This document is a tabulation of bids report for the CA ERFO PLUMAS NF 23N18(1) federal contract opportunity to replace the Frazier Creek Bridge in Plumas National Forest, California. The bridge and portions of the roadway approaches will be reconstructed and overlaid with asphalt to reduce sediment runoff. Two contractors submitted bids by November 1st: Genesis Design and Development bid $2,365,336 while Steelhead Constructors JV bid $3,376,376. The engineer's estimate was $1,877,000. Key work includes mobilization, clearing and grubbing, excavation, riprap, structural concrete, prefabricated steel bridge installation, geosynthetic reinforced soil, guardrails, seeding and mulching. Equipment needs comprise dump trucks, backhoes, loaders, graders and excavators. The award date has not yet been determined.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tabulation of Bids Report Date: 11/02/22
1 out of 7Source Selection Information - See FAR 2.101 & 3.104
Project No: CA ERFO PLUMAS NF 23N18(1)
Project Name: Frazier Creek Bridge
Schedule: A
Schedule Type: Base
Solcitation No: 6982AF22B000029
Division: Central Federal Lands
State: CA County: Plumas
Federal Land: Opened at: Lakewood, CO
Opened by: Sheri Walsh
Date: 11/01/22
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Genesis Design and Development, LLC $2,365,336.00 7033 Kalgan Rd NE Rio Rancho, NM 87144
Steelhead Constructors JV $3,376,376.00 PO Box 536 Palo Cedro, CA 96073
Engineer's Estimate $1,877,000.00
Acquisition Program Specialist
2 out of 7Source Selection Information - See FAR 2.101 & 3.104
Project No: CA ERFO PLUMAS NF 23N18(1)
Project Name: Frazier Creek Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0020 15101-0000 MOBILIZATION
Genesis Design and Development, LLC Lump Sum $215,100.00 Steelhead Constructors JV Lump Sum $694,946.00 Engineer's Estimate ALL LPSM Lump Sum $244,635.00
A0040 15206-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING STAKE
Genesis Design and Development, LLC $614,300.00 $30,715.00 Steelhead Constructors JV $100,000.00 $5,000.00 Engineer's Estimate 0.050 MILE $40,000.00 $2,000.00
A0060 15214-1000 SURVEY AND STAKING, BRIDGE
Genesis Design and Development, LLC Lump Sum $61,400.00 Steelhead Constructors JV Lump Sum $20,000.00 Engineer's Estimate ALL LPSM Lump Sum $18,000.00
A0080 15216-2000 SURVEY AND STAKING, GRADE FINISHING STAKES
Genesis Design and Development, LLC $307,100.00 $30,710.00 Steelhead Constructors JV $75,000.00 $7,500.00 Engineer's Estimate 0.100 MILE $65,000.00 $6,500.00
A0100 15301-0000 CONTRACTOR QUALITY CONTROL
Genesis Design and Development, LLC Lump Sum $141,500.00 Steelhead Constructors JV Lump Sum $80,000.00 Engineer's Estimate ALL LPSM Lump Sum $100,000.00
A0120 15401-0000 CONTRACTOR TESTING
Genesis Design and Development, LLC Lump Sum $100,000.00 Steelhead Constructors JV Lump Sum $50,000.00 Engineer's Estimate ALL LPSM Lump Sum $80,000.00
A0140 15501-0000 CONSTRUCTION SCHEDULE
Genesis Design and Development, LLC Lump Sum $12,000.00 Steelhead Constructors JV Lump Sum $10,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00
3 out of 7Source Selection Information - See FAR 2.101 & 3.104
Project No: CA ERFO PLUMAS NF 23N18(1)
Project Name: Frazier Creek Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0160 15701-0000 SOIL EROSION CONTROL
Genesis Design and Development, LLC Lump Sum $50,000.00 Steelhead Constructors JV Lump Sum $25,000.00 Engineer's Estimate ALL LPSM Lump Sum $40,000.00
A0180 20101-0000 CLEARING AND GRUBBING
Genesis Design and Development, LLC $107,900.00 $43,160.00 Steelhead Constructors JV $125,000.00 $50,000.00 Engineer's Estimate 0.40 ACRE $35,000.00 $14,000.00
A0200 20303-1600 REMOVAL OF PAVEMENT, ASPHALT
Genesis Design and Development, LLC $44.00 $26,620.00 Steelhead Constructors JV $35.00 $21,175.00 Engineer's Estimate 605 SQYD $35.00 $21,175.00
A0220 20304-2000 REMOVAL OF BRIDGE
Genesis Design and Development, LLC Lump Sum $28,700.00 Steelhead Constructors JV Lump Sum $90,000.00 Engineer's Estimate ALL LPSM Lump Sum $175,000.00
A0240 20401-0000 ROADWAY EXCAVATION
Genesis Design and Development, LLC $450.00 $117,000.00 Steelhead Constructors JV $130.00 $33,800.00 Engineer's Estimate 260 CUYD $100.00 $26,000.00
A0260 20820-0000 DEWATERING
Genesis Design and Development, LLC Lump Sum $50,000.00 Steelhead Constructors JV Lump Sum $125,000.00 Engineer's Estimate ALL LPSM Lump Sum $60,000.00
A0280 25101-2500 PLACED RIPRAP, METHOD B, CLASS 5
Genesis Design and Development, LLC $372.00 $70,680.00 Steelhead Constructors JV $250.00 $47,500.00 Engineer's Estimate 190 CUYD $300.00 $57,000.00
4 out of 7Source Selection Information - See FAR 2.101 & 3.104
Project No: CA ERFO PLUMAS NF 23N18(1)
Project Name: Frazier Creek Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0300 30202-2000 ROADWAY AGGREGATE, METHOD 2 (ROADWAY APPROACHES)
Genesis Design and Development, LLC $124.00 $31,000.00 Steelhead Constructors JV $125.00 $31,250.00 Engineer's Estimate 250 TON $100.00 $25,000.00
A0320 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1
Genesis Design and Development, LLC $307.00 $48,506.00 Steelhead Constructors JV $500.00 $79,000.00 Engineer's Estimate 158 TON $350.00 $55,300.00
A0340 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)
Genesis Design and Development, LLC $1,600.00 $30,400.00 Steelhead Constructors JV $5,750.00 $109,250.00 Engineer's Estimate 19 CUYD $2,500.00 $47,500.00
A0360 55401-1000 REINFORCING STEEL
Genesis Design and Development, LLC $6.00 $10,200.00 Steelhead Constructors JV $8.00 $13,600.00 Engineer's Estimate 1,700 LB $5.00 $8,500.00
A0380 55504-0000 PRE-FABRICATED STEEL BRIDGE (20'x52')
Genesis Design and Development, LLC Lump Sum $479,300.00 Steelhead Constructors JV Lump Sum $690,000.00 Engineer's Estimate ALL LPSM Lump Sum $275,000.00
A0400 57404-0000 GEOSYNTHETIC REINFORCED SOIL - INTERGRATED BRIDGE SYSTEM
Genesis Design and Development, LLC $231.00 $586,740.00 Steelhead Constructors JV $425.00 $1,079,500.00 Engineer's Estimate 2,540 SQFT $200.00 $508,000.00
A0420 61701-4150 GUARDRAIL SYSTEM CRG, TYPE 2, CLASS B
Genesis Design and Development, LLC $610.00 $15,250.00 Steelhead Constructors JV $275.00 $6,875.00 Engineer's Estimate 25 LNFT $140.00 $3,500.00
5 out of 7Source Selection Information - See FAR 2.101 & 3.104
Project No: CA ERFO PLUMAS NF 23N18(1)
Project Name: Frazier Creek Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0440 61702-0400 TERMINAL SECTION, TYPE G4-CRT
Genesis Design and Development, LLC $6,100.00 $12,200.00 Steelhead Constructors JV $6,000.00 $12,000.00 Engineer's Estimate 2 EACH $7,000.00 $14,000.00
A0460 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT
Genesis Design and Development, LLC $6,100.00 $12,200.00 Steelhead Constructors JV $6,500.00 $13,000.00 Engineer's Estimate 2 EACH $7,000.00 $14,000.00
A0480 61707-0000 STRUCTURE TRANSITION RAILING
Genesis Design and Development, LLC $610.00 $30,500.00 Steelhead Constructors JV $350.00 $17,500.00 Engineer's Estimate 50 LNFT $175.00 $8,750.00
A0500 62201-0200 DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY
Genesis Design and Development, LLC $150.00 $3,000.00 Steelhead Constructors JV $200.00 $4,000.00 Engineer's Estimate 20 HOUR $170.00 $3,400.00
A0520 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH
Genesis Design and Development, LLC $180.00 $3,600.00 Steelhead Constructors JV $150.00 $3,000.00 Engineer's Estimate 20 HOUR $153.00 $3,060.00
A0540 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY
Genesis Design and Development, LLC $180.00 $3,600.00 Steelhead Constructors JV $225.00 $4,500.00 Engineer's Estimate 20 HOUR $220.00 $4,400.00
A0560 62201-2750 MOTOR GRADER
Genesis Design and Development, LLC $210.00 $4,200.00 Steelhead Constructors JV $250.00 $5,000.00 Engineer's Estimate 20 HOUR $200.00 $4,000.00
6 out of 7Source Selection Information - See FAR 2.101 & 3.104
Project No: CA ERFO PLUMAS NF 23N18(1)
Project Name: Frazier Creek Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0580 62201-3350 HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY
Genesis Design and Development, LLC $180.00 $3,600.00 Steelhead Constructors JV $250.00 $5,000.00 Engineer's Estimate 20 HOUR $220.00 $4,400.00
A0600 62301-0000 GENERAL LABOR
Genesis Design and Development, LLC $120.00 $2,400.00 Steelhead Constructors JV $90.00 $1,800.00 Engineer's Estimate 20 HOUR $80.00 $1,600.00
A0620 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES
Genesis Design and Development, LLC $150.00 $3,000.00 Steelhead Constructors JV $375.00 $7,500.00 Engineer's Estimate 20 HOUR $300.00 $6,000.00
A0640 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES
Genesis Design and Development, LLC $180.00 $3,600.00 Steelhead Constructors JV $375.00 $7,500.00 Engineer's Estimate 20 HOUR $265.00 $5,300.00
A0660 62511-2000 SEEDING, HYDRAULIC METHOD
Genesis Design and Development, LLC $11.00 $2,640.00 Steelhead Constructors JV $6.00 $1,440.00 Engineer's Estimate 240 SQYD $3.50 $840.00
A0680 62516-2000 MULCHING, HYDRAULIC METHOD
Genesis Design and Development, LLC $32.00 $7,680.00 Steelhead Constructors JV $6.00 $1,440.00 Engineer's Estimate 240 SQYD $3.50 $840.00
A0700 62520-0000 FERTILIZER
Genesis Design and Development, LLC $102,500.00 $5,125.00 Steelhead Constructors JV $2,000.00 $100.00 Engineer's Estimate 0.050 ACRE $2,000.00 $100.00
7 out of 7Source Selection Information - See FAR 2.101 & 3.104
Project No: CA ERFO PLUMAS NF 23N18(1)
Project Name: Frazier Creek Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0720 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
Genesis Design and Development, LLC $565.00 $2,260.00 Steelhead Constructors JV $350.00 $1,400.00 Engineer's Estimate 4 EACH $500.00 $2,000.00
A0740 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
Genesis Design and Development, LLC $150.00 $6,750.00 Steelhead Constructors JV $40.00 $1,800.00 Engineer's Estimate 45 SQFT $160.00 $7,200.00
A0760 63701-0000 FIELD OFFICE
Genesis Design and Development, LLC $80,000.00 $80,000.00 Steelhead Constructors JV $20,000.00 $20,000.00 Engineer's Estimate 1 EACH $20,000.00 $20,000.00
Total Schedule - All Items
Genesis Design and Development, LLC $2,365,336.00 Steelhead Constructors JV $3,376,376.00 Engineer's Estimate $1,877,000.00