Amendment A002.pdf

PDF 699 KB Posted

Attached to
CO FLAP SH 5(1) Mount Blue Sky Highway
Solicitation number
6982AF24B000009
Issued by

About this file

This document is an amendment (A002) to a solicitation for a federal construction contract for the CO FLAP SH5(1) Mount Blue Sky Highway project. The key changes in this amendment include:

  • Revising the requirements for conserving topsoil and wetland sod from roadway excavation and embankment areas. Conserved topsoil and sod must be stockpiled separately for later reuse.
  • Adding requirements for controlled blasting methods when excavating rock, and limiting excavation/embankment foundation preparation to areas that can be completed in one shift.
  • Modifying the embankment construction requirements, including conducting a pre-construction meeting and constructing a control strip.
  • Adding a new cross-section drawing (XSS 53+00) to the plans.

The overall project involves reconstructing 0.7 miles of Colorado State Highway 5, which is located in the Arapaho and Roosevelt National Forest and designated as a Scenic Byway. The project is anticipated to cost between $5-10 million and is scheduled for construction from July 2024 to October 2025.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

2. AMENDMENT/MODIFICATION NUMBER

A002

*FAILURE TO ACKNOWLEDGE THIS AMENDMENT IN BLOCK 19 OF THE SF 1442 BY THE DESIGNATED DATE AND HOUR SPECIFIED IN THE SOLICITATION MAY RESULT IN REJECTION OF YOUR BID (REFER TO ITEM 11.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

FEDERAL HIGHWAY ADMINISTRATION

CENTRAL FEDERAL LANDS HIGHWAY DIVISION

12300 WEST DAKOTA AVENUE, SUITE 360

LAKEWOOD, COLORADO 80228

ATTENTION: STEPHANIE NAVARRO

9A. AMENDMENT OF SOLICITATION NUMBER

6982AF24B000009

5. PROJECT NUMBER (If applicable)

CO FLAP SH5(1)

6/12/2024

9B. DATED (SEE ITEM 11)

5/20/2024

0*

*See Item 14 x

INVITATION FOR BID- E Section Replace page E-41 with the attached amended page E-41

INVITATION FOR BID- Cross Sections Replace sheet X36 with the attached amended page X36

E‐41

CO FLAP SH5(1)

Mount Blue Sky Highway

(c) Conserved Topsoil. Delete the subsection and substitute the following:

(c) Conserve Topsoil and Wetland Sod. Excavated material conserved from roadway excavation and embankment foundation areas that is suitable for growth of grass, cover crops, and native vegetation.

Materials

204.03. Add the following:

Geotextile 714.01(a) Granular Backfill 703.03(c) Riprap, Class 1 705.02 Stabilization Geogrid 714.03 Asphalt concrete 403, Type II

Construction Requirements

204.05 Conserved Topsoil. Delete the subsection and substitute the following:

204.05 Conserved Topsoil and Wetland Sod.

Conserve 4 inches of topsoil and 4 inches of wetland sod from the roadway excavation and from embankment foundation areas by the CO. Stockpile topsoil and wetland sod at staging location, as directed by CO. Separate topsoil and wetland sod from other excavated material.

204.06 Roadway Excavation.

(a) Rock cuts. Add the following:

When blasting rock, use controlled blasting methods according to Subsection 205.08(b).

204.09 Prepare Foundation for Embankment Construction: Add the following paragraph to end of section:

Limit excavation and embankment foundation preparation to an area of embankment construction that can be completed in one shift. Place and compact first lift of embankment material within 12 hours of starting excavation and foundation preparation.

204.10 Embankment Construction. Delete the first paragraph and substitute the following:

Conduct a pre-embankment construction preparatory phase meeting at least 3 days before the start of operations according to Subsection 153.04(a). Produce or stockpile sufficient class 1 riprap to construct a 25-foot (7.6 meters) long control strip, full bottom width, and a lift thickness of 24 inches.

Construct the control strip at a location approved by CO. Complete first layer of all rock embankment work between August 1 and June 1.

Miguel Martinez (Designer) Cloud

Miguel Martinez (Designer) Text Box AMENDMENT A002 Revised 06/12/2024

Amendment A002 Dated 6/12/24

Miguel Martinez (Designer) Cloud

Miguel Martinez (Designer) Cloud

Miguel Martinez (Designer) Text Box AMENDMENT A002: Add XSS 53+00 to plans

Miguel Martinez (Designer) Polygon

Miguel Martinez (Designer) Text Box

Miguel Martinez (Designer) Text Box

Miguel Martinez (Designer) Polygon