A001.pdf
PDF 566 KB Posted
- Attached to
- AZ NP GRCA 272(1) Mather Point Campground Loops Federal contract opportunity
- Solicitation number
- 6982AF22B000017
About this file
This document contains a federal contract solicitation and related opportunity. The solicitation seeks bids for the AZ NP GRCA 272(1) Mather Point Campground Loops project located in Grand Canyon Village, Coconino County, Arizona. The project scope involves rehabilitating approximately 2.37 miles of campground roads and campsite parking stalls at the Mather Point Campground within the South Rim of the Grand Canyon National Park. The work is broken into one schedule and two options, with Schedule A covering 1.51 miles and Options Y and Z covering additional road segments totaling 0.86 miles. Sealed bids are due by June 23, 2022. The contract will be awarded to the lowest priced technically acceptable bidder. The Department of Transportation Federal Highway Administration is the contracting agency.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Tabulation Mather Pt.pdf | ||
| Bid Opening Summary AZ NP GRCA 272 Mather Point.pdf | ||
| QnA 6.19.22.pdf | ||
| Questions and Answers During Solicitation AZ NP GRCA 272(1) MATHER POINT CAMPGROUND LOOPS 06172022.pdf | ||
| QnA 6.10.22.pdf | ||
| QnA 6.7.22.pdf | ||
| 6982AF22B000017.pdf | ||
| FP-14.pdf | ||
| Plan GRCA 272(1)_2022-04-26_Stamped.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
1 4
A001 06/10/2022 HFLCEO220206PR AZ NP GRCA 272(1)
FEDERAL HIGHWAY ADMINISTRATION
CENTRAL FEDERAL LANDS HIGHWAY DIVISION
12300 WEST DAKOTA AVENUE, SUITE 360
LAKEWOOD, COLORADO 80228
ATTENTION: LESLIE KARSTEN
6905001
6982AF22B000017
05/23/22
0*
*See Item 14
IFB
Remove and replace pages A-1, A-4, and B-8 with the attached corresponding pages.
*FAILURE TO ACKNOWLEDGE THIS AMENDMENT IN BLOCK 19 OF THE SF 1442 BY THE DESIGNATED DATE AND HOUR SPECIFIED IN THE
SOLICITATION MAY RESULT IN REJECTION OF YOUR BID (REFER TO ITEM 11.)
SOLICITATION, OFFER
AND AWARD
(Construction, Alteration or Repair)
1. SOLICITATION NO.
6982AF22B000017
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED
05/23/2022
PAGE OF
PAGES
IMPORTANT - THE "OFFER SECTION ON THE REVERSE MUST BE FULLY COMPLETED BY OFFEROR.
4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
HFLCEO220206PR
6. PROJECT NO.
AZ NP GRCA 272(1)
7. ISSUED BY:
FEDERAL HIGHWAY ADMINISTRATION
CENTRAL FEDERAL LANDS DIVISION
12300 WEST DAKOTA AVENUE, SUITE 167
LAKEWOOD, COLORADO 80228
CODE: 69050001 8. ADDRESS OFFER TO:
Leslie Karsten, Contract Specialist Federal Highway Administration Central Federal Lands Division Office 12300 W. Dakota Avenue Lakewood, CO 80228
9. FOR INFORMATION CALL
SEE PAGE A-3
A. NAME:
SEE PAGE A-3
B. TELEPHONE NO. (Include area code)
SEE PAGE A-3
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS:
ROADWAY CONSTRUCTION PROJECT IN STRICT ACCORDANCE WITH:
1. FEDERAL ACQUISITION AND TRANSPORATION ACQUISITION REGULATIONS (FAR & TAR)
2. DEPARTMENT OF LABOR, CONSTRUCTION WAGE RATE REQUIREMENT RATES
3. SPECIAL CONTRACT REQUIREMENTS
4. PLANS
5. BID SCHEDULE
6. STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY
PROJECTS, FP-14, U.S. CUSTOMARY UNITS
See Subsection 104.04 of the FP-14 for governing order of precedence
11. The Contractor shall begin performance within 10 calendar days and complete it within * calendar days after receiving award notice to proceed. The performance period is mandatory negotiable. *Refer to Subsection 108.01 as amended in the Special Contract Requirements.
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.) YES NO
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and 0 copies to perform the work required are due at the place specified in Item 8. by 2:00 p.m. (hour) local time on 06/23/2022. If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is is not required.
C. All offers are subject to the (1) work requirements and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
STANDARD FORM 1442 (REV. 8/2014)
Prescribed by GSA
FAR (48 CFR) 53.236-1(d)
X
X
X
X
X
A - 1
1:00 pm
Amendment A001 06/10/22
Leslie.Karsten Cross-Out
Bid Schedule Instructions
BIDDERS, PLEASE NOTE: This Bid Proposal is comprised of one schedule and two options.
Before preparing the bid, carefully read the Solicitation Provisions and the following:
• Insert a numeric unit bid price for each pay item for which a quantity appears in the bid schedule. Unit bid prices should be quoted no more precisely than the nearest cent (2 decimal places). Unit bid prices quoted more precisely will be rounded up to the nearest cent by the Government
• Multiply the unit price by the quantity for each pay item and show the amount bid.
When the words “Lump Sum” appear as a unit bid price, insert an amount for each lump sum pay item.
• Total all amounts bid for each pay item and show the Construction Cost Total on the space provided on the last page of each schedule or option.
• Also show the Construction Cost Total for each schedule/option as well as the combined Total of each Schedule and the Option in the spaces provided on the Bid Summary page.
NOTE: If the amount bid for a pay item is inconsistent with the product of the unit price provided by the bidder and the quantity provided by the Government, the unit price will govern and the Government will determine a corrected amount bid for the pay item by multiplying the unit price by the quantity.
Basis for Award
To be eligible for award of contract, the offeror shall submit prices for each item in Bid Schedule A and Option Y and Option Z. Accordingly, contract award will be made to the lowest responsible bidder conforming to the solicitation, provided funds are available.
Per FAR provision 52.217-5, Evaluation of Options (JULY 1990), the Government will evaluate offers for award purposes by adding the total price for all options to the total price for Schedule A. Evaluation of options will not obligate the Government to exercise the option(s). If the determination is made to exercise any of the Options, the Contracting Officer will provide the contractor with written notice no later than 30 days after contract award, per FAR clause 52.217-7, Option for Increased Quantity- Separately Priced Line Item (MAR 1989).
Per FAR provision 52.217-4, Evaluation of Options Exercised at Time of Contract Award, the Government will evaluate offers for award purposes by adding the total price for Schedule A together with any Option(s) exercised at the time of award, depending on funds availability. If the determination is made to exercise any of the Options, the Contracting Officer will provide the contractor with written notice no later than 30 days after contract award, per FAR clause 52.217-7, Option for Increased Quantity- Separately Priced Line Item
(MAR 1989).
A - 4 Amendment A001 06/10/22
B-8
52.214-19 Contract Award - Sealed Bidding - Construction. (AUG 1996)
52.214-31 Facsimile Bids (DEC 1989)
52.214-34 Submission of Offers in the English Language. (APR 1991)
52.214-35 Submission of Offers in U.S. Currency. (APR 1991)
52.215-5 Facsimile Proposals. (OCT 1997)
52.216-1 Type of Contract. (APR 1984)
The Government contemplates award of a FIRM FIXED PRICE contract resulting from this solicitation.
(End of provision)
52.217-5 Evaluation of Options (JUL 1990)
The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
(End of provision)
52.217-4 Evaluation of Options Exercised at Time of Contract Award. (JUNE 1988)
The Government will evaluate the total price for the basic requirement together with any option(s) exercised at the time of award.
(End of provision)
52.222-5 Construction Wage Rate Requirements Secondary Site of the Work. (MAY 2014)
52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction. (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the
Goals for Minority Participation for Each Trade
Goals for Female Participation for Each Trade
19.6% - Coconino County, AZ 6.9%
Amendment A001 06/10/22
File details come from the government source that posted it. Updated .