Signed Tabulation of Bids.pdf

PDF 700 KB Posted

Attached to
CA ERFO PLUMAS NF 23N18(1), Frazier Creek Bridge
Solicitation number
6982AF22B000029
Issued by

About this file

This document is a tabulation of bids report for the CA ERFO PLUMAS NF 23N18(1) federal contract opportunity to replace the Frazier Creek Bridge in Plumas National Forest, California. The bridge and portions of the roadway approaches will be reconstructed and overlaid with asphalt to reduce sediment runoff. Two contractors submitted bids by November 1st: Genesis Design and Development bid $2,365,336 while Steelhead Constructors JV bid $3,376,376. The engineer's estimate was $1,877,000. Key work includes mobilization, clearing and grubbing, excavation, riprap, structural concrete, prefabricated steel bridge installation, geosynthetic reinforced soil, guardrails, seeding and mulching. Equipment needs comprise dump trucks, backhoes, loaders, graders and excavators. The award date has not yet been determined.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tabulation of Bids Report Date: 11/02/22

1 out of 7Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO PLUMAS NF 23N18(1)

Project Name: Frazier Creek Bridge

Schedule: A

Schedule Type: Base

Solcitation No: 6982AF22B000029

Division: Central Federal Lands

State: CA County: Plumas

Federal Land: Opened at: Lakewood, CO

Opened by: Sheri Walsh

Date: 11/01/22

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Genesis Design and Development, LLC $2,365,336.00 7033 Kalgan Rd NE Rio Rancho, NM 87144

Steelhead Constructors JV $3,376,376.00 PO Box 536 Palo Cedro, CA 96073

Engineer's Estimate $1,877,000.00

Acquisition Program Specialist

2 out of 7Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO PLUMAS NF 23N18(1)

Project Name: Frazier Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0020 15101-0000 MOBILIZATION

Genesis Design and Development, LLC Lump Sum $215,100.00 Steelhead Constructors JV Lump Sum $694,946.00 Engineer's Estimate ALL LPSM Lump Sum $244,635.00

A0040 15206-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING STAKE

Genesis Design and Development, LLC $614,300.00 $30,715.00 Steelhead Constructors JV $100,000.00 $5,000.00 Engineer's Estimate 0.050 MILE $40,000.00 $2,000.00

A0060 15214-1000 SURVEY AND STAKING, BRIDGE

Genesis Design and Development, LLC Lump Sum $61,400.00 Steelhead Constructors JV Lump Sum $20,000.00 Engineer's Estimate ALL LPSM Lump Sum $18,000.00

A0080 15216-2000 SURVEY AND STAKING, GRADE FINISHING STAKES

Genesis Design and Development, LLC $307,100.00 $30,710.00 Steelhead Constructors JV $75,000.00 $7,500.00 Engineer's Estimate 0.100 MILE $65,000.00 $6,500.00

A0100 15301-0000 CONTRACTOR QUALITY CONTROL

Genesis Design and Development, LLC Lump Sum $141,500.00 Steelhead Constructors JV Lump Sum $80,000.00 Engineer's Estimate ALL LPSM Lump Sum $100,000.00

A0120 15401-0000 CONTRACTOR TESTING

Genesis Design and Development, LLC Lump Sum $100,000.00 Steelhead Constructors JV Lump Sum $50,000.00 Engineer's Estimate ALL LPSM Lump Sum $80,000.00

A0140 15501-0000 CONSTRUCTION SCHEDULE

Genesis Design and Development, LLC Lump Sum $12,000.00 Steelhead Constructors JV Lump Sum $10,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00

3 out of 7Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO PLUMAS NF 23N18(1)

Project Name: Frazier Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0160 15701-0000 SOIL EROSION CONTROL

Genesis Design and Development, LLC Lump Sum $50,000.00 Steelhead Constructors JV Lump Sum $25,000.00 Engineer's Estimate ALL LPSM Lump Sum $40,000.00

A0180 20101-0000 CLEARING AND GRUBBING

Genesis Design and Development, LLC $107,900.00 $43,160.00 Steelhead Constructors JV $125,000.00 $50,000.00 Engineer's Estimate 0.40 ACRE $35,000.00 $14,000.00

A0200 20303-1600 REMOVAL OF PAVEMENT, ASPHALT

Genesis Design and Development, LLC $44.00 $26,620.00 Steelhead Constructors JV $35.00 $21,175.00 Engineer's Estimate 605 SQYD $35.00 $21,175.00

A0220 20304-2000 REMOVAL OF BRIDGE

Genesis Design and Development, LLC Lump Sum $28,700.00 Steelhead Constructors JV Lump Sum $90,000.00 Engineer's Estimate ALL LPSM Lump Sum $175,000.00

A0240 20401-0000 ROADWAY EXCAVATION

Genesis Design and Development, LLC $450.00 $117,000.00 Steelhead Constructors JV $130.00 $33,800.00 Engineer's Estimate 260 CUYD $100.00 $26,000.00

A0260 20820-0000 DEWATERING

Genesis Design and Development, LLC Lump Sum $50,000.00 Steelhead Constructors JV Lump Sum $125,000.00 Engineer's Estimate ALL LPSM Lump Sum $60,000.00

A0280 25101-2500 PLACED RIPRAP, METHOD B, CLASS 5

Genesis Design and Development, LLC $372.00 $70,680.00 Steelhead Constructors JV $250.00 $47,500.00 Engineer's Estimate 190 CUYD $300.00 $57,000.00

4 out of 7Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO PLUMAS NF 23N18(1)

Project Name: Frazier Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0300 30202-2000 ROADWAY AGGREGATE, METHOD 2 (ROADWAY APPROACHES)

Genesis Design and Development, LLC $124.00 $31,000.00 Steelhead Constructors JV $125.00 $31,250.00 Engineer's Estimate 250 TON $100.00 $25,000.00

A0320 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1

Genesis Design and Development, LLC $307.00 $48,506.00 Steelhead Constructors JV $500.00 $79,000.00 Engineer's Estimate 158 TON $350.00 $55,300.00

A0340 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)

Genesis Design and Development, LLC $1,600.00 $30,400.00 Steelhead Constructors JV $5,750.00 $109,250.00 Engineer's Estimate 19 CUYD $2,500.00 $47,500.00

A0360 55401-1000 REINFORCING STEEL

Genesis Design and Development, LLC $6.00 $10,200.00 Steelhead Constructors JV $8.00 $13,600.00 Engineer's Estimate 1,700 LB $5.00 $8,500.00

A0380 55504-0000 PRE-FABRICATED STEEL BRIDGE (20'x52')

Genesis Design and Development, LLC Lump Sum $479,300.00 Steelhead Constructors JV Lump Sum $690,000.00 Engineer's Estimate ALL LPSM Lump Sum $275,000.00

A0400 57404-0000 GEOSYNTHETIC REINFORCED SOIL - INTERGRATED BRIDGE SYSTEM

Genesis Design and Development, LLC $231.00 $586,740.00 Steelhead Constructors JV $425.00 $1,079,500.00 Engineer's Estimate 2,540 SQFT $200.00 $508,000.00

A0420 61701-4150 GUARDRAIL SYSTEM CRG, TYPE 2, CLASS B

Genesis Design and Development, LLC $610.00 $15,250.00 Steelhead Constructors JV $275.00 $6,875.00 Engineer's Estimate 25 LNFT $140.00 $3,500.00

5 out of 7Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO PLUMAS NF 23N18(1)

Project Name: Frazier Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0440 61702-0400 TERMINAL SECTION, TYPE G4-CRT

Genesis Design and Development, LLC $6,100.00 $12,200.00 Steelhead Constructors JV $6,000.00 $12,000.00 Engineer's Estimate 2 EACH $7,000.00 $14,000.00

A0460 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT

Genesis Design and Development, LLC $6,100.00 $12,200.00 Steelhead Constructors JV $6,500.00 $13,000.00 Engineer's Estimate 2 EACH $7,000.00 $14,000.00

A0480 61707-0000 STRUCTURE TRANSITION RAILING

Genesis Design and Development, LLC $610.00 $30,500.00 Steelhead Constructors JV $350.00 $17,500.00 Engineer's Estimate 50 LNFT $175.00 $8,750.00

A0500 62201-0200 DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY

Genesis Design and Development, LLC $150.00 $3,000.00 Steelhead Constructors JV $200.00 $4,000.00 Engineer's Estimate 20 HOUR $170.00 $3,400.00

A0520 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH

Genesis Design and Development, LLC $180.00 $3,600.00 Steelhead Constructors JV $150.00 $3,000.00 Engineer's Estimate 20 HOUR $153.00 $3,060.00

A0540 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY

Genesis Design and Development, LLC $180.00 $3,600.00 Steelhead Constructors JV $225.00 $4,500.00 Engineer's Estimate 20 HOUR $220.00 $4,400.00

A0560 62201-2750 MOTOR GRADER

Genesis Design and Development, LLC $210.00 $4,200.00 Steelhead Constructors JV $250.00 $5,000.00 Engineer's Estimate 20 HOUR $200.00 $4,000.00

6 out of 7Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO PLUMAS NF 23N18(1)

Project Name: Frazier Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0580 62201-3350 HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY

Genesis Design and Development, LLC $180.00 $3,600.00 Steelhead Constructors JV $250.00 $5,000.00 Engineer's Estimate 20 HOUR $220.00 $4,400.00

A0600 62301-0000 GENERAL LABOR

Genesis Design and Development, LLC $120.00 $2,400.00 Steelhead Constructors JV $90.00 $1,800.00 Engineer's Estimate 20 HOUR $80.00 $1,600.00

A0620 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES

Genesis Design and Development, LLC $150.00 $3,000.00 Steelhead Constructors JV $375.00 $7,500.00 Engineer's Estimate 20 HOUR $300.00 $6,000.00

A0640 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES

Genesis Design and Development, LLC $180.00 $3,600.00 Steelhead Constructors JV $375.00 $7,500.00 Engineer's Estimate 20 HOUR $265.00 $5,300.00

A0660 62511-2000 SEEDING, HYDRAULIC METHOD

Genesis Design and Development, LLC $11.00 $2,640.00 Steelhead Constructors JV $6.00 $1,440.00 Engineer's Estimate 240 SQYD $3.50 $840.00

A0680 62516-2000 MULCHING, HYDRAULIC METHOD

Genesis Design and Development, LLC $32.00 $7,680.00 Steelhead Constructors JV $6.00 $1,440.00 Engineer's Estimate 240 SQYD $3.50 $840.00

A0700 62520-0000 FERTILIZER

Genesis Design and Development, LLC $102,500.00 $5,125.00 Steelhead Constructors JV $2,000.00 $100.00 Engineer's Estimate 0.050 ACRE $2,000.00 $100.00

7 out of 7Source Selection Information - See FAR 2.101 & 3.104

Project No: CA ERFO PLUMAS NF 23N18(1)

Project Name: Frazier Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0720 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3

Genesis Design and Development, LLC $565.00 $2,260.00 Steelhead Constructors JV $350.00 $1,400.00 Engineer's Estimate 4 EACH $500.00 $2,000.00

A0740 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

Genesis Design and Development, LLC $150.00 $6,750.00 Steelhead Constructors JV $40.00 $1,800.00 Engineer's Estimate 45 SQFT $160.00 $7,200.00

A0760 63701-0000 FIELD OFFICE

Genesis Design and Development, LLC $80,000.00 $80,000.00 Steelhead Constructors JV $20,000.00 $20,000.00 Engineer's Estimate 1 EACH $20,000.00 $20,000.00

Total Schedule - All Items

Genesis Design and Development, LLC $2,365,336.00 Steelhead Constructors JV $3,376,376.00 Engineer's Estimate $1,877,000.00

2022-11-02T10:36:19-0600
ERIC J GROSSKREUZ