This is a tabulation of bids report for a federal highway project to improve Kings Canyon Road located in Nevada. The project is solicited by the Department of Transportation Federal Highway Administration under solicitation number 6982AF20B000026. Two bids were received for the base schedule from Hooker Creek, Inc. at $3,040,546 and MKD Construction, Inc. at $3,951,373, with Hooker Creek, Inc. being the apparent low bidder. The engineer's estimate for the project was $3,525,000. The report provides line item details for over 170 pay items describing the required construction and installation work. Key aspects of the work include roadway construction, drainage structures, fencing, signs, erosion control, and temporary traffic control. The anticipated award date is not provided.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tabulation of Bids Report Date: 06/07/21

1 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: NV FLAP 39(1)

Project Name: Kings Canyon Road

Schedule: A

Schedule Type: Base

Solcitation No: 6982AF20B000026

Division: Central Federal Lands

State: NV County: Carson City

Federal Land: Hubmoldt-Toiyabe National Forest Opened at: Lakewood

Opened by: Josephine Helms

Date: 06/03/21

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Hooker Creek, Inc. $3,040,546.00 1015 Anderson St.

Red Bluff, CA 96080

MKD Construction, Inc. bid opening June 3, 2021 $3,951,373.00 20 Stokes Drive Mound House, NV 89706

Engineer's Estimate $3,525,000.00

2 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: NV FLAP 39(1)

Project Name: Kings Canyon Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0020 15101-0000 MOBILIZATION

Hooker Creek, Inc. Lump Sum $300,000.00 MKD Construction, Inc. Lump Sum $744,000.00 Engineer's Estimate ALL LPSM Lump Sum $373,395.00

A0040 15215-3000 SURVEY AND STAKING, DRAINAGE STRUCTURE

Hooker Creek, Inc. $950.00 $29,450.00 MKD Construction, Inc. $750.00 $23,250.00 Engineer's Estimate 31 EACH $1,000.00 $31,000.00

A0060 15215-5000 SURVEY AND STAKING, BOX CULVERT

Hooker Creek, Inc. $1,950.00 $1,950.00 MKD Construction, Inc. $2,950.00 $2,950.00 Engineer's Estimate 1 EACH $2,000.00 $2,000.00

A0080 15215-7000 SURVEY AND STAKING, PARKING AREA

Hooker Creek, Inc. $10,500.00 $10,500.00 MKD Construction, Inc. $25,960.00 $25,960.00 Engineer's Estimate 1 EACH $5,000.00 $5,000.00

A0100 15225-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING CONTROL

Hooker Creek, Inc. $20,000.00 $16,200.00 MKD Construction, Inc. $7,500.00 $6,075.00 Engineer's Estimate 0.810 MILE $8,000.00 $6,480.00

A0120 15236-2000 SURVEY CONTROL, GRADE FINISHING

Hooker Creek, Inc. $29,000.00 $46,980.00 MKD Construction, Inc. $12,500.00 $20,250.00 Engineer's Estimate 1.620 MILE $10,000.00 $16,200.00

A0140 15301-0000 CONTRACTOR QUALITY CONTROL

Hooker Creek, Inc. Lump Sum $85,000.00 MKD Construction, Inc. Lump Sum $14,750.00 Engineer's Estimate ALL LPSM Lump Sum $90,000.00

3 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: NV FLAP 39(1)

Project Name: Kings Canyon Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0160 15401-0000 CONTRACTOR TESTING

Hooker Creek, Inc. Lump Sum $72,000.00 MKD Construction, Inc. Lump Sum $92,040.00 Engineer's Estimate ALL LPSM Lump Sum $90,000.00

A0180 15501-0000 CONSTRUCTION SCHEDULE

Hooker Creek, Inc. Lump Sum $15,000.00 MKD Construction, Inc. Lump Sum $8,850.00 Engineer's Estimate ALL LPSM Lump Sum $15,000.00

A0200 15701-0000 SOIL EROSION CONTROL (EROSION CONTROL)

Hooker Creek, Inc. Lump Sum $6,600.00 MKD Construction, Inc. Lump Sum $15,270.00 Engineer's Estimate ALL LPSM Lump Sum $20,000.00

A0220 15701-0000 SOIL EROSION CONTROL (NON-STORMWATER CONTROL)

Hooker Creek, Inc. Lump Sum $8,200.00 MKD Construction, Inc. Lump Sum $5,040.00 Engineer's Estimate ALL LPSM Lump Sum $40,000.00

A0240 15701-0000 SOIL EROSION CONTROL (SEDIMENT CONTROL)

Hooker Creek, Inc. Lump Sum $14,000.00 MKD Construction, Inc. Lump Sum $7,410.00 Engineer's Estimate ALL LPSM Lump Sum $20,000.00

A0260 15720-0000 STORM WATER POLLUTION PREVENTION PLAN

Hooker Creek, Inc. Lump Sum $2,500.00 MKD Construction, Inc. Lump Sum $3,540.00 Engineer's Estimate ALL LPSM Lump Sum $20,000.00

A0280 15802-0000 WATERING FOR DUST CONTROL

Hooker Creek, Inc. Lump Sum $28,000.00 MKD Construction, Inc. Lump Sum $18,300.00 Engineer's Estimate ALL LPSM Lump Sum $35,000.00

4 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: NV FLAP 39(1)

Project Name: Kings Canyon Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0300 20101-0000 CLEARING AND GRUBBING

Hooker Creek, Inc. $6,200.00 $34,720.00 MKD Construction, Inc. $21,900.00 $122,640.00 Engineer's Estimate 5.6 ACRE $6,500.00 $36,400.00

A0320 20304-1000 REMOVAL OF STRUCTURES AND OBSTRUCTIONS

Hooker Creek, Inc. Lump Sum $29,000.00 MKD Construction, Inc. Lump Sum $54,800.00 Engineer's Estimate ALL LPSM Lump Sum $35,000.00

A0340 20401-0000 ROADWAY EXCAVATION

Hooker Creek, Inc. $14.00 $281,400.00 MKD Construction, Inc. $17.25 $346,725.00 Engineer's Estimate 20,100 CUYD $22.00 $442,200.00

A0360 20402-0000 SUBEXCAVATION

Hooker Creek, Inc. $100.00 $50,000.00 MKD Construction, Inc. $128.00 $64,000.00 Engineer's Estimate 500 CUYD $85.00 $42,500.00

A0380 20441-0000 WASTE

Hooker Creek, Inc. $20.00 $25,100.00 MKD Construction, Inc. $35.00 $43,925.00 Engineer's Estimate 1,255 CUYD $20.00 $25,100.00

A0400 20820-0000 DEWATERING

Hooker Creek, Inc. Lump Sum $18,000.00 MKD Construction, Inc. Lump Sum $14,800.00 Engineer's Estimate ALL LPSM Lump Sum $17,000.00

A0420 25101-0200 PLACED RIPRAP, METHOD A, CLASS 2

Hooker Creek, Inc. $120.00 $4,200.00 MKD Construction, Inc. $262.00 $9,170.00 Engineer's Estimate 35 CUYD $125.00 $4,375.00

5 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: NV FLAP 39(1)

Project Name: Kings Canyon Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0440 25101-0400 PLACED RIPRAP, METHOD A, CLASS 4

Hooker Creek, Inc. $90.00 $4,500.00 MKD Construction, Inc. $125.00 $6,250.00 Engineer's Estimate 50 CUYD $210.00 $10,500.00

A0460 25126-0000 REMOVE AND RESET BOULDER

Hooker Creek, Inc. $580.00 $580.00 MKD Construction, Inc. $900.00 $900.00 Engineer's Estimate 1 EACH $500.00 $500.00

A0480 30111-1000 AGGREGATE SURFACE COURSE, 4-INCH DEPTH

Hooker Creek, Inc. $9.50 $5,662.00 MKD Construction, Inc. $37.00 $22,052.00 Engineer's Estimate 596 SQYD $20.00 $11,920.00

A0500 30202-2000 ROADWAY AGGREGATE, METHOD 2

Hooker Creek, Inc. $30.00 $122,400.00 MKD Construction, Inc. $48.00 $195,840.00 Engineer's Estimate 4,080 TON $50.00 $204,000.00

A0520 30401-5300 FULL DEPTH RECLAMATION, METHOD 2, 6-INCH DEPTH

Hooker Creek, Inc. $49,000.00 $37,240.00 MKD Construction, Inc. $62,750.00 $47,690.00 Engineer's Estimate 0.760 MILE $50,000.00 $38,000.00

A0540 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1

Hooker Creek, Inc. $165.00 $594,000.00 MKD Construction, Inc. $153.00 $550,800.00 Engineer's Estimate 3,600 TON $140.00 $504,000.00

A0560 40601-0000 FOG SEAL

Hooker Creek, Inc. $1,050.00 $6,300.00 MKD Construction, Inc. $1,500.00 $9,000.00 Engineer's Estimate 6 TON $800.00 $4,800.00

6 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: NV FLAP 39(1)

Project Name: Kings Canyon Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0580 41102-0000 PRIME COAT

Hooker Creek, Inc. $1.35 $17,280.00 MKD Construction, Inc. $2.20 $28,160.00 Engineer's Estimate 12,800 SQYD $0.60 $7,680.00

A0600 41105-0000 BLOTTER

Hooker Creek, Inc. $138.00 $2,622.00 MKD Construction, Inc. $275.00 $5,225.00 Engineer's Estimate 19 TON $250.00 $4,750.00

A0620 41201-0000 TACK COAT

Hooker Creek, Inc. $750.00 $4,500.00 MKD Construction, Inc. $1,825.00 $10,950.00 Engineer's Estimate 6 TON $1,000.00 $6,000.00

A0640 50101-0600 MINOR CONCRETE PAVEMENT, REINFORCED, 6-INCH DEPTH

Hooker Creek, Inc. $280.00 $35,000.00 MKD Construction, Inc. $163.00 $20,375.00 Engineer's Estimate 125 SQYD $250.00 $31,250.00

A0660 60101-0000 CONCRETE (HEADWALL AND WINGWALLS FOR 6'X4' BOX CULVERT)

Hooker Creek, Inc. $5,500.00 $99,000.00 MKD Construction, Inc. $2,225.00 $40,050.00 Engineer's Estimate 18 CUYD $2,400.00 $43,200.00

A0680 60103-1960 CONCRETE, HEADWALL FOR 36-INCH EQUIVALENT DIAMETER PIPE CULVERT

Hooker Creek, Inc. $16,000.00 $16,000.00 MKD Construction, Inc. $9,100.00 $9,100.00 Engineer's Estimate 1 EACH $6,500.00 $6,500.00

A0700 60201-0800 24-INCH PIPE CULVERT (HDPE)

Hooker Creek, Inc. $265.00 $25,970.00 MKD Construction, Inc. $120.00 $11,760.00 Engineer's Estimate 98 LNFT $200.00 $19,600.00

7 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: NV FLAP 39(1)

Project Name: Kings Canyon Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0720 60201-0800 24-INCH PIPE CULVERT

Hooker Creek, Inc. $160.00 $15,680.00 MKD Construction, Inc. $120.00 $11,760.00 Engineer's Estimate 98 LNFT $160.00 $15,680.00

A0740 60201-0900 30-INCH PIPE CULVERT (HDPE)

Hooker Creek, Inc. $315.00 $21,420.00 MKD Construction, Inc. $215.00 $14,620.00 Engineer's Estimate 68 LNFT $230.00 $15,640.00

A0760 60201-1100 42-INCH PIPE CULVERT (HDPE)

Hooker Creek, Inc. $265.00 $68,900.00 MKD Construction, Inc. $260.00 $67,600.00 Engineer's Estimate 260 LNFT $330.00 $85,800.00

A0780 60202-0200 18-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT

Hooker Creek, Inc. $115.00 $111,550.00 MKD Construction, Inc. $150.00 $145,500.00 Engineer's Estimate 970 LNFT $140.00 $135,800.00

A0800 60202-0500 30-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT

Hooker Creek, Inc. $200.00 $6,800.00 MKD Construction, Inc. $180.00 $6,120.00 Engineer's Estimate 34 LNFT $185.00 $6,290.00

A0820 60202-0600 36-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT

Hooker Creek, Inc. $200.00 $10,000.00 MKD Construction, Inc. $210.00 $10,500.00 Engineer's Estimate 50 LNFT $255.00 $12,750.00

A0840 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT

Hooker Creek, Inc. $500.00 $2,500.00 MKD Construction, Inc. $725.00 $3,625.00 Engineer's Estimate 5 EACH $650.00 $3,250.00

8 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: NV FLAP 39(1)

Project Name: Kings Canyon Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0860 60210-0900 END SECTION FOR 30-INCH PIPE CULVERT

Hooker Creek, Inc. $1,200.00 $1,200.00 MKD Construction, Inc. $1,000.00 $1,000.00 Engineer's Estimate 1 EACH $750.00 $750.00

A0880 60210-1000 END SECTION FOR 36-INCH PIPE CULVERT

Hooker Creek, Inc. $1,200.00 $1,200.00 MKD Construction, Inc. $1,135.00 $1,135.00 Engineer's Estimate 1 EACH $1,600.00 $1,600.00

A0900 60210-1100 END SECTION FOR 42-INCH PIPE CULVERT

Hooker Creek, Inc. $2,400.00 $2,400.00 MKD Construction, Inc. $1,950.00 $1,950.00 Engineer's Estimate 1 EACH $2,250.00 $2,250.00

A0920 60211-0600 END SECTION FOR 18-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT

Hooker Creek, Inc. $315.00 $13,860.00 MKD Construction, Inc. $755.00 $33,220.00 Engineer's Estimate 44 EACH $850.00 $37,400.00

A0940 60211-0900 END SECTION FOR 30-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT

Hooker Creek, Inc. $725.00 $1,450.00 MKD Construction, Inc. $750.00 $1,500.00 Engineer's Estimate 2 EACH $1,000.00 $2,000.00

A0960 60211-1000 END SECTION FOR 36-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT

Hooker Creek, Inc. $1,000.00 $1,000.00 MKD Construction, Inc. $2,200.00 $2,200.00 Engineer's Estimate 1 EACH $1,200.00 $1,200.00

A0980 60220-1200 6 FEET SPAN, 4 FEET RISE PRECAST REINFORCED CONCRETE BOX CULVERT

Hooker Creek, Inc. $2,200.00 $105,600.00 MKD Construction, Inc. $2,000.00 $96,000.00 Engineer's Estimate 48 LNFT $2,500.00 $120,000.00

9 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: NV FLAP 39(1)

Project Name: Kings Canyon Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1000 60401-0000 MANHOLE

Hooker Creek, Inc. $19,000.00 $38,000.00 MKD Construction, Inc. $21,225.00 $42,450.00 Engineer's Estimate 2 EACH $16,000.00 $32,000.00

A1020 60405-0000 MANHOLE ADJUSTMENT

Hooker Creek, Inc. $1,200.00 $2,400.00 MKD Construction, Inc. $1,825.00 $3,650.00 Engineer's Estimate 2 EACH $1,300.00 $2,600.00

A1040 60901-2300 CURB, ASPHALT, 6-INCH DEPTH

Hooker Creek, Inc. $50.00 $1,250.00 MKD Construction, Inc. $315.00 $7,875.00 Engineer's Estimate 25 LNFT $35.00 $875.00

A1060 60902-1000 CURB AND GUTTER, CONCRETE, 12-INCH DEPTH

Hooker Creek, Inc. $42.00 $78,960.00 MKD Construction, Inc. $45.00 $84,600.00 Engineer's Estimate 1,880 LNFT $60.00 $112,800.00

A1080 61101-0000 WATER SYSTEM

Hooker Creek, Inc. Lump Sum $19,000.00 MKD Construction, Inc. Lump Sum $27,000.00 Engineer's Estimate ALL LPSM Lump Sum $20,000.00

A1100 61108-1000 ADJUST WATER VALVE

Hooker Creek, Inc. $1,000.00 $2,000.00 MKD Construction, Inc. $850.00 $1,700.00 Engineer's Estimate 2 EACH $1,000.00 $2,000.00

A1120 61501-0100 SIDEWALK, CONCRETE

Hooker Creek, Inc. $80.00 $12,400.00 MKD Construction, Inc. $105.00 $16,275.00 Engineer's Estimate 155 SQYD $135.00 $20,925.00

10 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: NV FLAP 39(1)

Project Name: Kings Canyon Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1140 61504-1000 ACCESSIBILITY RAMP, CONCRETE

Hooker Creek, Inc. $400.00 $3,200.00 MKD Construction, Inc. $510.00 $4,080.00 Engineer's Estimate 8 SQYD $150.00 $1,200.00

A1160 61901-2500 FENCE, SPLIT RAIL, 3 RAIL

Hooker Creek, Inc. $45.00 $22,500.00 MKD Construction, Inc. $35.00 $17,500.00 Engineer's Estimate 500 LNFT $35.00 $17,500.00

A1180 61902-0900 GATE, METAL

Hooker Creek, Inc. $5,500.00 $11,000.00 MKD Construction, Inc. $17,700.00 $35,400.00 Engineer's Estimate 2 EACH $18,000.00 $36,000.00

A1200 61907-0000 FENCE POST

Hooker Creek, Inc. $570.00 $570.00 MKD Construction, Inc. $800.00 $800.00 Engineer's Estimate 1 EACH $750.00 $750.00

A1220 61921-1000 REMOVE AND RESET FENCE

Hooker Creek, Inc. $12.00 $10,320.00 MKD Construction, Inc. $25.00 $21,500.00 Engineer's Estimate 860 LNFT $30.00 $25,800.00

A1240 62201-0200 DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY

Hooker Creek, Inc. $160.00 $6,400.00 MKD Construction, Inc. $165.00 $6,600.00 Engineer's Estimate 40 HOUR $190.00 $7,600.00

A1260 62201-1000 WHEEL LOADER, 4 CUBIC YARD MINIMUM RATED CAPACITY

Hooker Creek, Inc. $165.00 $6,600.00 MKD Construction, Inc. $245.00 $9,800.00 Engineer's Estimate 40 HOUR $210.00 $8,400.00

11 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: NV FLAP 39(1)

Project Name: Kings Canyon Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1280 62201-2750 MOTOR GRADER

Hooker Creek, Inc. $193.00 $7,720.00 MKD Construction, Inc. $305.00 $12,200.00 Engineer's Estimate 40 HOUR $300.00 $12,000.00

A1300 62201-3300 HYDRAULIC EXCAVATOR, 3/4 CUBIC YARD MINIMUM CAPACITY

Hooker Creek, Inc. $183.00 $7,320.00 MKD Construction, Inc. $185.00 $7,400.00 Engineer's Estimate 40 HOUR $290.00 $11,600.00

A1320 62301-0000 GENERAL LABOR

Hooker Creek, Inc. $47.00 $1,880.00 MKD Construction, Inc. $95.00 $3,800.00 Engineer's Estimate 40 HOUR $120.00 $4,800.00

A1340 62302-0000 SPECIAL LABOR (BIOLOGIST)

Hooker Creek, Inc. $315.00 $6,300.00 MKD Construction, Inc. $205.00 $4,100.00 Engineer's Estimate 20 HOUR $200.00 $4,000.00

A1360 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES

Hooker Creek, Inc. $280.00 $11,200.00 MKD Construction, Inc. $300.00 $12,000.00 Engineer's Estimate 40 HOUR $200.00 $8,000.00

A1380 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES

Hooker Creek, Inc. $255.00 $10,200.00 MKD Construction, Inc. $280.00 $11,200.00 Engineer's Estimate 40 HOUR $240.00 $9,600.00

A1400 62407-0000 PLACING CONSERVED TOPSOIL

Hooker Creek, Inc. $6.50 $13,000.00 MKD Construction, Inc. $35.00 $70,000.00 Engineer's Estimate 2,000 CUYD $45.00 $90,000.00

12 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: NV FLAP 39(1)

Project Name: Kings Canyon Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1420 62510-2000 SEEDING, HYDRAULIC METHOD

Hooker Creek, Inc. $2,500.00 $9,500.00 MKD Construction, Inc. $9,250.00 $35,150.00 Engineer's Estimate 3.8 ACRE $4,000.00 $15,200.00

A1440 62515-2000 MULCHING, HYDRAULIC METHOD

Hooker Creek, Inc. $5,000.00 $19,000.00 MKD Construction, Inc. $18,000.00 $68,400.00 Engineer's Estimate 3.8 ACRE $3,500.00 $13,300.00

A1460 62901-0000 ROLLED EROSION CONTROL PRODUCT

Hooker Creek, Inc. $11.00 $83,600.00 MKD Construction, Inc. $12.00 $91,200.00 Engineer's Estimate 7,600 SQYD $7.00 $53,200.00

A1480 63301-0000 SIGN SYSTEM

Hooker Creek, Inc. $600.00 $18,600.00 MKD Construction, Inc. $545.00 $16,895.00 Engineer's Estimate 31 EACH $500.00 $15,500.00

A1500 63308-0000 OBJECT MARKER

Hooker Creek, Inc. $580.00 $2,320.00 MKD Construction, Inc. $100.00 $400.00 Engineer's Estimate 4 EACH $315.00 $1,260.00

A1520 63309-0000 DELINEATOR (GUIDE POST)

Hooker Creek, Inc. $100.00 $12,000.00 MKD Construction, Inc. $91.00 $10,920.00 Engineer's Estimate 120 EACH $70.00 $8,400.00

A1540 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID

Hooker Creek, Inc. $0.28 $9,856.00 MKD Construction, Inc. $0.38 $13,376.00 Engineer's Estimate 35,200 LNFT $0.40 $14,080.00

13 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: NV FLAP 39(1)

Project Name: Kings Canyon Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1560 63405-0050 PAVEMENT MARKINGS, SYMBOLS

Hooker Creek, Inc. $58.00 $232.00 MKD Construction, Inc. $175.00 $700.00 Engineer's Estimate 4 EACH $200.00 $800.00

A1580 63501-0000 TEMPORARY TRAFFIC CONTROL

Hooker Creek, Inc. Lump Sum $120,000.00 MKD Construction, Inc. Lump Sum $192,000.00 Engineer's Estimate ALL LPSM Lump Sum $165,000.00

A1600 64603-1000 FIXTURE, VAULT TOILET

Hooker Creek, Inc. $63,000.00 $63,000.00 MKD Construction, Inc. $80,000.00 $80,000.00 Engineer's Estimate 1 EACH $60,000.00 $60,000.00

A1620 64604-3000 FIXTURE, PEDESTRIAN RAILING

Hooker Creek, Inc. $72.00 $6,624.00 MKD Construction, Inc. $150.00 $13,800.00 Engineer's Estimate 92 LNFT $300.00 $27,600.00

A1640 64605-1000 FIXTURE, KIOSK

Hooker Creek, Inc. Lump Sum $2,300.00 MKD Construction, Inc. Lump Sum $1,475.00 Engineer's Estimate ALL LPSM Lump Sum $3,000.00

A1660 64620-0000 REMOVE AND RESET (INFORMATION SIGNS)

Hooker Creek, Inc. $1,500.00 $1,500.00 MKD Construction, Inc. $2,000.00 $2,000.00 Engineer's Estimate 1 EACH $7,500.00 $7,500.00

A1680 64620-0400 REMOVE AND RESET MAILBOX

Hooker Creek, Inc. $160.00 $2,880.00 MKD Construction, Inc. $1,150.00 $20,700.00 Engineer's Estimate 18 EACH $275.00 $4,950.00

14 out of 14Source Selection Information - See FAR 2.101 & 3.104

Project No: NV FLAP 39(1)

Project Name: Kings Canyon Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1700 64620-1000 REMOVE AND RESET HISTORIC MARKER

Hooker Creek, Inc. $3,500.00 $3,500.00 MKD Construction, Inc. $5,800.00 $5,800.00 Engineer's Estimate 1 EACH $7,000.00 $7,000.00

Total Schedule - All Items

Hooker Creek, Inc. $3,040,546.00 MKD Construction, Inc. $3,951,373.00 Engineer's Estimate $3,525,000.00

2021-06-15T15:22:43-0600
JOSEPHINE P HELMS