QnA Wilson 11.21.25.pdf

PDF 139 KB Posted

Attached to
NV FTBL 1094(1) Wilson Campground Road Federal contract opportunity
Solicitation number
6982AF25B000025
Issued by
Department of Transportation Federal Highway Administration

About this file

This document is a Questions and Answers file for the NV FTBL 1094(1) Wilson Campground Road project, spanning multiple dates from October 28 to November 21, 2025. The document provides clarifications on various bidding and project implementation details, including equipment usage, labor requirements, and project constraints. Key points include specification of hourly rate items for technical work, confirmation that equipment and labor costs for specific line items are included in Section 622 of the FP-14, and guidance on biological monitoring requirements.

Notable project specifics include no pre-bid site visit, a bid opening on November 20, 2025 at 2:00 PM (which was not extended despite contractor requests), and restrictions on ground-disturbing activities starting no earlier than July 1, 2026. The contractor is responsible for identifying construction water sources, potentially from Wilson Reservoir, and must refer to various Special Contract Requirements (SCR) sections for detailed guidance on project execution, including staking, permitting, erosion control, and biological monitoring. The project involves roadway excavation, with material generated on-site anticipated to supply necessary fill quantities.

View the file

Other files for this federal contract opportunity

Other files attached to NV FTBL 1094(1) Wilson Campground Road, newest first.
File Type Posted
Wilson Bid Opening Summary Sched and Opt.pdf PDF
Wilson Interested Vendors 11.20.25.pdf PDF
QnA Wilson 11.19.25 REV FINAL.pdf PDF
A001 11.19.25 Wilson.pdf PDF
QnA Wilson 11.19.25.pdf PDF
QnA Wilson 11.12.25 Final.pdf PDF
QnA Wilson 10.28.25.pdf PDF
Section 152 Physical Data.zip ZIP file
6982AF25B000025 FINAL.pdf PDF
01.100 Plans FLAT.pdf PDF
20.100 Final Hydraulic Report FLAT.pdf PDF
21.95 Final Geotechnical Report FLAT.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for

NV FTBL 1094(1) WILSON CAMPGROUND ROAD

October 28, 2025

Questions Answers 1 In an effort to ensure we are completing the Bid Schedule properly, we have a question regarding the “Hourly” unit price items.

a) For example, Line Item Numbers A0720 through A0820 include a quantity of 40 hours (with the exception of A0800 which is 80 hours). Are we to assume these line items are a “weekly rate” – and that we are pricing them “per week” – or is the government estimate that we will only need an 8 yard dump truck for a total of 40 hours (per line A0720)?

b) Additionally, for these line items, are we to assume that is the equipment AND operator cost (per hour), or is that standby time for the equipment only?

c) Finally, if these lines are for equipment and labor, does that mean we exclude these costs from the other line items (where this equipment and labor will be utilized) – basically making those items material only?

a) Items A0720 though A0820 are for technical work ordered by the CO and not otherwise provided for under the contract. Refer to Section 622 of the FP-14 and Section 623 of the Special Contract Requirements (SCR’s). For instance, for an item such as A0340 20401- 0000 Roadway Excavation any equipment and labor used to complete the work for roadway excavation will be included in that item and will NOT be paid under the 622 and 623 items.

b) Items A0720 through A0780 include equipment and operator cost in accordance with Section 622 of the FP- 14.

c) Refer to answer a).

2 Line Item A0840 – which is a labor line item for the Biological Monitor, but this is a Lump Sum unit; whereas, the bid schedule only allows for 80 hours of General Labor (as opposed to a “lump sum” unit of general labor).

Line A0840 62303-1000 Special Labor Hired Technical Services (Biological Monitor) will perform all biologist work as required by SCR Subsection 107.10 (e) and will be paid as LPSM.

For General Labor, refer to the answer given to question 1 a) above.

3 Could you please confirm whether a pre-bid site visit is scheduled for this project?

There is no pre-bid site visit.

November 10, 2025

4 What is the last day questions can be submitted? Please reference Notice to Bidders, page A-iii.

5 Is there a bird survey required for this project? Refer to SCR 107.10 (e)

6 Have there been any addendums issued as of today? No Amendment has been issued as of November 12, 2025.

7 If weather conditions allow, can we start "ground disturbing activities" earlier than July 1, 2026? Say May 1, 2026?

No, bid according to limitations of operations listed in SCR Subsection 108.01.

November 12, 2025

8 Considering the upcoming Thanksgiving holiday — we respectfully request a two-week extension of the bid due date, currently scheduled for November 20, 2025, at 2:00 PM.

No, the bid opening date will not be extended.

9 Will the contractor be able to utilize Wilson Reservoir or its overflow ditch as a source for construction water? We’ve tried to contact the local BLM office for use of construction water, however they are closed due to the Government shutdown.

Contractor may contact Wilson Reservoir owner for request of water source. Contact Info: John Jackson; Petanyp@gmail.com;

208-841-3539 Contractor is responsible for identifying source for construction water.

November 17, 2025

9 Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?

Refer to SCR Subsection 153.02 for QC Manager requirements.

10 Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?

Refer to SCR and FP-14 Subsection 108.03(c)

11 Are soil boring reports available? If not, it will be assumed that excavation will be clear of rocks and obstructions.

Refer to the Geotechnical Report posted on SAM.gov and referenced in SCR Subsection 102.02A mailto:Petanyp@gmail.com

12 Is there a bulk water fill i.e. a hydrant or water source we can pump from for grading operations in close proximity?

Contractor may contact Wilson Reservoir owner for request of water source. Contact Info: John Jackson; Petanyp@gmail.com;

208-841-3539 Contractor is responsible for identifying source for construction water.

13 Does this project require phasing? Refer to SCR Section 107, 108, and 156 for limitations of operations.

14 Is this project tax exempt? See FAR Clause 52.229-3 Federal, State, and Local Taxes 15 When do you anticipate on site work starting? Refer to SCR Subsection 108.01 16 Is permitting required? Refer to SCR Section 107 17 Please provide staking data points for the project. Refer to Section 152 Physical Data.zip file posted to SAM.gov and SCR Subsection 152.04 for information provided.

18 Are red, yellow, and blue tops required? Refer to SCR Subsection 152.04 19 Does the Field office duration need to include the duration for

Option X?

Refer to SCR Subsection 637.02

20 Please provide details and size of existing cattle guards to be removed and reset.

Measurements and reset approach are the responsibility of the contractor.

21 Are we to assume the cattle guards will require new precast concrete?

Measurements and reset/replace approach are the responsibility of the contractor, to include new precast concrete, if required.

22 In the absence of a SWPPP plan do we need to account for silt fencing along the entirety of the project or is there a preferred erosion control material?

Refer to SCR Section 157

23 Is it necessary for the biologist to be on site for the full duration? Refer to SCR Subsection 107.10(e)

November 19, 2025

24 Can you extend the bid opening? Refer to Amendment A001

November 21, 2025

25 The Bid Schedule has a line item for Roadway Excavation but not a line item for Import Borrow. We cannot determine the amount of import borrow since the plans do not have finish grade elevations.

See Section 204 of the SCR’s. When net earthwork results in more excavation than fill placement only excavation quantity is paid. Material generated onsite anticipated to supply necessary fill quantity. If import is required for other work items, that is an

How should the contractor proceed when import borrow is required without an import borrow line item?

indirect payment per section 109.05(b). See also B sheets grading summary.

File details come from the government source that posted it. Updated .