands Division in Lakewood, CO. The Q&A addresses technical questions about project materials like hydroseeding seed (referencing section 713.04), Rolled Erosion Control Product Type 3B, and shoulder fill materials, while also providing guidance for vendors about SAM.gov registration and bid submission procedures. The government declined requests for project continuance due to a government shutdown and maintained strict requirements for original bid bond submissions.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for CA FLAP MOD 258(1) Blue Lake Road

September 24, 2025

Questions Answers 1 Bid Schedule, A7-A8, Schedule A, Schedule Type: Base show:

Pay Item #30202-2000 (Fill with Roadway Aggregate, method 2 at 2,750 tons) as well as Pay Item #62402-0300 (Furnish and Placing Topsoil, 4-inch depth at 6.7 acres).

Was this pay item inadvertently doubled-up on the 4-foot shoulder areas (both sides of the road), or is it FHWA's intention to shoulder-fill both materials? To help with our question, we're specifically looking at Typical Section, sheet no. A7, Detail A, B.

If both are required, please clarify the following material(s) needed:

Is this FP-14 Section 313 - Aggregate-Topsoil Course; 313.01- 313.02?

a. Aggregate for aggregate-topsoil course 703.13

b. Seed 713.04

c. Topsoil 713.01

d. Water 725.01 ( c )

Is this FP-14 Section 713 - Roadside Improvement Material Topsoil; 713.01?

Is this FP-14 Section 703 - Aggregate; 703-2?

The limits of turf establishment and topsoil are outside of the shoulder up material (roadway aggregate, method 2). Turf and topsoil are not required over the shoulder up material (roadway aggregate, method 2).

2 We at NPA specialty equipment are a spider excavator company specializing in rockfall , landslide , and difficult terrain.

We would like to bid only on the rockfall and slope stabilization part of the project.

There is an interested vendor’s tab on SAM.gov. You have to be signed in and have tied your entity to your registration when you signed up. If both of those things don’t happen the interested vendors list tab won’t be visible.

We don’t maintain a separate plan holders list.

You can call the federal service desk if you need further assistance. The number is 1‐866‐606‐7828

September 30, 2025

3 Is there a scheduled site visit? A pre-bid meeting or show me trip. There will not be a scheduled site visit or pre-bid meeting.

October 3, 2025

4 Seed Project: CA FLAP MOD 258(1) Blue Lake Road

Solicitation No. 6982AF25R00001

RFP page A-i indicates “Bid bonds must be originals with original signatures and corporate seals. Photocopies and Faxed copies are NOT acceptable and will make your bid non-responsive. Original’s must be received no later than the response due date and time.” Can the government please clarify if offerors should submit the original bid bond to the attention of Eric Grosskreuz, Acquisition Program Specialist or Jorey Deml, Contract Specialist?

The bid bonds for RFP 6982AF25R000017 CA FLAP MOD 258(1) Blue Lake Road shall be submitted to the attention of Eric Grosskreuz.

5 Please confirm that the address in Block 8 of the SF1442 (Federal Highway Administration, Central Federal Lands Division Office 12300 W. Dakota Avenue, Lakewood, CO 80228) is the correct address for sending original bid bonds.

Yes, this is the correct address.

October 21, 2025

6 Due to the government shutdown, our pending approval for our JV agreement has been delayed, please consider a continuance of the project for this reason.

There will not be a continuance of the project for this reason.

October 22, 2025

8 What seed is to be used for the hydroseeding? See section 713.04 9 Which mat ( Rolled Erosion Control Product) is needed for this item Type 3B