BID TABS UT FLAP SLA 10(1) Mill Creek Canyon Road.pdf
PDF 600 KB Posted
- Attached to
- UT FLAP SLA 10(1) Mill Creek Canyon Road
- Solicitation number
- 6982AF24B000015
About this file
This document is a Tabulation of Bids Report for a federal contract opportunity. The project is for the reconstruction and widening of Mill Creek Canyon Road in Salt Lake County, Utah. The project will improve safety, access to recreational sites, and protect natural resources. Key details include:
The solicitation number is 6982AF24B000015 for project UT FLAP SLA 10(1) - Mill Creek Canyon Road. The project consists of 3.1 miles of road reconstruction and widening to 20-foot paved width, 1.4 miles of 24-foot paved width, and improvements to pertinent parking and trailhead areas. The principal work items include clearing and grubbing, roadway excavation, special rock embankment, retaining walls, aggregate base, and asphalt concrete pavement. The government engineer's estimate was $20,578,105. Four bids were received, with the apparent low bidder being S & L Landscaping and Excavation Inc. at $22,298,868. The contract has not yet been awarded.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tabulation of Bids Report Date: 11/20/24
1 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Solcitation No: 6982AF24B000015
Division: Central Federal Lands
State: UT County: Salt Lake
Federal Land: Opened at: LAKEWOOD CO
Opened by: KELLY PALMER
Date: 11/12/24
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
S & L Landscaping and Excavation Inc $22,298,868.00 935 W Center St Lindon, UT 84042
MC Contractors, Inc ( $23,285,191.82 ) no
2054 W SR 32
Francis , UT 84036
Central Southern Construction Corp $24,984,426.60 119 Sewald St Jacksonville, FL 32204
Granite Construction Company $25,221,706.00 PO Box 50085 Watsonville, CA 950775085
Engineer's Estimate $20,578,105.00
2 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1000 15101-0000 MOBILIZATION
S & L Landscaping and Excavation Inc Lump Sum $2,400,000.00 MC Contractors, Inc Lump Sum $3,448,000.00 Central Southern Construction Corp Lump Sum $2,500,000.00 Granite Construction Company Lump Sum $2,108,200.00 Engineer's Estimate ALL LPSM Lump Sum $2,469,917.00
A1001 15215-3000 SURVEY AND STAKING, DRAINAGE STRUCTURE
S & L Landscaping and Excavation Inc $1,000.00 $68,000.00 MC Contractors, Inc $2,887.50 $196,350.00 Central Southern Construction Corp $5,625.00 $382,500.00 Granite Construction Company $1,500.00 $102,000.00 Engineer's Estimate 68 EACH $1,000.00 $68,000.00
A1002 15215-5000 SURVEY AND STAKING, BOX CULVERT
S & L Landscaping and Excavation Inc $3,500.00 $10,500.00 MC Contractors, Inc $2,887.50 $8,662.50 Central Southern Construction Corp $11,250.00 $33,750.00 Granite Construction Company $15,500.00 $46,500.00 Engineer's Estimate 3 EACH $7,000.00 $21,000.00
A1003 15215-7000 SURVEY AND STAKING, PARKING AREA
S & L Landscaping and Excavation Inc $10,000.00 $50,000.00 MC Contractors, Inc $2,887.50 $14,437.50 Central Southern Construction Corp $18,750.00 $93,750.00 Granite Construction Company $12,250.00 $61,250.00 Engineer's Estimate 5 EACH $5,000.00 $25,000.00
A1004 15225-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING CONTROL
S & L Landscaping and Excavation Inc $8,000.00 $36,480.00 MC Contractors, Inc $3,588.59 $16,363.97 Central Southern Construction Corp $22,500.00 $102,600.00 Granite Construction Company $67,250.00 $306,660.00 Engineer's Estimate 4.56 MILE $10,000.00 $45,600.00
A1005 15236-2000 SURVEY CONTROL, GRADE FINISHING
S & L Landscaping and Excavation Inc $6,000.00 $54,720.00 MC Contractors, Inc $5,197.50 $47,401.20 Central Southern Construction Corp $25,000.00 $228,000.00 Granite Construction Company $50,500.00 $460,560.00 Engineer's Estimate 9.12 MILE $6,000.00 $54,720.00
3 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1006 15301-0000 CONTRACTOR QUALITY CONTROL
S & L Landscaping and Excavation Inc Lump Sum $700,000.00 MC Contractors, Inc Lump Sum $1,122,000.00 Central Southern Construction Corp Lump Sum $600,000.00 Granite Construction Company Lump Sum $1,385,000.00 Engineer's Estimate ALL LPSM Lump Sum $666,000.00
A1007 15401-0000 CONTRACTOR TESTING
S & L Landscaping and Excavation Inc Lump Sum $400,000.00 MC Contractors, Inc Lump Sum $775,000.00 Central Southern Construction Corp Lump Sum $850,000.00 Granite Construction Company Lump Sum $213,000.00 Engineer's Estimate ALL LPSM Lump Sum $416,000.00
A1008 15501-0000 CONSTRUCTION SCHEDULE
S & L Landscaping and Excavation Inc Lump Sum $25,000.00 MC Contractors, Inc Lump Sum $42,500.00 Central Southern Construction Corp Lump Sum $30,000.00 Granite Construction Company Lump Sum $50,000.00 Engineer's Estimate ALL LPSM Lump Sum $166,000.00
A1009 15701-0000 SOIL EROSION CONTROL
S & L Landscaping and Excavation Inc Lump Sum $400,000.00 MC Contractors, Inc Lump Sum $490,000.00 Central Southern Construction Corp Lump Sum $550,000.00 Granite Construction Company Lump Sum $601,000.00 Engineer's Estimate ALL LPSM Lump Sum $317,000.00
A1010 15702-1000 SOIL EROSION CONTROL, TEMPORARY DIVERSION CHANNEL
S & L Landscaping and Excavation Inc Lump Sum $900,000.00 MC Contractors, Inc Lump Sum $565,000.00 Central Southern Construction Corp Lump Sum $300,000.00 Granite Construction Company Lump Sum $749,000.00 Engineer's Estimate ALL LPSM Lump Sum $250,000.00
A1011 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
S & L Landscaping and Excavation Inc Lump Sum $15,000.00 MC Contractors, Inc Lump Sum $12,000.00 Central Southern Construction Corp Lump Sum $40,000.00 Granite Construction Company Lump Sum $10,000.00 Engineer's Estimate ALL LPSM Lump Sum $20,000.00
4 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1012 15802-0000 WATERING FOR DUST CONTROL
S & L Landscaping and Excavation Inc Lump Sum $200,000.00 MC Contractors, Inc Lump Sum $725,000.00 Central Southern Construction Corp Lump Sum $384,250.00 Granite Construction Company Lump Sum $110,000.00 Engineer's Estimate ALL LPSM Lump Sum $200,000.00
A1013 20101-0000 CLEARING AND GRUBBING
S & L Landscaping and Excavation Inc $12,000.00 $390,000.00 MC Contractors, Inc $19,550.00 $635,375.00 Central Southern Construction Corp $16,250.00 $528,125.00 Granite Construction Company $11,350.00 $368,875.00 Engineer's Estimate 32.5 ACRE $25,000.00 $812,500.00
A1014 20301-0300 REMOVAL OF BOX CULVERT
S & L Landscaping and Excavation Inc $15,000.00 $15,000.00 MC Contractors, Inc $60,000.00 $60,000.00 Central Southern Construction Corp $68,500.00 $68,500.00 Granite Construction Company $38,500.00 $38,500.00 Engineer's Estimate 1 EACH $40,000.00 $40,000.00
A1015 20301-1100 REMOVAL OF GATE
S & L Landscaping and Excavation Inc $2,000.00 $2,000.00 MC Contractors, Inc $1,500.00 $1,500.00 Central Southern Construction Corp $7,525.00 $7,525.00 Granite Construction Company $2,500.00 $2,500.00 Engineer's Estimate 1 EACH $1,500.00 $1,500.00
A1016 20301-2400 REMOVAL OF SIGN
S & L Landscaping and Excavation Inc $125.00 $10,000.00 MC Contractors, Inc $100.00 $8,000.00 Central Southern Construction Corp $120.00 $9,600.00 Granite Construction Company $268.00 $21,440.00 Engineer's Estimate 80 EACH $175.00 $14,000.00
A1017 20301-2800 REMOVAL OF STRUCTURES AND OBSTRUCTIONS (WATER VALVE VAULT)
S & L Landscaping and Excavation Inc $5,000.00 $10,000.00 MC Contractors, Inc $25,000.00 $50,000.00 Central Southern Construction Corp $2,106.00 $4,212.00 Granite Construction Company $6,825.00 $13,650.00 Engineer's Estimate 2 EACH $250.00 $500.00
5 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1018 20301-2800 REMOVAL OF STRUCTURES AND OBSTRUCTIONS (VAULT TOILET)
S & L Landscaping and Excavation Inc $7,000.00 $21,000.00 MC Contractors, Inc $25,000.00 $75,000.00 Central Southern Construction Corp $3,353.00 $10,059.00 Granite Construction Company $16,500.00 $49,500.00 Engineer's Estimate 3 EACH $13,500.00 $40,500.00
A1019 20302-2100 REMOVAL OF PIPE CULVERT
S & L Landscaping and Excavation Inc $30.00 $6,030.00 MC Contractors, Inc $40.00 $8,040.00 Central Southern Construction Corp $100.00 $20,100.00 Granite Construction Company $69.00 $13,869.00 Engineer's Estimate 201 LNFT $60.00 $12,060.00
A1020 20303-0300 REMOVAL OF CONCRETE
S & L Landscaping and Excavation Inc $50.00 $2,000.00 MC Contractors, Inc $81.00 $3,240.00 Central Southern Construction Corp $210.00 $8,400.00 Granite Construction Company $78.00 $3,120.00 Engineer's Estimate 40 SQYD $60.00 $2,400.00
A1021 20401-0000 ROADWAY EXCAVATION
S & L Landscaping and Excavation Inc $35.00 $1,802,500.00 MC Contractors, Inc $26.78 $1,379,170.00 Central Southern Construction Corp $35.00 $1,802,500.00 Granite Construction Company $40.00 $2,060,000.00 Engineer's Estimate 51,500 CUYD $45.00 $2,317,500.00
A1022 20402-0000 SUBEXCAVATION
S & L Landscaping and Excavation Inc $60.00 $120,000.00 MC Contractors, Inc $65.00 $130,000.00 Central Southern Construction Corp $150.00 $300,000.00 Granite Construction Company $49.00 $98,000.00 Engineer's Estimate 2,000 CUYD $100.00 $200,000.00
A1023 20415-0000 SELECT TOPPING (BIORETENTION MEDIA)
S & L Landscaping and Excavation Inc $200.00 $18,000.00 MC Contractors, Inc $650.00 $58,500.00 Central Southern Construction Corp $154.00 $13,860.00 Granite Construction Company $300.00 $27,000.00 Engineer's Estimate 90 CUYD $200.00 $18,000.00
6 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1024 20441-0000 WASTE
S & L Landscaping and Excavation Inc $30.00 $97,200.00 MC Contractors, Inc $70.00 $226,800.00 Central Southern Construction Corp $23.00 $74,520.00 Granite Construction Company $140.00 $453,600.00 Engineer's Estimate 3,240 CUYD $25.00 $81,000.00
A1025 20465-0000 CONSERVE AND PLACE BOULDER
S & L Landscaping and Excavation Inc $200.00 $16,000.00 MC Contractors, Inc $200.00 $16,000.00 Central Southern Construction Corp $454.00 $36,320.00 Granite Construction Company $975.00 $78,000.00 Engineer's Estimate 80 EACH $225.00 $18,000.00
A1026 20701-1000 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 2, TYPE E
S & L Landscaping and Excavation Inc $4.00 $12,400.00 MC Contractors, Inc $8.00 $24,800.00 Central Southern Construction Corp $22.00 $68,200.00 Granite Construction Company $4.80 $14,880.00 Engineer's Estimate 3,100 SQYD $5.00 $15,500.00
A1027 20703-2000 GEOGRID, STABILIZATION
S & L Landscaping and Excavation Inc $7.00 $21,700.00 MC Contractors, Inc $8.00 $24,800.00 Central Southern Construction Corp $8.00 $24,800.00 Granite Construction Company $5.90 $18,290.00 Engineer's Estimate 3,100 SQYD $6.00 $18,600.00
A1028 21101-2000 ROADWAY OBLITERATION, METHOD 2
S & L Landscaping and Excavation Inc $50.00 $20,500.00 MC Contractors, Inc $50.00 $20,500.00 Central Southern Construction Corp $29.00 $11,890.00 Granite Construction Company $28.50 $11,685.00 Engineer's Estimate 410 SQYD $6.00 $2,460.00
A1029 25101-0100 PLACED RIPRAP, METHOD A, CLASS 1
S & L Landscaping and Excavation Inc $300.00 $39,000.00 MC Contractors, Inc $193.00 $25,090.00 Central Southern Construction Corp $251.00 $32,630.00 Granite Construction Company $494.00 $64,220.00 Engineer's Estimate 130 CUYD $150.00 $19,500.00
7 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1030 25101-0200 PLACED RIPRAP, METHOD A, CLASS 2
S & L Landscaping and Excavation Inc $300.00 $39,000.00 MC Contractors, Inc $193.00 $25,090.00 Central Southern Construction Corp $279.00 $36,270.00 Granite Construction Company $492.50 $64,025.00 Engineer's Estimate 130 CUYD $200.00 $26,000.00
A1031 25101-0300 PLACED RIPRAP, METHOD A, CLASS 3
S & L Landscaping and Excavation Inc $325.00 $55,250.00 MC Contractors, Inc $274.00 $46,580.00 Central Southern Construction Corp $285.00 $48,450.00 Granite Construction Company $447.75 $76,117.50 Engineer's Estimate 170 CUYD $220.00 $37,400.00
A1032 25101-0400 PLACED RIPRAP, METHOD A, CLASS 4
S & L Landscaping and Excavation Inc $350.00 $152,250.00 MC Contractors, Inc $274.00 $119,190.00 Central Southern Construction Corp $269.00 $117,015.00 Granite Construction Company $421.50 $183,352.50 Engineer's Estimate 435 CUYD $235.00 $102,225.00
A1033 25125-0000 BOULDER
S & L Landscaping and Excavation Inc $300.00 $81,000.00 MC Contractors, Inc $62.50 $16,875.00 Central Southern Construction Corp $570.00 $153,900.00 Granite Construction Company $745.00 $201,150.00 Engineer's Estimate 270 EACH $220.00 $59,400.00
A1034 25126-0000 REMOVE AND RESET BOULDER
S & L Landscaping and Excavation Inc $100.00 $52,000.00 MC Contractors, Inc $355.00 $184,600.00 Central Southern Construction Corp $998.00 $518,960.00 Granite Construction Company $505.50 $262,860.00 Engineer's Estimate 520 EACH $175.00 $91,000.00
A1035 25201-0000 SPECIAL ROCK EMBANKMENT (ROCK ARMORED SLOPE)
S & L Landscaping and Excavation Inc $350.00 $1,120,000.00 MC Contractors, Inc $271.00 $867,200.00 Central Southern Construction Corp $350.00 $1,120,000.00 Granite Construction Company $185.00 $592,000.00 Engineer's Estimate 3,200 CUYD $250.00 $800,000.00
8 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1036 25210-0000 ROCKERY (RETAINING WALL)
S & L Landscaping and Excavation Inc $30.00 $93,000.00 MC Contractors, Inc $121.00 $375,100.00 Central Southern Construction Corp $375.00 $1,162,500.00 Granite Construction Company $85.00 $263,500.00 Engineer's Estimate 3,100 SQFT $120.00 $372,000.00
A1037 25902-0000 SOIL NAIL RETAINING WALL
S & L Landscaping and Excavation Inc $300.00 $2,610,000.00 MC Contractors, Inc $205.00 $1,783,500.00 Central Southern Construction Corp $175.00 $1,522,500.00 Granite Construction Company $191.00 $1,661,700.00 Engineer's Estimate 8,700 SQFT $240.00 $2,088,000.00
A1038 25903-0000 VERIFICATION TEST NAIL
S & L Landscaping and Excavation Inc $8,000.00 $64,000.00 MC Contractors, Inc $8,700.00 $69,600.00 Central Southern Construction Corp $8,694.00 $69,552.00 Granite Construction Company $3,400.00 $27,200.00 Engineer's Estimate 8 EACH $1,800.00 $14,400.00
A1039 30101-0000 AGGREGATE BASE
S & L Landscaping and Excavation Inc $40.00 $1,000,000.00 MC Contractors, Inc $48.78 $1,219,500.00 Central Southern Construction Corp $55.00 $1,375,000.00 Granite Construction Company $50.00 $1,250,000.00 Engineer's Estimate 25,000 TON $35.00 $875,000.00
A1041 30203-2120 ROADWAY AGGREGATE, METHOD 2, SURFACE COURSE, 4-INCH DEPTH
S & L Landscaping and Excavation Inc $40.00 $24,000.00 MC Contractors, Inc $300.00 $180,000.00 Central Southern Construction Corp $39.00 $23,400.00 Granite Construction Company $81.00 $48,600.00 Engineer's Estimate 600 SQYD $25.00 $15,000.00
A1043 40101-5600 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH OR 3/4-INCH NOMINAL MAXIMUM SIZE
AGGREGATE, 0.3 TO <3 MILLION ESAL
S & L Landscaping and Excavation Inc $175.00 $2,012,500.00 MC Contractors, Inc $151.80 $1,745,700.00 Central Southern Construction Corp $181.00 $2,081,500.00 Granite Construction Company $175.00 $2,012,500.00 Engineer's Estimate 11,500 TON $155.00 $1,782,500.00
9 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1044 40105-3000 ANTISTRIP ADDITIVE, TYPE 3
S & L Landscaping and Excavation Inc $800.00 $96,000.00 MC Contractors, Inc $884.00 $106,080.00 Central Southern Construction Corp $1,100.00 $132,000.00 Granite Construction Company $323.00 $38,760.00 Engineer's Estimate 120 TON $400.00 $48,000.00
A1046 40601-0000 FOG SEAL
S & L Landscaping and Excavation Inc $1,000.00 $30,000.00 MC Contractors, Inc $884.00 $26,520.00 Central Southern Construction Corp $1,063.00 $31,890.00 Granite Construction Company $1,881.00 $56,430.00 Engineer's Estimate 30 TON $700.00 $21,000.00
A1047 40605-0000 BLOTTER
S & L Landscaping and Excavation Inc $100.00 $10,000.00 MC Contractors, Inc $71.50 $7,150.00 Central Southern Construction Corp $85.00 $8,500.00 Granite Construction Company $143.00 $14,300.00 Engineer's Estimate 100 TON $50.00 $5,000.00
A1048 41101-1000 PRIME COAT, METHOD 1
S & L Landscaping and Excavation Inc $1,000.00 $80,000.00 MC Contractors, Inc $775.00 $62,000.00 Central Southern Construction Corp $938.00 $75,040.00 Granite Construction Company $2,050.00 $164,000.00 Engineer's Estimate 80 TON $900.00 $72,000.00
A1049 41201-0000 TACK COAT
S & L Landscaping and Excavation Inc $1,500.00 $45,000.00 MC Contractors, Inc $1,265.00 $37,950.00 Central Southern Construction Corp $1,563.00 $46,890.00 Granite Construction Company $645.00 $19,350.00 Engineer's Estimate 30 TON $575.00 $17,250.00
A1050 55601-0500 BRIDGE RAILING, CONCRETE
S & L Landscaping and Excavation Inc $1,000.00 $55,000.00 MC Contractors, Inc $864.00 $47,520.00 Central Southern Construction Corp $719.00 $39,545.00 Granite Construction Company $1,989.00 $109,395.00 Engineer's Estimate 55 LNFT $400.00 $22,000.00
10 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1051 60103-0000 CONCRETE, HEADWALL (AND WINGWALL)
S & L Landscaping and Excavation Inc $60,000.00 $840,000.00 MC Contractors, Inc $58,700.00 $821,800.00 Central Southern Construction Corp $46,675.00 $653,450.00 Granite Construction Company $71,430.00 $1,000,020.00 Engineer's Estimate 14 EACH $50,000.00 $700,000.00
A1052 60103-0200 CONCRETE, HEADWALL FOR 42-INCH PIPE CULVERT
S & L Landscaping and Excavation Inc $35,000.00 $35,000.00 MC Contractors, Inc $40,000.00 $40,000.00 Central Southern Construction Corp $13,350.00 $13,350.00 Granite Construction Company $74,118.00 $74,118.00 Engineer's Estimate 1 EACH $8,000.00 $8,000.00
A1053 60201-0600 18-INCH PIPE CULVERT (RCP)
S & L Landscaping and Excavation Inc $200.00 $17,000.00 MC Contractors, Inc $198.00 $16,830.00 Central Southern Construction Corp $484.00 $41,140.00 Granite Construction Company $225.00 $19,125.00 Engineer's Estimate 85 LNFT $200.00 $17,000.00
A1054 60201-0600 18-INCH PIPE CULVERT (CMP)
S & L Landscaping and Excavation Inc $200.00 $38,000.00 MC Contractors, Inc $182.00 $34,580.00 Central Southern Construction Corp $497.00 $94,430.00 Granite Construction Company $225.00 $42,750.00 Engineer's Estimate 190 LNFT $175.00 $33,250.00
A1055 60201-0800 24-INCH PIPE CULVERT (CMP)
S & L Landscaping and Excavation Inc $225.00 $132,750.00 MC Contractors, Inc $210.00 $123,900.00 Central Southern Construction Corp $373.00 $220,070.00 Granite Construction Company $235.00 $138,650.00 Engineer's Estimate 590 LNFT $250.00 $147,500.00
A1056 60201-0800 24-INCH PIPE CULVERT (RCP)
S & L Landscaping and Excavation Inc $275.00 $30,250.00 MC Contractors, Inc $228.00 $25,080.00 Central Southern Construction Corp $318.00 $34,980.00 Granite Construction Company $235.00 $25,850.00 Engineer's Estimate 110 LNFT $250.00 $27,500.00
11 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1057 60201-0900 30-INCH PIPE CULVERT (CMP)
S & L Landscaping and Excavation Inc $300.00 $82,500.00 MC Contractors, Inc $265.00 $72,875.00 Central Southern Construction Corp $450.00 $123,750.00 Granite Construction Company $250.00 $68,750.00 Engineer's Estimate 275 LNFT $300.00 $82,500.00
A1058 60201-1000 36-INCH PIPE CULVERT (CMP)
S & L Landscaping and Excavation Inc $350.00 $59,500.00 MC Contractors, Inc $319.00 $54,230.00 Central Southern Construction Corp $549.00 $93,330.00 Granite Construction Company $300.00 $51,000.00 Engineer's Estimate 170 LNFT $350.00 $59,500.00
A1059 60201-1100 42-INCH PIPE CULVERT (CMP)
S & L Landscaping and Excavation Inc $400.00 $34,000.00 MC Contractors, Inc $350.00 $29,750.00 Central Southern Construction Corp $725.00 $61,625.00 Granite Construction Company $350.00 $29,750.00 Engineer's Estimate 85 LNFT $420.00 $35,700.00
A1060 60210-0600 END SECTION FOR 18-INCH PIPE CULVERT
S & L Landscaping and Excavation Inc $1,500.00 $12,000.00 MC Contractors, Inc $667.00 $5,336.00 Central Southern Construction Corp $2,135.00 $17,080.00 Granite Construction Company $2,250.00 $18,000.00 Engineer's Estimate 8 EACH $615.00 $4,920.00
A1061 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT
S & L Landscaping and Excavation Inc $2,000.00 $44,000.00 MC Contractors, Inc $862.00 $18,964.00 Central Southern Construction Corp $2,329.00 $51,238.00 Granite Construction Company $2,400.00 $52,800.00 Engineer's Estimate 22 EACH $1,000.00 $22,000.00
A1062 60210-0900 END SECTION FOR 30-INCH PIPE CULVERT
S & L Landscaping and Excavation Inc $2,500.00 $32,500.00 MC Contractors, Inc $1,610.00 $20,930.00 Central Southern Construction Corp $2,531.00 $32,903.00 Granite Construction Company $3,100.00 $40,300.00 Engineer's Estimate 13 EACH $1,700.00 $22,100.00
12 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1063 60210-1000 END SECTION FOR 36-INCH PIPE CULVERT
S & L Landscaping and Excavation Inc $3,500.00 $21,000.00 MC Contractors, Inc $2,172.00 $13,032.00 Central Southern Construction Corp $3,281.00 $19,686.00 Granite Construction Company $3,500.00 $21,000.00 Engineer's Estimate 6 EACH $2,600.00 $15,600.00
A1064 60210-1100 END SECTION FOR 42-INCH PIPE CULVERT
S & L Landscaping and Excavation Inc $4,000.00 $12,000.00 MC Contractors, Inc $3,440.00 $10,320.00 Central Southern Construction Corp $4,000.00 $12,000.00 Granite Construction Company $4,600.00 $13,800.00 Engineer's Estimate 3 EACH $3,000.00 $9,000.00
A1065 60220-0000 PRECAST REINFORCED CONCRETE BOX CULVERT
S & L Landscaping and Excavation Inc $8,000.00 $1,104,000.00 MC Contractors, Inc $3,000.00 $414,000.00 Central Southern Construction Corp $4,400.00 $607,200.00 Granite Construction Company $6,700.00 $924,600.00 Engineer's Estimate 138 LNFT $3,500.00 $483,000.00
A1066 60404-1000 CATCH BASIN, FLH TYPE 1 (DROP INLET)
S & L Landscaping and Excavation Inc $6,000.00 $54,000.00 MC Contractors, Inc $8,470.00 $76,230.00 Central Southern Construction Corp $7,613.00 $68,517.00 Granite Construction Company $6,200.00 $55,800.00 Engineer's Estimate 9 EACH $5,000.00 $45,000.00
A1067 60409-0900 INLET TOP, METAL FRAME AND GRATE, FLH TYPE 7
S & L Landscaping and Excavation Inc $3,000.00 $18,000.00 MC Contractors, Inc $2,500.00 $15,000.00 Central Southern Construction Corp $9,489.00 $56,934.00 Granite Construction Company $17,000.00 $102,000.00 Engineer's Estimate 6 EACH $13,000.00 $78,000.00
A1068 60410-0000 SPRINGBOX
S & L Landscaping and Excavation Inc $20,000.00 $120,000.00 MC Contractors, Inc $10,000.00 $60,000.00 Central Southern Construction Corp $7,125.00 $42,750.00 Granite Construction Company $7,075.00 $42,450.00 Engineer's Estimate 6 EACH $5,000.00 $30,000.00
13 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1069 60501-0000 STANDARD UNDERDRAIN SYSTEM
S & L Landscaping and Excavation Inc $100.00 $270,000.00 MC Contractors, Inc $130.00 $351,000.00 Central Southern Construction Corp $124.00 $334,800.00 Granite Construction Company $142.00 $383,400.00 Engineer's Estimate 2,700 LNFT $150.00 $405,000.00
A1070 60901-1700 CURB, CONCRETE, 18-INCH DEPTH
S & L Landscaping and Excavation Inc $45.00 $274,500.00 MC Contractors, Inc $51.00 $311,100.00 Central Southern Construction Corp $70.00 $427,000.00 Granite Construction Company $58.00 $353,800.00 Engineer's Estimate 6,100 LNFT $40.00 $244,000.00
A1071 60901-1700 CURB, CONCRETE, 18-INCH DEPTH (BIG WATER CURB RAMP)
S & L Landscaping and Excavation Inc $45.00 $2,025.00 MC Contractors, Inc $70.00 $3,150.00 Central Southern Construction Corp $80.00 $3,600.00 Granite Construction Company $77.00 $3,465.00 Engineer's Estimate 45 LNFT $40.00 $1,800.00
A1072 60902-1000 CURB AND GUTTER, CONCRETE, 12-INCH DEPTH (MOUNTABLE)
S & L Landscaping and Excavation Inc $45.00 $6,975.00 MC Contractors, Inc $58.00 $8,990.00 Central Southern Construction Corp $85.00 $13,175.00 Granite Construction Company $81.00 $12,555.00 Engineer's Estimate 155 LNFT $60.00 $9,300.00
A1073 60902-1000 CURB AND GUTTER, CONCRETE, 12-INCH DEPTH (SPILL)
S & L Landscaping and Excavation Inc $45.00 $20,475.00 MC Contractors, Inc $54.00 $24,570.00 Central Southern Construction Corp $90.00 $40,950.00 Granite Construction Company $76.00 $34,580.00 Engineer's Estimate 455 LNFT $60.00 $27,300.00
A1074 60902-1000 CURB AND GUTTER, CONCRETE, 12-INCH DEPTH (CATCH)
S & L Landscaping and Excavation Inc $45.00 $38,250.00 MC Contractors, Inc $52.00 $44,200.00 Central Southern Construction Corp $100.00 $85,000.00 Granite Construction Company $69.00 $58,650.00 Engineer's Estimate 850 LNFT $60.00 $51,000.00
14 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1075 60915-1000 WHEELSTOP, CONCRETE
S & L Landscaping and Excavation Inc $500.00 $18,000.00 MC Contractors, Inc $600.00 $21,600.00 Central Southern Construction Corp $562.00 $20,232.00 Granite Construction Company $750.00 $27,000.00 Engineer's Estimate 36 EACH $300.00 $10,800.00
A1076 61501-0100 SIDEWALK, CONCRETE
S & L Landscaping and Excavation Inc $100.00 $60,000.00 MC Contractors, Inc $92.00 $55,200.00 Central Southern Construction Corp $116.00 $69,600.00 Granite Construction Company $130.00 $78,000.00 Engineer's Estimate 600 SQYD $60.00 $36,000.00
A1077 61503-2000 MEDIAN, EXPOSED AGGREGATE CONCRETE (RIVER ROCK INLAY)
S & L Landscaping and Excavation Inc $300.00 $180,000.00 MC Contractors, Inc $373.00 $223,800.00 Central Southern Construction Corp $159.00 $95,400.00 Granite Construction Company $385.00 $231,000.00 Engineer's Estimate 600 SQYD $225.00 $135,000.00
A1078 61509-0000 DETECTABLE WARNING PANELS
S & L Landscaping and Excavation Inc $1,000.00 $21,000.00 MC Contractors, Inc $490.00 $10,290.00 Central Southern Construction Corp $438.00 $9,198.00 Granite Construction Company $575.00 $12,075.00 Engineer's Estimate 21 SQYD $600.00 $12,600.00
A1079 61902-2100 GATE, METAL, 30 FEET WIDTH
S & L Landscaping and Excavation Inc $40,000.00 $40,000.00 MC Contractors, Inc $10,000.00 $10,000.00 Central Southern Construction Corp $9,375.00 $9,375.00 Granite Construction Company $25,000.00 $25,000.00 Engineer's Estimate 1 EACH $30,000.00 $30,000.00
A1080 61921-1000 REMOVE AND RESET FENCE
S & L Landscaping and Excavation Inc $25.00 $6,400.00 MC Contractors, Inc $39.00 $9,984.00 Central Southern Construction Corp $19.00 $4,864.00 Granite Construction Company $74.00 $18,944.00 Engineer's Estimate 256 LNFT $30.00 $7,680.00
15 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1081 62011-5100 STONE MASONRY CAP
S & L Landscaping and Excavation Inc $5,000.00 $5,000.00 MC Contractors, Inc $10,000.00 $10,000.00 Central Southern Construction Corp $44,063.00 $44,063.00 Granite Construction Company $31,400.00 $31,400.00 Engineer's Estimate 1 EACH $500.00 $500.00
A1082 62013-2000 STONE MASONRY WALL
S & L Landscaping and Excavation Inc $2,000.00 $4,000.00 MC Contractors, Inc $2,500.00 $5,000.00 Central Southern Construction Corp $56,219.00 $112,438.00 Granite Construction Company $43,000.00 $86,000.00 Engineer's Estimate 2 SQYD $2,500.00 $5,000.00
A1083 62201-0200 DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY
S & L Landscaping and Excavation Inc $150.00 $12,000.00 MC Contractors, Inc $125.00 $10,000.00 Central Southern Construction Corp $150.00 $12,000.00 Granite Construction Company $155.00 $12,400.00 Engineer's Estimate 80 HOUR $160.00 $12,800.00
A1084 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH
S & L Landscaping and Excavation Inc $100.00 $8,000.00 MC Contractors, Inc $120.00 $9,600.00 Central Southern Construction Corp $150.00 $12,000.00 Granite Construction Company $161.00 $12,880.00 Engineer's Estimate 80 HOUR $160.00 $12,800.00
A1085 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY
S & L Landscaping and Excavation Inc $175.00 $14,000.00 MC Contractors, Inc $150.00 $12,000.00 Central Southern Construction Corp $150.00 $12,000.00 Granite Construction Company $175.00 $14,000.00 Engineer's Estimate 80 HOUR $170.00 $13,600.00
A1086 62201-1300 BULLDOZER, 160HP MINIMUM FLYWHEEL POWER
S & L Landscaping and Excavation Inc $175.00 $14,000.00 MC Contractors, Inc $250.00 $20,000.00 Central Southern Construction Corp $238.00 $19,040.00 Granite Construction Company $238.00 $19,040.00 Engineer's Estimate 80 HOUR $200.00 $16,000.00
16 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1087 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE
S & L Landscaping and Excavation Inc $175.00 $14,000.00 MC Contractors, Inc $160.00 $12,800.00 Central Southern Construction Corp $238.00 $19,040.00 Granite Construction Company $229.00 $18,320.00 Engineer's Estimate 80 HOUR $225.00 $18,000.00
A1088 62201-3350 HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY
S & L Landscaping and Excavation Inc $175.00 $14,000.00 MC Contractors, Inc $185.00 $14,800.00 Central Southern Construction Corp $175.00 $14,000.00 Granite Construction Company $211.00 $16,880.00 Engineer's Estimate 80 HOUR $215.00 $17,200.00
A1089 62301-0000 GENERAL LABOR
S & L Landscaping and Excavation Inc $50.00 $12,000.00 MC Contractors, Inc $65.00 $15,600.00 Central Southern Construction Corp $50.00 $12,000.00 Granite Construction Company $65.00 $15,600.00 Engineer's Estimate 240 HOUR $85.00 $20,400.00
A1090 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES
S & L Landscaping and Excavation Inc $100.00 $16,000.00 MC Contractors, Inc $200.00 $32,000.00 Central Southern Construction Corp $238.00 $38,080.00 Granite Construction Company $200.00 $32,000.00 Engineer's Estimate 160 HOUR $150.00 $24,000.00
A1091 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES
S & L Landscaping and Excavation Inc $125.00 $25,000.00 MC Contractors, Inc $200.00 $40,000.00 Central Southern Construction Corp $238.00 $47,600.00 Granite Construction Company $155.00 $31,000.00 Engineer's Estimate 200 HOUR $200.00 $40,000.00
A1092 62406-0300 PLACING CONSERVED TOPSOIL, 4-INCH DEPTH
S & L Landscaping and Excavation Inc $8,000.00 $113,600.00 MC Contractors, Inc $6,600.00 $93,720.00 Central Southern Construction Corp $5,369.00 $76,239.80 Granite Construction Company $23,000.00 $326,600.00 Engineer's Estimate 14.2 ACRE $10,000.00 $142,000.00
17 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1093 62510-2000 SEEDING, HYDRAULIC METHOD
S & L Landscaping and Excavation Inc $3,000.00 $42,600.00 MC Contractors, Inc $4,040.00 $57,368.00 Central Southern Construction Corp $4,369.00 $62,039.80 Granite Construction Company $1,250.00 $17,750.00 Engineer's Estimate 14.2 ACRE $2,500.00 $35,500.00
A1094 62636-2000 BUNDLES, WILLOW
S & L Landscaping and Excavation Inc $50.00 $10,000.00 MC Contractors, Inc $500.00 $100,000.00 Central Southern Construction Corp $125.00 $25,000.00 Granite Construction Company $150.00 $30,000.00 Engineer's Estimate 200 EACH $100.00 $20,000.00
A1095 62901-1400 ROLLED EROSION CONTROL PRODUCT, TYPE 5.C
S & L Landscaping and Excavation Inc $8.00 $56,000.00 MC Contractors, Inc $15.00 $105,000.00 Central Southern Construction Corp $2.00 $14,000.00 Granite Construction Company $6.50 $45,500.00 Engineer's Estimate 7,000 SQYD $12.00 $84,000.00
A1096 63301-0000 SIGN SYSTEM
S & L Landscaping and Excavation Inc $750.00 $80,250.00 MC Contractors, Inc $1,645.00 $176,015.00 Central Southern Construction Corp $803.00 $85,921.00 Granite Construction Company $1,625.00 $173,875.00 Engineer's Estimate 107 EACH $850.00 $90,950.00
A1097 63308-3000 OBJECT MARKER, TYPE 3
S & L Landscaping and Excavation Inc $600.00 $60,000.00 MC Contractors, Inc $271.00 $27,100.00 Central Southern Construction Corp $603.00 $60,300.00 Granite Construction Company $268.00 $26,800.00 Engineer's Estimate 100 EACH $250.00 $25,000.00
A1098 63318-1000 SNOW POLE HOLDER (TYPE 3)
S & L Landscaping and Excavation Inc $2,000.00 $26,000.00 MC Contractors, Inc $600.00 $7,800.00 Central Southern Construction Corp $813.00 $10,569.00 Granite Construction Company $1,410.00 $18,330.00 Engineer's Estimate 13 EACH $350.00 $4,550.00
18 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1099 63318-1000 SNOW POLE HOLDER (TYPE 2)
S & L Landscaping and Excavation Inc $1,000.00 $1,000.00 MC Contractors, Inc $500.00 $500.00 Central Southern Construction Corp $813.00 $813.00 Granite Construction Company $1,275.00 $1,275.00 Engineer's Estimate 1 EACH $300.00 $300.00
A1100 63318-1000 SNOW POLE HOLDER (TYPE 1)
S & L Landscaping and Excavation Inc $1,000.00 $34,000.00 MC Contractors, Inc $380.00 $12,920.00 Central Southern Construction Corp $813.00 $27,642.00 Granite Construction Company $550.00 $18,700.00 Engineer's Estimate 34 EACH $275.00 $9,350.00
A1101 63401-0850 PAVEMENT MARKINGS, TYPE D, DOTTED (4-INCH, WHITE)
S & L Landscaping and Excavation Inc $3.00 $2,553.00 MC Contractors, Inc $1.75 $1,489.25 Central Southern Construction Corp $2.00 $1,702.00 Granite Construction Company $2.00 $1,702.00 Engineer's Estimate 851 LNFT $3.00 $2,553.00
A1102 63401-1500 PAVEMENT MARKINGS, TYPE H, SOLID (YIELD TRIANGLES)
S & L Landscaping and Excavation Inc $70.00 $15,120.00 MC Contractors, Inc $69.30 $14,968.80 Central Southern Construction Corp $75.00 $16,200.00 Granite Construction Company $68.00 $14,688.00 Engineer's Estimate 216 LNFT $10.00 $2,160.00
A1103 63401-1500 PAVEMENT MARKINGS, TYPE H, SOLID (24-INCH, WHITE)
S & L Landscaping and Excavation Inc $20.00 $30,960.00 MC Contractors, Inc $20.20 $31,269.60 Central Southern Construction Corp $22.00 $34,056.00 Granite Construction Company $20.00 $30,960.00 Engineer's Estimate 1,548 LNFT $10.00 $15,480.00
A1104 63401-1500 PAVEMENT MARKINGS, TYPE H, SOLID (4-INCH, WHITE)
S & L Landscaping and Excavation Inc $10.00 $8,230.00 MC Contractors, Inc $8.00 $6,584.00 Central Southern Construction Corp $9.00 $7,407.00 Granite Construction Company $8.00 $6,584.00 Engineer's Estimate 823 LNFT $5.00 $4,115.00
19 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1105 63402-0700 PAVEMENT MARKINGS, TYPE D, SOLID (4-INCH, WHITE)
S & L Landscaping and Excavation Inc $7,000.00 $71,400.00 MC Contractors, Inc $6,930.00 $70,686.00 Central Southern Construction Corp $7,500.00 $76,500.00 Granite Construction Company $6,850.00 $69,870.00 Engineer's Estimate 10.2 MILE $4,200.00 $42,840.00
A1106 63402-0700 PAVEMENT MARKINGS, TYPE D, SOLID (4-INCH, DOUBLE YELLOW)
S & L Landscaping and Excavation Inc $7,500.00 $86,250.00 MC Contractors, Inc $6,930.00 $79,695.00 Central Southern Construction Corp $7,500.00 $86,250.00 Granite Construction Company $6,850.00 $78,775.00 Engineer's Estimate 11.5 MILE $5,000.00 $57,500.00
A1107 63405-2890 PAVEMENT MARKINGS, TYPE H (SHARROW)
S & L Landscaping and Excavation Inc $300.00 $21,000.00 MC Contractors, Inc $277.00 $19,390.00 Central Southern Construction Corp $300.00 $21,000.00 Granite Construction Company $274.00 $19,180.00 Engineer's Estimate 70 EACH $250.00 $17,500.00
A1108 63405-2890 PAVEMENT MARKINGS, TYPE H (SYMBOLS, BICYCLIST)
S & L Landscaping and Excavation Inc $500.00 $3,500.00 MC Contractors, Inc $375.00 $2,625.00 Central Southern Construction Corp $406.00 $2,842.00 Granite Construction Company $371.00 $2,597.00 Engineer's Estimate 7 EACH $250.00 $1,750.00
A1109 63405-2950 PAVEMENT MARKINGS, TYPE H, STRAIGHT ARROW
S & L Landscaping and Excavation Inc $300.00 $6,000.00 MC Contractors, Inc $219.00 $4,380.00 Central Southern Construction Corp $238.00 $4,760.00 Granite Construction Company $217.00 $4,340.00 Engineer's Estimate 20 EACH $300.00 $6,000.00
A1110 63405-3250 PAVEMENT MARKINGS, TYPE H, ACCESSIBILITY SYMBOL
S & L Landscaping and Excavation Inc $500.00 $4,500.00 MC Contractors, Inc $375.00 $3,375.00 Central Southern Construction Corp $406.00 $3,654.00 Granite Construction Company $371.00 $3,339.00 Engineer's Estimate 9 EACH $425.00 $3,825.00
20 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1111 63501-0000 TEMPORARY TRAFFIC CONTROL
S & L Landscaping and Excavation Inc Lump Sum $500,000.00 MC Contractors, Inc Lump Sum $25,000.00 Central Southern Construction Corp Lump Sum $226,663.00 Granite Construction Company Lump Sum $228,000.00 Engineer's Estimate ALL LPSM Lump Sum $476,000.00
A1112 63601-3000 SYSTEM INSTALLATION, ELECTRICAL
S & L Landscaping and Excavation Inc Lump Sum $50,000.00 MC Contractors, Inc Lump Sum $250,000.00 Central Southern Construction Corp Lump Sum $19,063.00 Granite Construction Company Lump Sum $57,000.00 Engineer's Estimate ALL LPSM Lump Sum $20,000.00
A1113 63621-1000 UTILITY BOX, PULLBOX (TELECOMMUNICATIONS)
S & L Landscaping and Excavation Inc $3,500.00 $56,000.00 MC Contractors, Inc $5,600.00 $89,600.00 Central Southern Construction Corp $2,725.00 $43,600.00 Granite Construction Company $8,550.00 $136,800.00 Engineer's Estimate 16 EACH $700.00 $11,200.00
A1114 63621-1000 UTILITY BOX, PULLBOX (POWER)
S & L Landscaping and Excavation Inc $3,500.00 $77,000.00 MC Contractors, Inc $6,030.00 $132,660.00 Central Southern Construction Corp $2,875.00 $63,250.00 Granite Construction Company $23,350.00 $513,700.00 Engineer's Estimate 22 EACH $5,000.00 $110,000.00
A1115 63622-0000 UTILITY TRENCH (TELECOMMUNICATIONS)
S & L Landscaping and Excavation Inc $30.00 $20,250.00 MC Contractors, Inc $62.00 $41,850.00 Central Southern Construction Corp $100.00 $67,500.00 Granite Construction Company $100.00 $67,500.00 Engineer's Estimate 675 LNFT $30.00 $20,250.00
A1116 63622-0000 UTILITY TRENCH (JOINT)
S & L Landscaping and Excavation Inc $45.00 $711,000.00 MC Contractors, Inc $66.50 $1,050,700.00 Central Southern Construction Corp $112.00 $1,769,600.00 Granite Construction Company $109.00 $1,722,200.00 Engineer's Estimate 15,800 LNFT $45.00 $711,000.00
21 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1117 63622-0000 UTILITY TRENCH (POWER)
S & L Landscaping and Excavation Inc $35.00 $17,500.00 MC Contractors, Inc $63.00 $31,500.00 Central Southern Construction Corp $101.00 $50,500.00 Granite Construction Company $75.00 $37,500.00 Engineer's Estimate 500 LNFT $30.00 $15,000.00
A1118 64603-0800 FIXTURE, KIOSK (DOUBLE PANEL)
S & L Landscaping and Excavation Inc $20,000.00 $80,000.00 MC Contractors, Inc $10,300.00 $41,200.00 Central Southern Construction Corp $13,313.00 $53,252.00 Granite Construction Company $8,500.00 $34,000.00 Engineer's Estimate 4 EACH $17,000.00 $68,000.00
A1119 64603-0800 FIXTURE, KIOSK (NARROW SINGLE PANEL)
S & L Landscaping and Excavation Inc $15,000.00 $15,000.00 MC Contractors, Inc $7,250.00 $7,250.00 Central Southern Construction Corp $7,589.00 $7,589.00 Granite Construction Company $4,775.00 $4,775.00 Engineer's Estimate 1 EACH $7,500.00 $7,500.00
A1120 64603-0800 FIXTURE, KIOSK (SINGLE PANEL)
S & L Landscaping and Excavation Inc $15,000.00 $15,000.00 MC Contractors, Inc $7,500.00 $7,500.00 Central Southern Construction Corp $10,425.00 $10,425.00 Granite Construction Company $4,775.00 $4,775.00 Engineer's Estimate 1 EACH $10,000.00 $10,000.00
A1121 64603-1000 FIXTURE, VAULT TOILET (DOUBLE)
S & L Landscaping and Excavation Inc $150,000.00 $150,000.00 MC Contractors, Inc $90,320.00 $90,320.00 Central Southern Construction Corp $125,425.00 $125,425.00 Granite Construction Company $102,800.00 $102,800.00 Engineer's Estimate 1 EACH $120,000.00 $120,000.00
A1122 64603-1000 FIXTURE, VAULT TOILET (SINGLE)
S & L Landscaping and Excavation Inc $100,000.00 $600,000.00 MC Contractors, Inc $56,000.00 $336,000.00 Central Southern Construction Corp $73,437.00 $440,622.00 Granite Construction Company $60,300.00 $361,800.00 Engineer's Estimate 6 EACH $100,000.00 $600,000.00
22 out of 22
Project No: UT FLAP SLA 10(1)
Project Name: Mill Creek Canyon Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1123 64605-0000 FIXTURE (INTERPRETIVE RAIL FOOTING)
S & L Landscaping and Excavation Inc Lump Sum $20,000.00 MC Contractors, Inc Lump Sum $85,000.00 Central Southern Construction Corp Lump Sum $21,875.00 Granite Construction Company Lump Sum $26,300.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00
A1124 64620-1100 REMOVE AND RESET KIOSK
S & L Landscaping and Excavation Inc $5,000.00 $10,000.00 MC Contractors, Inc $3,750.00 $7,500.00 Central Southern Construction Corp $3,438.00 $6,876.00 Granite Construction Company $2,500.00 $5,000.00 Engineer's Estimate 2 EACH $500.00 $1,000.00
A1125 64704-1000 MITIGATION, STREAMBED MATERIAL
S & L Landscaping and Excavation Inc $150.00 $60,000.00 MC Contractors, Inc $90.00 $36,000.00 Central Southern Construction Corp $206.00 $82,400.00 Granite Construction Company $486.00 $194,400.00 Engineer's Estimate 400 CUYD $200.00 $80,000.00
Total Schedule - All Items
S & L Landscaping and Excavation Inc $22,298,868.00 MC Contractors, Inc $23,285,191.82 Central Southern Construction Corp $24,984,426.60 Granite Construction Company $25,221,706.00 Engineer's Estimate $20,578,105.00