Tabulation of Bids Report Date: 12/12/18
1 out of 16
Project No: AZ FLAP 237(1)
Project Name: Mormon Lake Road
Schedule: A
Schedule Type: Base
Solcitation No: 6982AF18B000031
Division: Central Federal Lands
State: AZ County: Coconino
Federal Land: Coconino National Forest Opened at: Lakewood, CO
Opened by: Lori Kliethermes
Date: 11/28/18
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
LaForge and Budd Construction Company, Inc. ( $0.00 ) no 2020 North 21st Street Parsons, KS 67357
Intermountain West Civil Constructors, Inc. $9,449,044.70 1564 N. Alma School Road, Suite 200 Mesa, AZ 85201
Stormwater Plans, LLC dba SWP Contracting and Paving $9,749,920.00 5624 N. 54th Avenue Glendale, AZ 85301
Vastco, Inc. $11,380,554.14
Standard Construction Company, Inc. $17,029,775.00 810 E. Western Avenue Avondale, AZ 85323
Engineer's Estimate $10,708,050.00
2 out of 16
Project No: AZ FLAP 237(1)
Project Name: Mormon Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0020 15101-0000 MOBILIZATION
LaForge and Budd Construction Company, Inc. Lump Sum $0.00 Intermountain West Civil Constructors, Inc. Lump Sum $839,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $1,041,000.00 Vastco, Inc. Lump Sum $1,100,000.00 Standard Construction Company, Inc. Lump Sum $897,000.00 Engineer's Estimate ALL LPSM Lump Sum $1,193,116.00
A0040 15206-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING STAKE
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $5,500.00 $47,278.00 Stormwater Plans, LLC dba SWP Contracting and Paving $10,000.00 $85,960.00 Vastco, Inc. $8,100.00 $69,627.60 Standard Construction Company, Inc. $7,000.00 $60,172.00 Engineer's Estimate 8.596 MILE $5,000.00 $42,980.00
A0060 15210-3000 CENTERLINE, VERIFICATION AND STAKING
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $2,200.00 $2,582.80 Stormwater Plans, LLC dba SWP Contracting and Paving $10,000.00 $11,740.00 Vastco, Inc. $21,860.00 $25,663.64 Standard Construction Company, Inc. $3,000.00 $3,522.00 Engineer's Estimate 1.174 MILE $6,000.00 $7,044.00
A0080 15214-3000 SURVEY AND STAKING, PARKING AREA
LaForge and Budd Construction Company, Inc. Lump Sum $0.00 Intermountain West Civil Constructors, Inc. Lump Sum $4,200.00 Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $20,000.00 Vastco, Inc. Lump Sum $17,000.00 Standard Construction Company, Inc. Lump Sum $5,700.00 Engineer's Estimate ALL LPSM Lump Sum $8,000.00
A0100 15216-2000 SURVEY AND STAKING, GRADE FINISHING STAKES
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $4,300.00 $73,929.90 Stormwater Plans, LLC dba SWP Contracting and Paving $10,000.00 $171,930.00 Vastco, Inc. $5,414.00 $93,082.90 Standard Construction Company, Inc. $7,000.00 $120,351.00 Engineer's Estimate 17.193 MILE $5,000.00 $85,965.00
3 out of 16
Project No: AZ FLAP 237(1)
Project Name: Mormon Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0120 15301-0000 CONTRACTOR QUALITY CONTROL
LaForge and Budd Construction Company, Inc. Lump Sum $0.00 Intermountain West Civil Constructors, Inc. Lump Sum $95,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $300,000.00 Vastco, Inc. Lump Sum $138,950.00 Standard Construction Company, Inc. Lump Sum $229,000.00 Engineer's Estimate ALL LPSM Lump Sum $175,000.00
A0140 15401-0000 CONTRACTOR TESTING
LaForge and Budd Construction Company, Inc. Lump Sum $0.00 Intermountain West Civil Constructors, Inc. Lump Sum $105,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $400,000.00 Vastco, Inc. Lump Sum $117,860.00 Standard Construction Company, Inc. Lump Sum $104,000.00 Engineer's Estimate ALL LPSM Lump Sum $175,000.00
A0160 15501-0000 CONSTRUCTION SCHEDULE
LaForge and Budd Construction Company, Inc. Lump Sum $0.00 Intermountain West Civil Constructors, Inc. Lump Sum $9,500.00 Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $20,000.00 Vastco, Inc. Lump Sum $6,616.00 Standard Construction Company, Inc. Lump Sum $55,000.00 Engineer's Estimate ALL LPSM Lump Sum $25,000.00
A0180 15701-0000 SOIL EROSION CONTROL
LaForge and Budd Construction Company, Inc. Lump Sum $0.00 Intermountain West Civil Constructors, Inc. Lump Sum $17,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $50,000.00 Vastco, Inc. Lump Sum $113,640.00 Standard Construction Company, Inc. Lump Sum $55,000.00 Engineer's Estimate ALL LPSM Lump Sum $100,000.00
A0200 15701-0000 SOIL EROSION CONTROL Sediment Control
LaForge and Budd Construction Company, Inc. Lump Sum $0.00 Intermountain West Civil Constructors, Inc. Lump Sum $24,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $80,000.00 Vastco, Inc. Lump Sum $194,500.00 Standard Construction Company, Inc. Lump Sum $102,000.00 Engineer's Estimate ALL LPSM Lump Sum $50,000.00
4 out of 16
Project No: AZ FLAP 237(1)
Project Name: Mormon Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0220 15701-0000 SOIL EROSION CONTROL Non-Stormwater Control
LaForge and Budd Construction Company, Inc. Lump Sum $0.00 Intermountain West Civil Constructors, Inc. Lump Sum $5,300.00 Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $40,000.00 Vastco, Inc. Lump Sum $5,855.00 Standard Construction Company, Inc. Lump Sum $76,000.00 Engineer's Estimate ALL LPSM Lump Sum $50,000.00
A0240 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
LaForge and Budd Construction Company, Inc. Lump Sum $0.00 Intermountain West Civil Constructors, Inc. Lump Sum $24,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $100,000.00 Vastco, Inc. Lump Sum $10,580.00 Standard Construction Company, Inc. Lump Sum $65,000.00 Engineer's Estimate ALL LPSM Lump Sum $25,000.00
A0260 15802-0000 WATERING FOR DUST CONTROL
LaForge and Budd Construction Company, Inc. Lump Sum $0.00 Intermountain West Civil Constructors, Inc. Lump Sum $134,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $200,000.00 Vastco, Inc. Lump Sum $210,440.00 Standard Construction Company, Inc. Lump Sum $232,000.00 Engineer's Estimate ALL LPSM Lump Sum $150,000.00
A0280 20101-0000 CLEARING AND GRUBBING
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $3,600.00 $259,200.00 Stormwater Plans, LLC dba SWP Contracting and Paving $650.00 $46,800.00 Vastco, Inc. $3,932.00 $283,104.00 Standard Construction Company, Inc. $16,000.00 $1,152,000.00 Engineer's Estimate 72.000 ACRE $6,000.00 $432,000.00
A0300 20301-2400 REMOVAL OF SIGN
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $107.00 $11,235.00 Stormwater Plans, LLC dba SWP Contracting and Paving $80.00 $8,400.00 Vastco, Inc. $17.50 $1,837.50 Standard Construction Company, Inc. $225.00 $23,625.00 Engineer's Estimate 105 EACH $110.00 $11,550.00
5 out of 16
Project No: AZ FLAP 237(1)
Project Name: Mormon Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0320 20304-1000 REMOVAL OF STRUCTURES AND OBSTRUCTIONS
LaForge and Budd Construction Company, Inc. Lump Sum $0.00 Intermountain West Civil Constructors, Inc. Lump Sum $40,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $474,000.00 Vastco, Inc. Lump Sum $9,380.00 Standard Construction Company, Inc. Lump Sum $90,000.00 Engineer's Estimate ALL LPSM Lump Sum $20,000.00
A0340 20401-0000 ROADWAY EXCAVATION
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $16.00 $480,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving $10.00 $300,000.00 Vastco, Inc. $20.86 $625,800.00 Standard Construction Company, Inc. $94.00 $2,820,000.00 Engineer's Estimate 30,000 CUYD $25.00 $750,000.00
A0360 20402-0000 SUBEXCAVATION
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $32.00 $64,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving $20.00 $40,000.00 Vastco, Inc. $64.00 $128,000.00 Standard Construction Company, Inc. $60.00 $120,000.00 Engineer's Estimate 2,000 CUYD $50.00 $100,000.00
A0380 20410-0000 SELECT BORROW
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $32.00 $464,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving $35.00 $507,500.00 Vastco, Inc. $36.00 $522,000.00 Standard Construction Company, Inc. $14.00 $203,000.00 Engineer's Estimate 14,500 CUYD $30.00 $435,000.00
A0400 20441-0000 WASTE
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $12.00 $111,600.00 Stormwater Plans, LLC dba SWP Contracting and Paving $17.00 $158,100.00 Vastco, Inc. $10.35 $96,255.00 Standard Construction Company, Inc. $28.00 $260,400.00 Engineer's Estimate 9,300 CUYD $10.00 $93,000.00
6 out of 16
Project No: AZ FLAP 237(1)
Project Name: Mormon Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0420 25101-2400 PLACED RIPRAP, METHOD B, CLASS 4
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $145.00 $10,875.00 Stormwater Plans, LLC dba SWP Contracting and Paving $90.00 $6,750.00 Vastco, Inc. $162.50 $12,187.50 Standard Construction Company, Inc. $146.00 $10,950.00 Engineer's Estimate 75 CUYD $175.00 $13,125.00
A0440 30203-2000 ROADWAY AGGREGATE, METHOD 2
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $7.50 $1,605,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving $4.25 $909,500.00 Vastco, Inc. $11.30 $2,418,200.00 Standard Construction Company, Inc. $17.00 $3,638,000.00 Engineer's Estimate 214,000 SQYD $6.00 $1,284,000.00
A0480 40101-5600 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH OR 3/4-INCH NOMINAL MAXIMUM SIZE
AGGREGATE, 0.3 TO <3 MILLION ESAL
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $97.50 $3,558,750.00 Stormwater Plans, LLC dba SWP Contracting and Paving $85.00 $3,102,500.00 Vastco, Inc. $105.00 $3,832,500.00 Standard Construction Company, Inc. $131.00 $4,781,500.00 Engineer's Estimate 36,500 TON $100.00 $3,650,000.00
A0500 40105-3000 ANTISTRIP ADDITIVE, TYPE 3
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $170.00 $62,050.00 Stormwater Plans, LLC dba SWP Contracting and Paving $210.00 $76,650.00 Vastco, Inc. $258.00 $94,170.00 Standard Construction Company, Inc. $252.00 $91,980.00 Engineer's Estimate 365 TON $200.00 $73,000.00
A0540 40601-0000 FOG SEAL
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $850.00 $79,050.00 Stormwater Plans, LLC dba SWP Contracting and Paving $400.00 $37,200.00 Vastco, Inc. $351.00 $32,643.00 Standard Construction Company, Inc. $811.00 $75,423.00 Engineer's Estimate 93 TON $500.00 $46,500.00
7 out of 16
Project No: AZ FLAP 237(1)
Project Name: Mormon Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0560 40605-0000 BLOTTER
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $40.00 $66,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving $10.00 $16,500.00 Vastco, Inc. $23.40 $38,610.00 Standard Construction Company, Inc. $69.00 $113,850.00 Engineer's Estimate 1,650 TON $30.00 $49,500.00
A0580 41102-1000 PRIME COAT, METHOD 1
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $0.55 $117,700.00 Stormwater Plans, LLC dba SWP Contracting and Paving $1.00 $214,000.00 Vastco, Inc. $0.35 $74,900.00 Standard Construction Company, Inc. $1.00 $214,000.00 Engineer's Estimate 214,000 SQYD $1.00 $214,000.00
A0600 41201-0000 TACK COAT
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $1,200.00 $116,400.00 Stormwater Plans, LLC dba SWP Contracting and Paving $550.00 $53,350.00 Vastco, Inc. $585.00 $56,745.00 Standard Construction Company, Inc. $860.00 $83,420.00 Engineer's Estimate 97 TON $800.00 $77,600.00
A0620 60201-0600 18-INCH PIPE CULVERT
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $95.00 $13,110.00 Stormwater Plans, LLC dba SWP Contracting and Paving $150.00 $20,700.00 Vastco, Inc. $186.00 $25,668.00 Standard Construction Company, Inc. $103.00 $14,214.00 Engineer's Estimate 138 LNFT $140.00 $19,320.00
A0640 60201-0800 24-INCH PIPE CULVERT
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $110.00 $17,930.00 Stormwater Plans, LLC dba SWP Contracting and Paving $170.00 $27,710.00 Vastco, Inc. $248.00 $40,424.00 Standard Construction Company, Inc. $162.00 $26,406.00 Engineer's Estimate 163 LNFT $150.00 $24,450.00
8 out of 16
Project No: AZ FLAP 237(1)
Project Name: Mormon Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0660 60201-0900 30-INCH PIPE CULVERT
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $150.00 $4,200.00 Stormwater Plans, LLC dba SWP Contracting and Paving $190.00 $5,320.00 Vastco, Inc. $397.00 $11,116.00 Standard Construction Company, Inc. $197.00 $5,516.00 Engineer's Estimate 28 LNFT $160.00 $4,480.00
A0680 60201-1000 36-INCH PIPE CULVERT
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $390.00 $10,140.00 Stormwater Plans, LLC dba SWP Contracting and Paving $325.00 $8,450.00 Vastco, Inc. $671.00 $17,446.00 Standard Construction Company, Inc. $328.00 $8,528.00 Engineer's Estimate 26.0 LNFT $235.00 $6,110.00
A0700 60210-0600 END SECTION FOR 18-INCH PIPE CULVERT
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $700.00 $9,100.00 Stormwater Plans, LLC dba SWP Contracting and Paving $475.00 $6,175.00 Vastco, Inc. $527.00 $6,851.00 Standard Construction Company, Inc. $490.00 $6,370.00 Engineer's Estimate 13 EACH $500.00 $6,500.00
A0720 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $750.00 $15,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving $525.00 $10,500.00 Vastco, Inc. $620.00 $12,400.00 Standard Construction Company, Inc. $640.00 $12,800.00 Engineer's Estimate 20 EACH $600.00 $12,000.00
A0740 60210-0900 END SECTION FOR 30-INCH PIPE CULVERT
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $1,300.00 $6,500.00 Stormwater Plans, LLC dba SWP Contracting and Paving $700.00 $3,500.00 Vastco, Inc. $900.00 $4,500.00 Standard Construction Company, Inc. $980.00 $4,900.00 Engineer's Estimate 5 EACH $650.00 $3,250.00
9 out of 16
Project No: AZ FLAP 237(1)
Project Name: Mormon Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0760 60210-1000 END SECTION FOR 36-INCH PIPE CULVERT
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $1,500.00 $12,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving $850.00 $6,800.00 Vastco, Inc. $1,086.00 $8,688.00 Standard Construction Company, Inc. $1,230.00 $9,840.00 Engineer's Estimate 8 EACH $800.00 $6,400.00
A0780 60220-1800 8 FEET SPAN, 4 FEET RISE PRECAST REINFORCED CONCRETE BOX CULVERT
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $2,350.00 $51,700.00 Stormwater Plans, LLC dba SWP Contracting and Paving $2,600.00 $57,200.00 Vastco, Inc. $2,430.00 $53,460.00 Standard Construction Company, Inc. $1,420.00 $31,240.00 Engineer's Estimate 22 LNFT $3,000.00 $66,000.00
A0800 60704-0000 CLEANING CULVERT IN PLACE
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $400.00 $12,400.00 Stormwater Plans, LLC dba SWP Contracting and Paving $600.00 $18,600.00 Vastco, Inc. $1,465.00 $45,415.00 Standard Construction Company, Inc. $1,850.00 $57,350.00 Engineer's Estimate 31 EACH $1,200.00 $37,200.00
A0820 60901-8000 CURB, TIMBER
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $16.00 $2,080.00 Stormwater Plans, LLC dba SWP Contracting and Paving $50.00 $6,500.00 Vastco, Inc. $42.00 $5,460.00 Standard Construction Company, Inc. $15.00 $1,950.00 Engineer's Estimate 130 LNFT $35.00 $4,550.00
A0840 60902-1100 CURB AND GUTTER, CONCRETE, 13-INCH DEPTH
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $27.00 $6,615.00 Stormwater Plans, LLC dba SWP Contracting and Paving $45.00 $11,025.00 Vastco, Inc. $40.00 $9,800.00 Standard Construction Company, Inc. $39.00 $9,555.00 Engineer's Estimate 245 LNFT $35.00 $8,575.00
10 out of 16
Project No: AZ FLAP 237(1)
Project Name: Mormon Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0860 61901-0000 FENCE
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $80.00 $24,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving $10.00 $3,000.00 Vastco, Inc. $58.50 $17,550.00 Standard Construction Company, Inc. $50.00 $15,000.00 Engineer's Estimate 300 LNFT $40.00 $12,000.00
A0880 61903-1300 CATTLE GUARD, 36 FEET
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $25,000.00 $100,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving $30,000.00 $120,000.00 Vastco, Inc. $22,100.00 $88,400.00 Standard Construction Company, Inc. $30,000.00 $120,000.00 Engineer's Estimate 4 EACH $25,000.00 $100,000.00
A0900 62201-0200 DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $95.00 $5,700.00 Stormwater Plans, LLC dba SWP Contracting and Paving $110.00 $6,600.00 Vastco, Inc. $122.00 $7,320.00 Standard Construction Company, Inc. $120.00 $7,200.00 Engineer's Estimate 60 HOUR $115.00 $6,900.00
A0920 62201-0350 BACKHOE
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $85.00 $5,100.00 Stormwater Plans, LLC dba SWP Contracting and Paving $100.00 $6,000.00 Vastco, Inc. $109.00 $6,540.00 Standard Construction Company, Inc. $130.00 $7,800.00 Engineer's Estimate 60 HOUR $125.00 $7,500.00
A0940 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $115.00 $6,900.00 Stormwater Plans, LLC dba SWP Contracting and Paving $100.00 $6,000.00 Vastco, Inc. $137.50 $8,250.00 Standard Construction Company, Inc. $220.00 $13,200.00 Engineer's Estimate 60 HOUR $130.00 $7,800.00
11 out of 16
Project No: AZ FLAP 237(1)
Project Name: Mormon Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0960 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $150.00 $9,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving $110.00 $6,600.00 Vastco, Inc. $155.00 $9,300.00 Standard Construction Company, Inc. $270.00 $16,200.00 Engineer's Estimate 60 HOUR $150.00 $9,000.00
A0980 62201-3300 HYDRAULIC EXCAVATOR, 3/4 CUBIC YARD MINIMUM CAPACITY
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $165.00 $9,900.00 Stormwater Plans, LLC dba SWP Contracting and Paving $130.00 $7,800.00 Vastco, Inc. $158.00 $9,480.00 Standard Construction Company, Inc. $230.00 $13,800.00 Engineer's Estimate 60 HOUR $150.00 $9,000.00
A1000 62301-0000 GENERAL LABOR
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $35.00 $2,100.00 Stormwater Plans, LLC dba SWP Contracting and Paving $35.00 $2,100.00 Vastco, Inc. $56.30 $3,378.00 Standard Construction Company, Inc. $64.00 $3,840.00 Engineer's Estimate 60 HOUR $40.00 $2,400.00
A1020 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $125.00 $12,500.00 Stormwater Plans, LLC dba SWP Contracting and Paving $150.00 $15,000.00 Vastco, Inc. $100.00 $10,000.00 Standard Construction Company, Inc. $190.00 $19,000.00 Engineer's Estimate 100 HOUR $120.00 $12,000.00
A1040 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $135.00 $13,500.00 Stormwater Plans, LLC dba SWP Contracting and Paving $150.00 $15,000.00 Vastco, Inc. $176.00 $17,600.00 Standard Construction Company, Inc. $190.00 $19,000.00 Engineer's Estimate 100 HOUR $160.00 $16,000.00
12 out of 16
Project No: AZ FLAP 237(1)
Project Name: Mormon Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1060 62510-2000 SEEDING, HYDRAULIC METHOD
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $900.00 $22,500.00 Stormwater Plans, LLC dba SWP Contracting and Paving $650.00 $16,250.00 Vastco, Inc. $752.00 $18,800.00 Standard Construction Company, Inc. $640.00 $16,000.00 Engineer's Estimate 25.0 ACRE $1,200.00 $30,000.00
A1080 62515-2000 MULCHING, HYDRAULIC METHOD
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $1,250.00 $31,250.00 Stormwater Plans, LLC dba SWP Contracting and Paving $1,050.00 $26,250.00 Vastco, Inc. $1,095.00 $27,375.00 Standard Construction Company, Inc. $3,600.00 $90,000.00 Engineer's Estimate 25.0 ACRE $1,400.00 $35,000.00
A1100 63301-0000 SIGN SYSTEM
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $600.00 $79,800.00 Stormwater Plans, LLC dba SWP Contracting and Paving $450.00 $59,850.00 Vastco, Inc. $425.00 $56,525.00 Standard Construction Company, Inc. $350.00 $46,550.00 Engineer's Estimate 133 EACH $650.00 $86,450.00
A1120 63308-2000 OBJECT MARKER, TYPE 2
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $81.00 $13,365.00 Stormwater Plans, LLC dba SWP Contracting and Paving $165.00 $27,225.00 Vastco, Inc. $48.00 $7,920.00 Standard Construction Company, Inc. $160.00 $26,400.00 Engineer's Estimate 165 EACH $120.00 $19,800.00
A1140 63309-0000 DELINEATOR
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $54.00 $10,854.00 Stormwater Plans, LLC dba SWP Contracting and Paving $165.00 $33,165.00 Vastco, Inc. $41.00 $8,241.00 Standard Construction Company, Inc. $68.00 $13,668.00 Engineer's Estimate 201 EACH $85.00 $17,085.00
13 out of 16
Project No: AZ FLAP 237(1)
Project Name: Mormon Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1160 63316-1000 REMOVE AND RESET SIGN
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $675.00 $5,400.00 Stormwater Plans, LLC dba SWP Contracting and Paving $300.00 $2,400.00 Vastco, Inc. $443.00 $3,544.00 Standard Construction Company, Inc. $225.00 $1,800.00 Engineer's Estimate 8 EACH $300.00 $2,400.00
A1180 63402-0300 PAVEMENT MARKINGS, TYPE B, SOLID
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $450.00 $34,650.00 Stormwater Plans, LLC dba SWP Contracting and Paving $500.00 $38,500.00 Vastco, Inc. $527.00 $40,579.00 Standard Construction Company, Inc. $580.00 $44,660.00 Engineer's Estimate 77.0 MILE $1,000.00 $77,000.00
A1200 63402-0400 PAVEMENT MARKINGS, TYPE B, BROKEN
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $500.00 $4,500.00 Stormwater Plans, LLC dba SWP Contracting and Paving $550.00 $4,950.00 Vastco, Inc. $585.00 $5,265.00 Standard Construction Company, Inc. $645.00 $5,805.00 Engineer's Estimate 9.0 MILE $600.00 $5,400.00
A1220 63405-0050 PAVEMENT MARKINGS, SYMBOLS
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $100.00 $2,200.00 Stormwater Plans, LLC dba SWP Contracting and Paving $110.00 $2,420.00 Vastco, Inc. $117.00 $2,574.00 Standard Construction Company, Inc. $130.00 $2,860.00 Engineer's Estimate 22 EACH $200.00 $4,400.00
A1240 63405-0550 PAVEMENT MARKINGS, TYPE B, STRAIGHT ARROW
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $100.00 $400.00 Stormwater Plans, LLC dba SWP Contracting and Paving $110.00 $440.00 Vastco, Inc. $117.00 $468.00 Standard Construction Company, Inc. $130.00 $520.00 Engineer's Estimate 4 EACH $200.00 $800.00
14 out of 16
Project No: AZ FLAP 237(1)
Project Name: Mormon Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1260 63405-0850 PAVEMENT MARKINGS, TYPE B, ACCESSIBILITY SYMBOL
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $100.00 $300.00 Stormwater Plans, LLC dba SWP Contracting and Paving $110.00 $330.00 Vastco, Inc. $117.00 $351.00 Standard Construction Company, Inc. $130.00 $390.00 Engineer's Estimate 3 EACH $100.00 $300.00
A1280 63501-1000 TEMPORARY TRAFFIC CONTROL, TRAFFIC CONTROL SUPERVISOR
LaForge and Budd Construction Company, Inc. Lump Sum $0.00 Intermountain West Civil Constructors, Inc. Lump Sum $50,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $250,000.00 Vastco, Inc. Lump Sum $18,525.00 Standard Construction Company, Inc. Lump Sum $63,000.00 Engineer's Estimate ALL LPSM Lump Sum $200,000.00
A1300 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $20.00 $10,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving $5.00 $2,500.00 Vastco, Inc. $20.40 $10,200.00 Standard Construction Company, Inc. $20.00 $10,000.00 Engineer's Estimate 500 EACH $25.00 $12,500.00
A1320 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $60.00 $30,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving $45.00 $22,500.00 Vastco, Inc. $57.40 $28,700.00 Standard Construction Company, Inc. $57.00 $28,500.00 Engineer's Estimate 500 EACH $70.00 $35,000.00
A1340 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $5,500.00 $11,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving $5,000.00 $10,000.00 Vastco, Inc. $5,866.00 $11,732.00 Standard Construction Company, Inc. $5,800.00 $11,600.00 Engineer's Estimate 2 EACH $6,000.00 $12,000.00
15 out of 16
Project No: AZ FLAP 237(1)
Project Name: Mormon Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1360 63503-1000 TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $1.00 $500.00 Stormwater Plans, LLC dba SWP Contracting and Paving $6.00 $3,000.00 Vastco, Inc. $1.10 $550.00 Standard Construction Company, Inc. $1.00 $500.00 Engineer's Estimate 500 LNFT $3.00 $1,500.00
A1380 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $15.00 $3,600.00 Stormwater Plans, LLC dba SWP Contracting and Paving $7.00 $1,680.00 Vastco, Inc. $17.55 $4,212.00 Standard Construction Company, Inc. $18.00 $4,320.00 Engineer's Estimate 240 SQFT $30.00 $7,200.00
A1400 63505-1000 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $650.00 $26,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving $550.00 $22,000.00 Vastco, Inc. $585.50 $23,420.00 Standard Construction Company, Inc. $620.00 $24,800.00 Engineer's Estimate 40.0 MILE $1,200.00 $48,000.00
A1420 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $29.00 $203,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving $35.00 $245,000.00 Vastco, Inc. $32.00 $224,000.00 Standard Construction Company, Inc. $45.00 $315,000.00 Engineer's Estimate 7,000 HOUR $35.00 $245,000.00
A1440 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $44.00 $132,000.00 Stormwater Plans, LLC dba SWP Contracting and Paving $45.00 $135,000.00 Vastco, Inc. $45.50 $136,500.00 Standard Construction Company, Inc. $70.00 $210,000.00 Engineer's Estimate 3,000 HOUR $50.00 $150,000.00
16 out of 16
Project No: AZ FLAP 237(1)
Project Name: Mormon Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1460 63610-0000 CONDUIT
LaForge and Budd Construction Company, Inc. $0.00 $0.00 Intermountain West Civil Constructors, Inc. $40.00 $1,600.00 Stormwater Plans, LLC dba SWP Contracting and Paving $100.00 $4,000.00 Vastco, Inc. $47.00 $1,880.00 Standard Construction Company, Inc. $170.00 $6,800.00 Engineer's Estimate 40 LNFT $10.00 $400.00
Total Schedule - All Items
LaForge and Budd Construction Company, Inc. $0.00 Intermountain West Civil Constructors, Inc. $9,449,044.70 Stormwater Plans, LLC dba SWP Contracting and Paving $9,749,920.00 Vastco, Inc. $11,380,554.14 Standard Construction Company, Inc. $17,029,775.00 Engineer's Estimate $10,708,050.00