Questions and Answers During Advertisement for NV FLAP 39(1) King_s Canyon Road 05182021.pdf

PDF 94 KB Posted

Attached to
NV FLAP 39(1) King's Canyon Road
Solicitation number
6982AF20B000026
Issued by

About this file

This document contains questions and answers from a pre-solicitation conference call for Nevada Federal Lands Access Program Project No. 39(1) King's Canyon Road. The project involves road construction and culvert replacement. According to the questions and answers, there was no organized site visit scheduled for interested offerors. Snap-Tite direct bury HDPE pipe culvert would be allowable for the project if it meets contractual requirements. The lead agency is the U.S. Department of Transportation Federal Highway Administration.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers During Advertisement for NV FLAP 39(1) King's Canyon Road

Tuesday, May 18, 2021

Questions Answers

1 Will there be an organized site visit?

No. Please see Amendment A001. The B&C pages (provisions and clauses) for a different project were incorrectly added to this solicitation. The correct B&C pages are in Amendment A001 and they state that there is no organized site visit for this project.

2 Can Snap-Tite be used as the direct bury HDPE pipe culvert for this project?

If this product meets the requirements of the contract it is possible the contractor may elect to use this product. Central Federal Lands does not purchase products or materials for contract awardees.