This document is a Questions and Answers (Q&A) file for the NV FTBL 1094(1) Wilson Campground Road project, dated October 28, 2025, with additional Q&A entries on November 10 and 12, 2025. The document addresses bidder inquiries about specific line items in the bid schedule, including hourly rates for equipment and labor, classification of line items for technical work, and a Biological Monitor labor line item. Key details include: no pre-bid site visit is scheduled, ground-disturbing activities are limited to starting July 1, 2026, the bid opening date is November 20, 2025, at 2:00 PM, and contractors are responsible for identifying their own construction water source. The project involves roadway work, with specific references to sections FP-14 and Special Contract Requirements (SCR), and includes provisions for technical work, equipment usage, and specialized labor services.

View the file

Other files for this federal contract opportunity

Other files attached to NV FTBL 1094(1) Wilson Campground Road, newest first.
File Type Posted
Wilson Bid Opening Summary Sched and Opt.pdf PDF
QnA Wilson 11.21.25.pdf PDF
Wilson Interested Vendors 11.20.25.pdf PDF
QnA Wilson 11.19.25 REV FINAL.pdf PDF
A001 11.19.25 Wilson.pdf PDF
QnA Wilson 11.19.25.pdf PDF
QnA Wilson 10.28.25.pdf PDF
6982AF25B000025 FINAL.pdf PDF
01.100 Plans FLAT.pdf PDF
20.100 Final Hydraulic Report FLAT.pdf PDF
Section 152 Physical Data.zip ZIP file
21.95 Final Geotechnical Report FLAT.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for

NV FTBL 1094(1) WILSON CAMPGROUND ROAD

October 28, 2025

Questions Answers 1 In an effort to ensure we are completing the Bid Schedule properly, we have a question regarding the “Hourly” unit price items.

a) For example, Line Item Numbers A0720 through A0820 include a quantity of 40 hours (with the exception of A0800 which is 80 hours). Are we to assume these line items are a “weekly rate” – and that we are pricing them “per week” – or is the government estimate that we will only need an 8 yard dump truck for a total of 40 hours (per line A0720)?

b) Additionally, for these line items, are we to assume that is the equipment AND operator cost (per hour), or is that standby time for the equipment only?

c) Finally, if these lines are for equipment and labor, does that mean we exclude these costs from the other line items (where this equipment and labor will be utilized) – basically making those items material only?

a) Items A0720 though A0820 are for technical work ordered by the CO and not otherwise provided for under the contract. Refer to Section 622 of the FP-14 and Section 623 of the Special Contract Requirements (SCR’s). For instance, for an item such as A0340 20401- 0000 Roadway Excavation any equipment and labor used to complete the work for roadway excavation will be included in that item and will NOT be paid under the 622 and 623 items.

b) Items A0720 through A0780 include equipment and operator cost in accordance with Section 622 of the FP- 14.

c) Refer to answer a).

2 Line Item A0840 – which is a labor line item for the Biological Monitor, but this is a Lump Sum unit; whereas, the bid schedule only allows for 80 hours of General Labor (as opposed to a “lump sum” unit of general labor).

Line A0840 62303-1000 Special Labor Hired Technical Services (Biological Monitor) will perform all biologist work as required by SCR Subsection 107.10 (e) and will be paid as LPSM.

For General Labor, refer to the answer given to question 1 a) above.

3 Could you please confirm whether a pre-bid site visit is scheduled for this project?

There is no pre-bid site visit.

November 10, 2025

4 What is the last day questions can be submitted? Please reference Notice to Bidders, page A-iii.

5 Is there a bird survey required for this project? Refer to SCR 107.10 (e)

6 Have there been any addendums issued as of today? No Amendment has been issued as of November 12, 2025.

7 If weather conditions allow, can we start "ground disturbing activities" earlier than July 1, 2026? Say May 1, 2026?

No, bid according to limitations of operations listed in SCR Subsection 108.01.

November 12, 2025

8 Considering the upcoming Thanksgiving holiday — we respectfully request a two-week extension of the bid due date, currently scheduled for November 20, 2025, at 2:00 PM.

No, the bid opening date will not be extended.

9 Will the contractor be able to utilize Wilson Reservoir or its overflow ditch as a source for construction water? We’ve tried to contact the local BLM office for use of construction water, however they are closed due to the Government shutdown.

Contractor may contact Wilson Reservoir owner for request of water source. Contact Info: John Jackson; Petanyp@gmail.com;

208-841-3539 Contractor is responsible for identifying source for construction water.