This document is an amendment to an invitation for bid for a federal highway construction project. The amendment provides notice that sections B and C of the original solicitation, containing provisions and clauses respectively, have been replaced with updated versions dated May 4, 2021. Bidders must acknowledge receipt of this amendment by the designated date and time specified in the solicitation or risk rejection of their bid. The project, designated NV FLAP 39(1), involves construction work on King's Canyon Road. The solicitation number is 6982AF20B000026 and was issued by the Federal Highway Administration Central Federal Lands Highway Division.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
B-7
Solicitation Provisions
52.203-11 Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. (SEP 2007)
52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements-Representation. (JAN 2017)
52.204-7 System for Award Management. (OCT 2018)
52.204-8 Annual Representations and Certifications. (MAR 2020)
52.204-16 Commercial and Government Entity Code Reporting (JUL 2016)
52.204-17 Ownership or Control of Offeror (JUL 2016)
52.204-20 Predecessor or Offeror (JUL 2016)
52.204-22 Alternative Line Item Proposal (JAN 2017)
52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (AUG 2020)
52.204-26 Covered Telecommunications Equipment or Services-Representation. (DEC 2019)
52.209-5 Certification Regarding Responsibility Matters. (OCT 2015)
52.209-7 Information Regarding Responsibility Matters (Oct 2018)
52.209-13 Violation of Arms Control Treaties or Agreements – Certification (FEB 2021)
52.214-3 Amendments to Invitations for Bids. (DEC 2016)
52.214-4 False Statements in Bids. (APR 1984)
52.214-5 Submission of Bids. (DEC 2016)
52.214-6 Explanation to Prospective Bidders. (APR 1984)
52.214-7 Late Submissions, Modifications, and Withdrawals of Bids. (NOV 1999)
52.214-18 Preparation of Bids - Construction. (APR 1984)
52.214-19 Contract Award - Sealed Bidding - Construction. (AUG 1996)
Amendment A001 May 4, 2021
B-8
52.214-31 Facsimile Bids (DEC 1989)
52.214-34 Submission of Offers in the English Language. (APR 1991)
52.214-35 Submission of Offers in U.S. Currency. (APR 1991)
52.215-1 Instructions to Offerors – Competitive Acquisition (JAN 2017)
52.215-5 Facsimile Proposals. (OCT 1997)
52.216-1 Type of Contract. (APR 1984)
The Government contemplates award of a FIRM FIXED PRICE contract resulting from this solicitation.
(End of provision)
52.222-5 Construction Wage Rate Requirements Secondary Site of the Work. (MAY 2014)
52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction. (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the
Goals for Minority Participation for Each Trade
Goals for Female Participation for Each
Trade 9.2% - Carson City, Non-
Metropolitan Statistical Area (Non
MSA), NV
6.9%
B-9 regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled Affirmative Action Compliance Requirements for Construction, and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade.
The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the -
(1) Name, address, and telephone number of the subcontractor; (2)
Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the covered area is Carson City, NV, a Non SMSA County.
(End of provision)
52.222-38 Compliance with Veterans' Employment Reporting Requirements. (FEB 2016)
52.223-22 Public Disclosure of Greenhouse Gas Emissions and Reduction Goals— Representation (DEC 2016)
52.225-10 Notice of Buy American Requirement—Construction Materials (MAY 2014)
52.225-20 Prohibition on Conducting Restricted Business Operations in Sudan-- Certification. (AUG 2009)
52.228-1 Bid Guarantee. (SEP 1996)
B-10
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds -
(1) To unsuccessful bidders as soon as practicable after the opening of bids;
and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be twenty (20%) percent of the bid price or $3,000,000.00, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
52.233-2 Service of Protest. (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:
Mr. Joseph Wilson Contracting Officer Federal Highway Administration 12300 West Dakota Avenue, Suite 360 Lakewood, Colorado 80228
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
B-11
52.236-27 Site Visit (Construction). (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) Site visits may be arranged during normal duty hours by contacting: No organized site visit will be held.
52.252-1 Solicitation Provisions Incorporated by Reference. (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far
52.252-3 Alterations in Solicitation. (APR 1984)
C-1
Contract Clauses
52.202-1 Definitions. (NOV 2013)
52.203-3 Gratuities. (APR 1984)
52.203-5 Covenant Against Contingent Fees. (MAY 2014)
52.203-6, Restrictions on Subcontractor Sales to the Government (SEP 2006)
52.203-7 Anti-Kickback Procedures. (MAY 2014)
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity. (MAY 2014)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity. (MAY 2014)
52.203-12 Limitation on Payments to Influence Certain Federal Transactions. (OCT 2010)
52.203-13 Contractor Code of Business Ethics and Conduct (OCT 2015)
52.203-14 Display of Hotline Poster(s). (OCT 2015)
(a) Definition.
"United States," as used in this clause, means the 50 States, the District of Columbia, and outlying areas.
(b) Display of fraud hotline poster(s). Except as provided in paragraph (c)--
(1) During contract performance in the United States, the Contractor shall prominently display in common work areas within business segments performing work under this contract and at contract work sites--
(i) Any agency fraud hotline poster or Department of Homeland Security (DHS) fraud hotline poster identified in paragraph (b)(3) of this clause; and
(ii) Any DHS fraud hotline poster subsequently identified by the Contracting Officer.
(2) Additionally, if the Contractor maintains a company website as a method of providing information to employees, the Contractor shall display an electronic version of the poster(s) at the website.
C-2
(3) Any required posters may be obtained as follows:
General Fraud https://www.oig.dot.gov/sites/default/files/files/OIG-generic-2.pdf
(c) If the Contractor has implemented a business ethics and conduct awareness program, including a reporting mechanism, such as a hotline poster, then the Contractor need not display any agency fraud hotline posters as required in paragraph
(b) of this clause, other than any required DHS posters.
(d) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (d), in all subcontracts that exceed $5,500,000, except when the subcontract--
(1) Is for the acquisition of a commercial item; or
(2) Is performed entirely outside the United States.
(End of clause)
52.203-17 Contractor Employee Whistleblower Rights and Requirements to Inform Employees of Whistleblower Rights (APR 2014)
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017)
52.204-1 Approval of Contract (DEC 1989)
This contract is subject to the written approval of the Acquisitions Branch Chief and shall not be binding until so approved.
(End of Clause)
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper.
(MAY 2011)
52.204-9 Personal Identity Verification of Contractor Personnel. (JAN 2011)
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (OCT 2018)
52.204-13 System for Award Management Maintenance. (OCT 2018)
52.204-14 Service Contract Reporting Requirements (OCT 2016)
52.204-18 Commercial and Government Entity Code Maintenance (JUL 2016)
C-3
52.204-19 Incorporation by Reference of Representations and Certifications. (DEC 2014)
52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (JUL 2018)
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (AUG 2020)
52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (OCT 2015)
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations (NOV 2015)
52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984) Alternate I
(APR 1984)
The Contractor shall be required to (a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than {Refer to Subsection 108.01 of the SCRs}. The time stated for completion shall include final cleanup of the premises.
The completion date is based on the assumption that the successful offeror will receive the notice to proceed by 7/1/2021. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.
52.211-12 Liquidated Damages - Construction. (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of (see FP-14 section 108) for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
52.211-13 Time Extensions. (SEP 2000)
52.211-18 Variation in Estimated Quantity. (APR 1984)
C-4
52.214-26 Audit and Records – Sealed Bidding. (OCT 2010)
52.214-27 Price Reduction for Defective Certified Cost or Pricing Data – Modifications – Sealed Bidding. (AUG 2011)
52.214-28 Subcontractor Certified Cost or Pricing Data – Modifications – Sealed Bidding.
(JUN 2020)
52.215-5 Facsimile Proposals. (OCT 1997)
52.219-3, Notice of Hubzone Set-Aside or Sole Source Award (MAR 2020)
52.219-8 Utilization of Small Business Concerns. (OCT 2018)
52.219-28 Post-Award Small Business Program Rerepresentation. (OCT 2020)
52.222-1 Notice to the Government of Labor Disputes. (FEB 1997)
52.222-3 Convict Labor. (JUN 2003)
52.222-4 Contract Work Hours and Safety Standards Act - Overtime Compensation. (MAY 2014)
52.222-6 Construction Wage Rate Requirements. (AUG 2018)
52.222-7 Withholding of Funds. (MAY 2014)
52.222-8 Payrolls and Basic Records. (AUG 2018)
52.222-9 Apprentices and Trainees. (JUL 2005)
52.222-10 Compliance with Copeland Act Requirements. (FEB 1988)
52.222-11 Subcontracts (Labor Standards). (MAY 2014)
52.222-12 Contract Termination - Debarment. (MAY 2014)
52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. (MAY 2014)
52.222-14 Disputes Concerning Labor Standards. (FEB 1988)
52.222-15 Certification of Eligibility. (MAY 2014)
52.222-21 Prohibition of Segregated Facilities. (APR 2015)
C-5
52.222-26 Equal Opportunity. (SEP 2016)
52.222-27 Affirmative Action Compliance Requirements for Construction. (APR 2015)
52.222-35 Equal Opportunity for Veterans. (OCT 2015)
52.222-36 Affirmative Action for Workers with Disabilities. (JUL 2014)
52.222-37 Employment Reports on Veterans. (FEB 2016)
52.222-50 Combating Trafficking in Persons. (OCT 2020)
52.222-54 Employment Eligibility Verification. (OCT 2015)
52.222-55 Minimum Wages Under Executive Order 13658 (OCT 2020)
52.222-62 Paid Sick Leave Under Executive Order 13706 (JAN 2017)
52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts (SEP 2013)
52.223-3 Hazardous Material Identification and Material Safety Data. (FEB 2021)
52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2011)
52.223-6 Drug-Free Workplace. (MAY 2001)
52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts (AUG 2018)
52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. (AUG 2011)
52.223-21 Foams (JUN 2016)
52.224-1 Privacy Act Notification. (APR 1984)
52.224-2 Privacy Act. (APR 1984)
52.225-9 Buy American-Construction Materials. (FEB 2021)
(a) Definitions. As used in this clause—
Commercially available off-the-shelf (COTS) item—
C-6
(1) Means any item of supply (including construction material) that is–
(i) A commercial item (as defined in paragraph (1) of the definition at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States;
or
(ii) A construction material manufactured in the United States, if–
Amendment A001 https://www.acquisition.gov/far/part-2#FAR_2_101
C-7
(A) The cost of its components mined, produced, or manufactured in the United States exceeds 55 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States.
Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for
Amendment A001 May 4, 2021 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3
C-8 construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
None
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)
(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
Amendment A001 https://www.acquisition.gov/far/part-12#FAR_12_505
C-9
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction material description
Unit of measure Quantity Price (dollars) *
Item 1 Foreign construction material Domestic construction material Item 2 Foreign construction material Domestic construction material
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]
[Include other applicable supporting information.]
C-10
[*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]
(End of Clause)
52.227-1 Authorization and Consent. (DEC 2007)
52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement. (DEC 2007)
52.227-4 Patent Indemnity--Construction Contracts. (DEC 2007)
52.228-2 Additional Bond Security. (OCT 1997)
52.228-5 Insurance - Work on a Government Installation. (JAN 1997)
52.228-11 Pledges of Assets. (FEB 2021)
52.228-12 Prospective Subcontractor Requests for Bonds. (MAY 2014)
52.228-14 Irrevocable Letter of Credit (Nov 2014)
52.228-15 Performance and Payment Bonds - Construction. (OCT 2010)
52.229-3 Federal, State, and Local Taxes. (FEB 2013)
52.232-5 Payments under Fixed-Price Construction Contracts. (JAN 2017)
52.232-17 Interest. (MAY 2014)
52.232-23 Assignment of Claims. (JAN 1986)
52.232-27 Prompt Payment For Construction Contracts. (JAN 2017)
52.232-33 Payment by Electronic Funds Transfer – System for Award Management
(OCT 2018)
52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013)
52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013)
52.233-1 Disputes. (MAY 2014) - Alternate I (DEC 1991)
52.233-3 Protest after Award. (AUG 1996)
52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004)
C-11
52.236-2 Differing Site Conditions. (APR 1984)
52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984)
52.236-4 Physical Data. (APR 1984)
Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(a) The indications of physical conditions on the drawings and in the specifications, are the result of site investigations by:
1) PAVEMENT AND MATERIALS REPORT
2) HYDRAULICS MEMORANDUM
(b) Weather conditions Contact National Weather Service.
(c) Transportation facilities N/A
(d) 3D LandXML files of existing ground & proposed design
52.236-5 Material and Workmanship. (APR 1984)
52.236-6 Superintendence by the Contractor. (APR 1984)
52.236-7 Permits and Responsibilities. (NOV 1991)
52.236-8 Other Contracts. (APR 1984)
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR 1984)
52.236-10 Operations and Storage Areas. (APR 1984)
52.236-11 Use and Possession Prior to Completion. (APR 1984)
52.236-12 Cleaning Up. (APR 1984)
52.236-13 Accident Prevention. (NOV 1991)
52.236-15 Schedules for Construction Contracts. (APR 1984)
C-12
52.236-17 Layout of Work. (APR 1984)
52.236-21 Specifications and Drawings for Construction. (FEB 1997)
52.236-26 Preconstruction Conference. (FEB 1995)
52.242-13 Bankruptcy. (JUL 1995)
52.242-14 Suspension of Work. (APR 1984)
52.243-4 Changes. (JUN 2007)
52.243-6 Change Order Accounting. (APR 1984)
52.244-6 Subcontracts for Commercial Items. (OCT 2020)
52.245-1 Government Property (JAN 2017) - Alternate I (APR 2012)
52.245-9 Use and Charges. (APR 2012)
52.246-12 Inspection of Construction. (AUG 1996)
52.247-64 Preference for Privately Owned U.S.-Flag Commercial Vessels (FEB 2006)
52.248-3 Value Engineering - Construction. (OCT 2020)
52.249-2 Termination for Convenience of the Government (Fixed-Price). (APR 2012) - Alternate I (SEP 1996)
52.249-10 Default (Fixed-Price Construction). (APR 1984)
52.252-2 Clauses Incorporated by Reference. (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): http://www.acquisition.gov/far
52.252-4 Alterations in Contract. (APR 1984)
Portions of this contract are altered as follows: NONE
C-13
52.253-1 Computer Generated Forms. (JAN 1991)
1252.223-71 Accident and Fire Reporting. (APR 2005)
(a) The Contractor shall report to the Contracting Officer any accident or fire occurring at the site of the work which causes:
(1) A fatality or as much as one lost workday on the part of any employee of the Contractor or subcontractor at any tier;
(2) Damage of $1,000 or more to Government-owned or leased property, either real or personal;
(3) Damage of $1,000 or more to Contractor or subcontractor owned or leased motor vehicles or mobile equipment; or
(4) Damage for which a contract time extension may be requested.
(b) Accident and fire reports required by paragraph (a) above shall be accomplished by the following means:
(1) Accidents or fires resulting in a death, hospitalization of five or more persons, or destruction of Government-owned or leased property (either real or personal), the total value of which is estimated at $100,000 or more, shall be reported immediately by telephone to the Contracting Officer or his/her authorized representative and shall be confirmed by telegram or facsimile transmission within 24 hours to the Contracting Officer. Such telegram or facsimile transmission shall state all known facts as to extent of injury and damage and as to cause of the accident or fire.
(2) Other accident and fire reports required by paragraph (a) above may be reported by the Contractor using a state, private insurance carrier, or Contractor accident report form which provides for the statement of:
(i) The extent of injury; and
(ii) The damage and cause of the accident or fire.
Such report shall be mailed or otherwise delivered to the Contracting Officer within 48 hours of the occurrence of the accident or fire.
(c) The Contractor shall assure compliance by subcontractors at all tiers with the requirements of this clause.
1252.223-73 Seat Belt Use Policies and Programs. (APR 2005)
C-14
In accordance with Executive Order 13043, Increasing Seat Belt Use in the United States, dated April 16, 1997, the contractor is encouraged to adopt and enforce on-the-job seat belt use policies and programs for its employees when operating company-owned, rented, or personally-owned vehicles. The National Highway Traffic Safety Administration (NHTSA) is responsible for providing leadership and guidance in support of this Presidential initiative. For information on how to implement such a program or for statistics on the potential benefits and cost-savings to your company or organization, please visit the Buckle Up America section of NHTSA’s website at www.nhtsa.dot.gov. Additional resources are available from the Network of Employers for Traffic Safety (NETS), a public-private partnership headquartered in the Washington, D.C.
metropolitan area, and dedicated to improving the traffic safety practices of employers and employees.
NETS is prepared to help with technical assistance, a simple, user friendly program kit, and an award for achieving the President’s goal of 90 percent seat belt use. NETS can be contacted at 1-888-221-0045 or visit its website at www.trafficsafety.org.
1252.228-73 Notification of Miller Act Payment Bond Protection. (APR 2005)
This notice clause shall be inserted by first tier subcontractors in all their subcontracts and shall contain information pertaining to the surety that provided the payment bond under the prime contract.
(a) The prime contract is subject to the Miller Act, (40 U.S.C. 3131 et al), under which the prime contractor has obtained a payment bond. This payment bond may provide certain unpaid employees, suppliers, and subcontractors a right to sue the bonding surety under the Miller Act for amounts owned for work performed and materials delivery under the prime contract.
(b) Persons believing that they have legal remedies under the Miller Act should consult their legal advisor regarding the proper steps to take to obtain these remedies. This notice clause does not provide any party any rights against the Federal Government, or create any relationship, contractual or otherwise, between the Federal Government and any private party.
(c) The surety which has provided the payment bond under the prime contract is:
On File with FHWA - Construction 12300 West Dakota Avenue, Suite 210 Lakewood, Colorado 80228 http://www.nhtsa.dot.gov/ http://www.trafficsafety.org/
C-15
1252.242-72 Dissemination of Contract Information. (OCT 1994)
The Contractor shall not publish, permit to be published, or distribute for public consumption, any information, oral or written, concerning the results or conclusions made pursuant to the performance of this contract, without the prior written consent of the Contracting Officer. Two copies of any material proposed to be published or distributed shall be submitted to the Contracting Officer.
1252.242-73 Contracting Officer's Technical Representative. (OCT 1994)
(a) The Contracting Officer may designate Government personnel to act as the Contracting Officer's Technical Representative (COTR) to perform functions under the contract such as review and/or inspection and acceptance of supplies, services, including construction, and other functions of a technical nature. The Contracting Officer will provide a written notice of such designation to the Contractor within five working days after contract award or for construction, not less than five working days prior to giving the contractor the notice to proceed. The designation letter will set forth the authorities and limitations of the COTR under the contract.
(b) The Contracting Officer cannot authorize the COTR or any other representative to sign documents (i.e., contracts, contract modifications, etc.) that require the signature of the Contracting Officer.
C-16
POST-AWARD EVALUATION OF CONTRACTOR PERFORMANCE
Contractor Performance Evaluations
a. Interim and final evaluations of contractor performance will be prepared on this contract in accordance with FAR 42.1502 and TAM 1242.1502. The final performance evaluations will be prepared at the time of completion of work.
b. The Contractor can elect to review the evaluation and submit additional information or provide a rebuttal statement. The contractor will be permitted 60 calendar days to respond from the date of receipt of the evaluation. Contractor response is voluntary.
If the contractor does not respond within 60 days, the Government will presume that the Contractor has no comment. Any disagreement between the parties regarding an evaluation will be referred to an individual at a level above the Contracting Officer, whose decision is final.
c. Copies of the evaluations, Contractor responses, and review comments, if any, will be retained as part of the contract file, and may be used to support future award decisions.
The Federal Highway Administration utilizes the Contractor Performance Assessment Reporting System (CPARS) to record and maintain past performance information.
CPARS hosts a suite of web-enabled applications that are used to document contractor performance information that is required by Federal Regulations. The CPARS module assesses performance on contracts for Systems, Services, Information Technology, and Operations Support; Architect-Engineer contracts; and Construction contracts.
Reference material can be accessed in CPARS.
The registration process requires the Contractor to identify an individual that will serve as a primary contact. This individual will be authorized access to the evaluation for review and comment. In addition, the Contractor is encouraged to identify a secondary contact in the event the primary contact is unavailable to process the evaluation within the required 60-day time period. After the FHWA Focal Point registers the contract in CPARS, the contractor representative will receive a system generated email notifying him/her that the contract is registered. A system generated email will also provide the Contractor with a User ID if the person does not already have a CPARS User ID.
After a performance evaluation, has been prepared and is ready for comment, the Contractor representative will receive a system generated email notification that the performance evaluation is electronically available for review and comment. The Contractor representative will receive an automated email whenever an assessment is completed and can subsequently retrieve the completed assessment from CPARS.
Contractors may access evaluations in CPARS for review and comment.
(End of Clause)
| topmostSubform[0]: |
| Page1[0]: |
| ContractIDCode[0]: |
| Page[0]: 1 |
| Pages[0]: 22 |
| AmendmentNo[0]: A001 |
| EffectiveDate[0]: 05/04/2021 |
| ReqNumber[0]: |
| ProjectNo[0]: NV FLAP 39(1) |
| IssuedBy[0]: FEDERAL HIGHWAY ADMINISTRATION |
CENTRAL FEDERAL LANDS HIGHWAY DIVISION
12300 WEST DAKOTA AVENUE, SUITE 360
LAKEWOOD, COLORADO 80228
ATTENTION: Josephine Helms
| Code[0]: 6905001 |
| AdministeredBy[0]: |
| Code[2]: |
| NameandAddress[0]: |
| Code[1]: |
| FacilityCode[0]: |
| CheckBox9[0]: 1 |
| AmendmentNo[1]: 6982AF20B000026 |
| Dated9B[0]: 05/04/2021 |
| CheckBox10[0]: Off |
| ModificationNo[0]: |
| Dated10B[0]: |
| CheckBox11[0]: 1 |
| Extended[0]: Off |
| NotExtended[0]: 1 |
| Copies[0]: 0* |
| AccountingData[0]: |
| CheckBox13A[0]: Off |
| A13[0]: |
| CheckBox13B[0]: Off |
| CheckBox13C[0]: Off |
| C13[0]: |
| CheckBox13D[0]: Off |
| D13[0]: |
| IsNot[0]: 1 |
| Is[0]: Off |
| CopiesReturned[0]: *See Item 14 |
| Description[0]: INVITATION FOR BID |
Remove Section B (Provisions) and Section C (Clauses) and replace with the attached corresponding sections dated 5/4/2021 (A001).
*FAILURE TO ACKNOWLEDGE THIS AMENDMENT IN BLOCK 19 OF THE SF 1442 BY THE DESIGNATED DATE AND HOUR SPECIFIED IN THE SOLICITATION MAY RESULT IN REJECTION OF YOUR BID (REFER TO ITEM 11.)
| NameandTitleSigner[0]: |
| DateSigned[0]: |
| NameandTitleOfficer[0]: |
| DateSigned[1]: |