This document is an amendment to an Invitation for Bid (IFB) for the CA FTNP SEKI 13(2) Mineral King Road construction project being solicited by the Federal Highway Administration. The project scope includes pulverizing the existing pavement, placing aggregate base, and paving the 12.09-mile Mineral King Road located in Sequoia and Kings Canyon National Park in Tulare County, California. Other work includes constructing retaining walls, drainage improvements, and culvert replacements. The contract is expected to be a firm-fixed-price with economic price adjustment. The solicitation has a projected advertisement date of October 2024 and construction is anticipated from April 2025 through October 2027. The estimated cost range for the project is $25 million to $35 million.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

2. AMENDMENT/MODIFICATION NUMBER

A002 CA FTNP SEKI 13(2)

FEDERAL HIGHWAY ADMINISTRATION

CENTRAL FEDERAL LANDS HIGHWAY DIVISION

12300 WEST DAKOTA AVENUE, SUITE 360

LAKEWOOD, COLORADO 80228

ATTENTION: JOREY DEML

6905001

9A. AMENDMENT OF SOLICITATION

6982AF24B000017

9B. DATED (SEE ITEM 11)

10/02/2024

0*

*See Item 14

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

INVITATION FOR BID

1. Replace the entire sections B,C, and D pages with the attached amended pages labeled with Amendment A002

*FAILURE TO ACKNOWLEDGE THIS AMENDMENT IN BLOCK 19 OF THE SF 1442 BY THE DESIGNATED DATE AND HOUR SPECIFIED IN THE SOLICITATION MAY RESULT IN REJECTION OF YOUR BID (REFER TO ITEM 11.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

11/4/2024

X

B-7

Solicitation Provisions

52.203-11 Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. (SEP 2007)

52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements-Representation. (JAN 2017)

52.204-5 Women-Owned Business (Other Than Small Business). (OCT 2014)

52.204-7 System for Award Management. (OCT 2018)

52.204-8 Annual Representations and Certifications. (MAY 2024)

52.204-16 Commercial and Government Entity Code Reporting (AUG 2020)

52.204-17 Ownership or Control of Offeror (AUG 2020)

52.204-20 Predecessor or Offeror (AUG 2020)

52.204-22 Alternative Line Item Proposal (JAN 2017)

52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (NOV 2021)

52.204-26 Covered Telecommunications Equipment or Services-Representation. (OCT 2020)

52.209-5 Certification Regarding Responsibility Matters. (AUG 2020)

52.209-7 Information Regarding Responsibility Matters (OCT 2018)

52.209-11 Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law (FEB 2016)

52.209-13 Violation of Arms Control Treaties or Agreements – Certification (NOV 2021)

52.214-3 Amendments to Invitations for Bids. (DEC 2016)

52.214-4 False Statements in Bids. (APR 1984)

52.214-5 Submission of Bids. (DEC 2016)

52.214-6 Explanation to Prospective Bidders. (APR 1984)

52.214-7 Late Submissions, Modifications, and Withdrawals of Bids. (NOV 1999)

Amendment A002 11/4/2024

B-8

52.214-18 Preparation of Bids - Construction. (APR 1984)

52.214-19 Contract Award - Sealed Bidding - Construction. (AUG 1996)

52.214-31 Facsimile Bids (DEC 1989)

52.214-34 Submission of Offers in the English Language. (APR 1991)

52.214-35 Submission of Offers in U.S. Currency. (APR 1991)

52.215-5 Facsimile Proposals. (OCT 1997)

52.216-1 Type of Contract. (APR 1984)

The Government contemplates award of a FIRM FIXED PRICE with Economic Price Adjustment contract resulting from this solicitation.

(End of provision)

52.217-5 Evaluation of Options (JUL 1990)

The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

(End of provision)

52.219-1 Small Business Program Representations (FEB 2024)

52.222-5 Construction Wage Rate Requirements Secondary Site of the Work. (MAY 2014)

52.223-1 Bio based Product Certification (MAY 2024)

As required by the Farm Security and Rural Investment Act of 2002 ( 7 U.S.C. 8101(4)) and the Energy Policy Act of 2005 ( 7 U.S.C. 8102(a)(2)(F)), the offeror certifies, by signing this offer, that biobased products (within categories of products listed by the United States Department of Agriculture in 7 CFR part 3201, subpart B) to be used or delivered in the performance of the contract, other than biobased products that are not purchased by the offeror as a direct result of this contract, will comply with the applicable specifications or other contractual requirements.

(End of provision)

B-9

52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction. (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled Affirmative Action Compliance Requirements for Construction, and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade.

The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the -

(1) Name, address, and telephone number of the subcontractor; (2)

Employer's identification number of the subcontractor;

Goals for Minority Participation for Each Trade

Goals for Female Participation for Each Trade

23.6% - Tulare County, CA 6.9%

B-10

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the covered area is Tulare County, CA.

52.222-38 Compliance with Veterans' Employment Reporting Requirements. (FEB 2016)

52.223-22 Public Disclosure of Greenhouse Gas Emissions and Reduction Goals— Representation (DEC 2016)

52.225-12 Notice of Buy American Requirement—Construction Materials Under Trade Agreements. (MAY 2014)

52.225-20 Prohibition on Conducting Restricted Business Operations in Sudan-- Certification. (AUG 2009)

52.228-1 Bid Guarantee. (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds -

(1) To unsuccessful bidders as soon as practicable after the opening of bids;

and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be twenty (20%) percent of the bid price or $3,000,000.00, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the

B-11

Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

52.233-2 Service of Protest. (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Mr. Joseph Wilson Acquisitions Branch Chief Federal Highway Administration 12300 West Dakota Avenue, Suite 360 Lakewood, Colorado 80228

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.236-27 Site Visit (Construction). (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) Site visit will be held on October 8, 2024 at 10:00am MST. Interested parties will meet at the Lookout Point Entrance Area on Mineral King Road at 10AM. The coordinates for the parking area are: 36.429644157342054, -118.76221831397702 which is approximately 15 miles (45 minutes travel time) from Three Rivers, CA.

52.252-1 Solicitation Provisions Incorporated by Reference. (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

B-12 http://www.acquisition.gov/far

52.252-3 Alterations in Solicitation. (APR 1984)

Portions of this solicitation are altered as follows: NONE

1252.239–92 Information and Communication Technology Accessibility Notice (NOV 2022)

C-1

Contract Clauses

52.202-1 Definitions. (JUN 2020)

52.203-3 Gratuities. (APR 1984)

52.203-5 Covenant Against Contingent Fees. (MAY 2014)

52.203-6, Restrictions on Subcontractor Sales to the Government (JUN 2020)

52.203-7 Anti-Kickback Procedures. (JUN 2020)

52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity. (MAY 2014)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity. (MAY 2014)

52.203-12 Limitation on Payments to Influence Certain Federal Transactions. (JUN 2020)

52.203-13 Contractor Code of Business Ethics and Conduct (NOV 2021)

52.203-14 Display of Hotline Poster(s) (NOV 2021)

(a) Definition.

United States, as used in this clause, means the 50 States, the District of Columbia, and outlying areas.

(b) Display of fraud hotline poster(s). Except as provided in paragraph (c)—

(1) During contract performance in the United States, the Contractor shall prominently display in common work areas within business segments performing work under this contract and at contract work sites-

(i) Any agency fraud hotline poster or Department of Homeland Security (DHS) fraud hotline poster identified in paragraph (b)(3) of this clause; and

(ii) Any DHS fraud hotline poster subsequently identified by the Contracting Officer.

(2) Additionally, if the Contractor maintains a company website as a method of providing information to employees, the Contractor shall display an electronic version of the poster(s) at the website.

(3) Any required posters may be obtained as follows:

C-2

General Fraud https://www.oig.dot.gov/sites/default/files/files/OIG-generic-2.pdf

(c) If the Contractor has implemented a business ethics and conduct awareness program, including a reporting mechanism, such as a hotline poster, then the Contractor need not display any agency fraud hotline posters as required in paragraph (b) of this clause, other than any required DHS posters.

(d) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (d), in all subcontracts that exceed the threshold specified in Federal Acquisition Regulation 3.1004(b)(1) on the date of subcontract award, except when the subcontract—

(1) Is for the acquisition of a commercial product or commercial service; or

(2) Is performed entirely outside the United States.

(End of clause)

52.203-17 Contractor Employee Whistleblower Rights and Requirements to Inform Employees of Whistleblower Rights (NOV 2023)

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017)

52.204-1 Approval of Contract (DEC 1989)

This contract is subject to the written approval of the Acquisitions Branch Chief and shall not be binding until so approved.

(End of Clause)

52.204-9 Personal Identity Verification of Contractor Personnel (JAN 2011)

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (JUN 2020)

52.204-13 System for Award Management Maintenance. (OCT 2018)

52.204-14 Service Contract Reporting Requirements (OCT 2016)

52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020)

52.204-19 Incorporation by Reference of Representations and Certifications. (DEC 2014)

52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or

C-3

Provided by Kaspersky Lab and Other Covered Entities (DEC 2023)

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (NOV 2021)

52.204-27 Prohibition on a ByteDance Covered Application (JUN 2023)

52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (NOV 2021)

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations (NOV 2015)

52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)

The Contractor shall be required to (a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than {Refer to Subsection 108.01 of the SCRs}. The time stated for completion shall include final cleanup of the premises.

(End of clause)

52.211-12 Liquidated Damages - Construction. (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $ 4,500.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

52.211-13 Time Extensions. (SEP 2000)

52.211-18 Variation in Estimated Quantity. (APR 1984)

52.214-26 Audit and Records – Sealed Bidding. (JUN 2020)

52.214-27 Price Reduction for Defective Certified Cost or Pricing Data – Modifications – Sealed Bidding. (JUN 2020)

52.214-28 Subcontractor Certified Cost or Pricing Data – Modifications – Sealed Bidding.

(JUN 2020)

C-4

52.217-7 Option for Increased Quantity - Separately Priced Line Item. (MAR 1989)

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 120 days after award. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns. (OCT 2022)

(a) Evaluation preference. (1) Offers will be evaluated by adding a factor of 10 percent to the price of all offers, except-

(i) Offers from HUBZone small business concerns that have not waived the evaluation preference; and

(ii) Otherwise successful offers from small business concerns.

(2) The factor of 10 percent shall be applied on a line item basis or to any group of items on which award may be made. Other evaluation factors described in the solicitation shall be applied before application of the factor.

(3) When the two highest rated offerors are a HUBZone small business concern and a large business, and the evaluated offer of the HUBZone small business concern is equal to the evaluated offer of the large business after considering the price evaluation preference, award will be made to the HUBZone small business concern.

(b) Waiver of evaluation preference. A HUBZone small business concern may elect to waive the evaluation preference, in which case the factor will be added to its offer for evaluation purposes.

□ Offeror elects to waive the evaluation preference.

(c) Joint venture. A HUBZone joint venture agrees that, in the performance of the contract, at least 40 percent of the aggregate work performed by the joint venture shall be completed by the HUBZone small business parties to the joint venture. Work performed by the HUBZone small business parties to the joint venture must be more than administrative functions.

52.219-8 Utilization of Small Business Concerns (FEB 2024)

C-5

52.219-9 Small Business Subcontracting Plan (SEP 2023) - Alternate I (NOV 2016)

52.219-14 Limitations on Subcontracting (OCT 2022)

52.219-16 Liquidated Damages -- Subcontracting Plan (SEP 2021)

52.219-28 Post-Award Small Business Program Rerepresentation (FEB 2024)

52.222-1 Notice to the Government of Labor Disputes. (FEB 1997)

52.222-3 Convict Labor. (JUN 2003)

52.222-4 Contract Work Hours and Safety Standards Act - Overtime Compensation. (MAY 2018)

52.222-6 Construction Wage Rate Requirements. (AUG 2018)

52.222-7 Withholding of Funds. (MAY 2014)

52.222-8 Payrolls and Basic Records. (JUL 2021)

52.222-9 Apprentices and Trainees. (JUL 2005)

52.222-10 Compliance with Copeland Act Requirements. (FEB 1988)

52.222-11 Subcontracts (Labor Standards). (MAY 2014)

52.222-12 Contract Termination - Debarment. (MAY 2014)

52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. (MAY 2014)

52.222-14 Disputes Concerning Labor Standards. (FEB 1988)

52.222-15 Certification of Eligibility. (MAY 2014)

52.222-21 Prohibition of Segregated Facilities. (APR 2015)

52.222-26 Equal Opportunity. (SEP 2016)

52.222-27 Affirmative Action Compliance Requirements for Construction. (APR 2015)

52.222-35 Equal Opportunity for Veterans. (JUN 2020)

52.222-36 Affirmative Action for Workers with Disabilities. (JUN 2020)

52.222-37 Employment Reports on Veterans (JUN 2020)

C-6

52.222-40 Notification of Employee Rights Under the National Labor Relations Act (DEC 2010)

52.222-50 Combating Trafficking in Persons (NOV 2021)

52.222-54 Employment Eligibility Verification (MAY 2022)

52.222-55 Minimum Wages Under Executive Order 13658 (JAN 2022)

52.222-62 Paid Sick Leave Under Executive Order 13706 (JAN 2022)

52.223-2 Reporting of Biobased Products Under Service and Construction Contract. (MAY 2024)

52.223-3 Hazardous Material Identification and Material Safety Data. (FEB 2021)

52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2024)

52.223-21 Foams (MAY 2024)

52.223-23 Sustainable Products and Services (MAY 2024)

52.224-1 Privacy Act Notification. (APR 1984)

52.224-2 Privacy Act. (APR 1984)

52.225-11 Buy American-Construction Materials under Trade Agreements (NOV 2023)

(a) Definitions. As used in this clause—

Caribbean Basin country construction material means a construction material that—

(1) Is wholly the growth, product, or manufacture of a Caribbean Basin country; or

(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a Caribbean Basin country into a new and different construction material distinct from the materials from which it was transformed.

Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

C-7

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C.40102(4), such as agricultural products and petroleum products.

Component means an article, material, or supply incorporated directly into a construction material.

Construction material means an article, material, or supply brought to the construction site by the Contractor or subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at

FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.

Designated country means any of the following countries:

C-8

(1) A World Trade Organization Government Procurement Agreement (WTO GPA) country (Armenia, Aruba, Australia, Austria, Belgium, Bulgaria, Canada, Croatia, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Moldova, Montenegro, Netherlands, New Zealand, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Taiwan, Ukraine, or United Kingdom);

(2) A Free Trade Agreement (FTA) country (Australia, Bahrain, Canada, Chile, Colombia, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Korea (Republic of), Mexico, Morocco, Nicaragua, Oman, Panama, Peru, or Singapore);

(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea- Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, South Sudan, Tanzania, Timor-Leste, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia); or

(4) A Caribbean Basin country (Antigua and Barbuda, Aruba, Bahamas, Barbados, Belize, Bonaire, British Virgin Islands, Curacao, Dominica, Grenada, Guyana, Haiti, Jamaica, Montserrat, Saba, St. Kitts and Nevis, St. Lucia, St. Vincent and the Grenadines, Sint Eustatius, Sint Maarten, or Trinidad and Tobago).

"Designated country construction material" means a construction material that is a WTO GPA country construction material, an FTA country construction material, a least developed country construction material, or a Caribbean Basin country construction material.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if—

(A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029.

(B) The construction material is a COTS item; or

C-9

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States.

Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Free Trade Agreement country construction material means a construction material that-

(1) Is wholly the growth, product, or manufacture of a Free Trade Agreement (FTA) country; or

(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a FTA country into a new and different construction material distinct from the materials from which it was transformed.

Least developed country construction material means a construction material that-

(1) Is wholly the growth, product, or manufacture of a least developed country; or

(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a least developed country into a new and different construction material distinct from the materials from which it was transformed.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

C-10

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

United States means the 50 States, the District of Columbia, and outlying areas.

WTO GPA country construction material means a construction material that-

(1) Is wholly the growth, product, or manufacture of a WTO GPA country; or

(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a WTO GPA country into a new and different construction material distinct from the materials from which it was transformed.

(b) Construction materials.

(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C.1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction material, excluding COTS fasteners. (See FAR 12.505(a)(2)). In addition, the Contracting Officer has determined that the WTO GPA and Free Trade Agreements (FTAs) apply to this acquisition. Therefore, the Buy American restrictions are waived for designated country construction materials.

(2) The Contractor shall use only domestic or designated country construction material in performing this contract, except as provided in paragraphs (b)(3) and (b)(4) of this clause.

(3) The requirement in paragraph (b)(2) of this clause does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

None

(4) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(3) of this clause if the Government determines that-

(i)The cost of domestic construction material would be unreasonable.

(A) For domestic construction material that is not a critical item or does not contain critical components.

(1)The cost of a particular domestic construction material subject to the restrictions of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

C-11

(2)For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(4)(i)(A)(1) of this clause.

(3)The procedures in paragraph (b)(4)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.

(B) For domestic construction material that is a critical item or contains critical components.

(1)The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.

(2)For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(4)(i)(B)(1) of this clause.

(3)The procedures in paragraph (b)(4)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.

(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1)

C-12

(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(4) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(4)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

C-13

Foreign and Domestic Construction Materials Price Comparison

Construction Material Description Unit of Measure Quantity Cost (Dollars)*

Item 1:

Foreign construction material

Domestic construction material

Item 2:

Foreign construction material

Domestic construction material

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]

[Include other applicable supporting information.]

[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]

52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving. (MAY 2024)

52.227-1 Authorization and Consent. (JUN 2020)

52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement. (JUN 2020)

52.227-4 Patent Indemnity--Construction Contracts. (DEC 2007)

52.228-2 Additional Bond Security. (OCT 1997)

52.228-5 Insurance - Work on a Government Installation. (JAN 1997)

52.228-11 Individual Surety - Pledges of Assets. (FEB 2021)

52.228-12 Prospective Subcontractor Requests for Bonds. (DEC 2022)

C-14

52.228-14 Irrevocable Letter of Credit (Nov 2014)

52.228-15 Performance and Payment Bonds - Construction. (JUN 2020)

52.229-3 Federal, State, and Local Taxes. (FEB 2013)

52.232-5 Payments under Fixed-Price Construction Contracts. (MAY 2014)

52.232-17 Interest. (MAY 2014)

52.232-23 Assignment of Claims. (MAY 2014)

52.232-27 Prompt Payment For Construction Contracts. (JAN 2017)

52.232-33 Payment by Electronic Funds Transfer – System for Award Management

(OCT 2018)

52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013)

52.232-40 Providing Accelerated Payments to Small Business Subcontractors (MAR 2023)

52.233-1 Disputes. (MAY 2014) - Alternate I (DEC 1991)

52.233-3 Protest after Award. (AUG 1996)

52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004)

52.236-1 Performance of Work by the Contractor (APR 1984)

The Contractor shall perform on the site, and with its own organization, work equivalent to at least thirty (30) percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.

52.236-2 Differing Site Conditions. (APR 1984)

52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984)

52.236-4 Physical Data. (APR 1984)

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

C-15

(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by:

1) Mineral King Road, Tulare County, CA, CA FTNP SEKI 13(2), Pavement and Materials Report, August 2024

2) Mineral King Road, Sequoia National Park, Tulare County, CA, CA FTNP SEKI 13(2), Final Geotechnical Report, Report No. CA-PX-0013-21-01, July 2021

3) Mineral King Road, Tulare County, CA, CA FTNP SEKI 13(2), Final Hydraulics Report, October 28, 2021

(b) Weather conditions Contact National Weather Service .

(c) Transportation facilities – N/A

(d) The following files can be sent upon request:

Mineral King Road – Existing Ground – Road Raise.xml Mineral King Road – Horizontal & Vertical Alignment.xml

52.236-5 Material and Workmanship. (APR 1984)

52.236-6 Superintendence by the Contractor. (APR 1984)

52.236-7 Permits and Responsibilities. (NOV 1991)

52.236-8 Other Contracts. (APR 1984)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR 1984)

52.236-10 Operations and Storage Areas. (APR 1984)

52.236-11 Use and Possession Prior to Completion. (APR 1984)

52.236-12 Cleaning Up. (APR 1984)

52.236-13 Accident Prevention. (NOV 1991) Alternate I (NOV 1991)

52.236-15 Schedules for Construction Contracts. (APR 1984)

52.236-17 Layout of Work. (APR 1984)

52.236-21 Specifications and Drawings for Construction. (FEB 1997)

52.236-26 Preconstruction Conference. (FEB 1995)

C-16

52.242-13 Bankruptcy. (JUL 1995)

52.242-14 Suspension of Work. (APR 1984)

52.243-4 Changes. (JUN 2007)

52.243-6 Change Order Accounting. (APR 1984)

52.244-6 Subcontracts for Commercial Products and Commercial Services (FEB 2024)

52.245-1 Government Property (SEP 2021) - Alternate I (APR 2012)

52.245-9 Use and Charges. (APR 2012)

52.246-12 Inspection of Construction. (AUG 1996)

52.247-64 Preference for Privately Owned U.S.-Flag Commercial Vessels (NOV 2021)

52.248-3 Value Engineering - Construction. (OCT 2020)

52.249-2 Termination for Convenience of the Government (Fixed-Price). (APR 2012) - Alternate I (SEP 1996)

52.249-10 Default (Fixed-Price Construction). (APR 1984)

52.252-2 Clauses Incorporated by Reference. (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): http://www.acquisition.gov/far

52.252-4 Alterations in Contract. (APR 1984)

Portions of this contract are altered as follows: NONE

52.253-1 Computer Generated Forms. (JAN 1991)

1252.201-70 Contracting Officer’s Representative (NOV 2022)

1252.222–72 Contractor Cooperation in Equal Employment Opportunity and Anti-

C-17

Harassment Investigations (NOV 2022)

1252.223-70 Removal or Disposal of Hazardous Substances – Applicable Licenses and Permits (NOV 2022)

1252.223-71 Accident and Fire Reporting (NOV 2022)

1252.223-73 Seat Belt Use Policies and Programs (NOV 2022)

1252.228-74 Notification of Payment Bond Protection (NOV 2022)

(a) The prime contract is subject to the Bonds statute (historically referred to as the Miller Act) (40 U.S.C. chapter 31, subchapter III), under which the prime contractor has obtained a payment bond. This payment bond may provide certain unpaid employees, suppliers, and subcontractors a right to sue the bonding surety under the Bonds statute for amounts owned for work performed and materials delivery under the prime contract.

(b) Persons believing that they have legal remedies under the Bonds statute should consult their legal advisor regarding the proper steps to take to obtain these remedies. This notice clause does not provide any party any rights against the Federal Government, or create any relationship, contractual or otherwise, between the Federal Government and any private party.

(c) The surety which has provided the payment bond under the prime contract is: On File with the FHWA.

(d) Subcontract flowdown requirements. This clause shall be flowed down to all subcontractors.

Prime contractors shall insert this notice clause in all first-tier subcontracts and shall require the clause to be subsequently flowed down by all first-tier subcontractors to all their subcontractors, at any tier. This notice contains information pertaining to the surety that provided the payment bond under the prime contract and is required to be inserted in its entirety to include the information set forth in paragraph (c).

1252.232–70 Electronic Submission of Payment Requests (NOV 2022)

1252.239–93 Information and Communication Technology Accessibility (NOV 2022)

POST-AWARD EVALUATION OF CONTRACTOR PERFORMANCE

Contractor Performance Evaluations

a. Interim and final evaluations of contractor performance will be prepared on this contract in accordance with FAR 42.1502 and TAM 1242.1502. The final performance evaluations will be prepared at the time of completion of work.

b. The Contractor can elect to review the evaluation and submit additional information or provide a rebuttal statement. The contractor will be permitted 60 calendar days to

C-18 respond from the date of receipt of the evaluation. Contractor response is voluntary.

If the contractor does not respond within 60 days, the Government will presume that the Contractor has no comment. Any disagreement between the parties regarding an evaluation will be referred to an individual at a level above the Contracting Officer, whose decision is final.

c. Copies of the evaluations, Contractor responses, and review comments, if any, will be retained as part of the contract file, and may be used to support future award decisions.

The Federal Highway Administration utilizes the Contractor Performance Assessment Reporting System (CPARS) to record and maintain past performance information.

CPARS hosts a suite of web-enabled applications that are used to document contractor performance information that is required by Federal Regulations. The CPARS module assesses performance on contracts for Systems, Services, Information Technology, and Operations Support; Architect-Engineer contracts; and Construction contracts.

Reference material can be accessed in CPARS.

The registration process requires the Contractor to identify an individual that will serve as a primary contact. This individual will be authorized access to the evaluation for review and comment. In addition, the Contractor is encouraged to identify a secondary contact in the event the primary contact is unavailable to process the evaluation within the required 60 day time period. After the FHWA Focal Point registers the contract in CPARS, the contractor representative will receive a system generated email notifying him/her that the contract is registered. A system generated email will also provide the Contractor with a User ID if the person does not already have a CPARS User ID.

After a performance evaluation has been prepared and is ready for comment, the Contractor representative will receive a system generated email notification that the performance evaluation is electronically available for review and comment. The Contractor representative will receive an automated email whenever an assessment is completed and can subsequently retrieve the completed assessment from CPARS.

Contractors may access evaluations in CPARS for review and comment.

"General Decision Number: CA20240021 10/18/2024

Superseded General Decision Number: CA20230021

State: California

Construction Types: Heavy (Heavy and Dredging) and Highway

County: Tulare County in California.

DREDGING (excluding self-propelled hopper dredge work), HEAVY (excluding water well drilling), AND HIGHWAY CONSTRUCTION

PROJECTS

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).

|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .