NM_FLAP_US60(1)_Bid_Tabulation_6982AF18B000023.pdf

PDF 32 KB Posted

Attached to
NM FLAP US60(1) Federal contract opportunity
Solicitation number
6982AF18B000023
Issued by
Department of Transportation Federal Highway Administration

About this file

Bid Tabulation

View the file

Other files for this federal contract opportunity

Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tabulation of Bids Report Date: 08/20/18

1 out of 13Source Selection Information - See FAR 2.101 & 3.104

Project No: NM FLAP US60(1)

Project Name: Old US 60 Bridge

Schedule: A

Schedule Type: Base

Solcitation No:

Division: Central Federal Lands

State: NM County: Socorro

Federal Land: Sevilleta National Wildlife Refuge Opened at: Lakewood

Opened by: Sheri Muehl

Date: 08/09/18

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Structures Inc. ( $5,468,432.20 ) no 4 Iverness Ct East Englewood, CO 80112

Groundhog Excavating Inc. $6,048,371.96 792 Nikanda Rd NE Albuquerque, NM 87107

VITAL Consulting Group, LLC $6,971,521.00 5200 Oakland Ave NE, Suite D Albuquerque, NM 87113

Engineer's Estimate $5,520,000.00

2 out of 13Source Selection Information - See FAR 2.101 & 3.104

Project No: NM FLAP US60(1)

Project Name: Old US 60 Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0020 15101-0000 MOBILIZATION

Structures Inc. Lump Sum $438,000.00 Groundhog Excavating Inc. Lump Sum $541,000.00 VITAL Consulting Group, LLC Lump Sum $630,000.00 Engineer's Estimate ALL LPSM Lump Sum $567,796.00

A0040 15206-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING STAKE

Structures Inc. $3,300.00 $749.10 Groundhog Excavating Inc. $105,912.00 $24,042.02 VITAL Consulting Group, LLC $32,300.00 $7,332.10 Engineer's Estimate 0.227 MILE $40,000.00 $9,080.00

A0060 15214-1000 SURVEY AND STAKING, BRIDGE

Structures Inc. Lump Sum $23,000.00 Groundhog Excavating Inc. Lump Sum $16,028.00 VITAL Consulting Group, LLC Lump Sum $51,200.00 Engineer's Estimate ALL LPSM Lump Sum $15,000.00

A0080 15236-2000 SURVEY CONTROL, GRADE FINISHING

Structures Inc. $10,300.00 $4,676.20 Groundhog Excavating Inc. $14,121.00 $6,410.93 VITAL Consulting Group, LLC $50,600.00 $22,972.40 Engineer's Estimate 0.454 MILE $25,000.00 $11,350.00

A0100 15301-0000 CONTRACTOR QUALITY CONTROL

Structures Inc. Lump Sum $41,160.00 Groundhog Excavating Inc. Lump Sum $96,549.00 VITAL Consulting Group, LLC Lump Sum $150,000.00 Engineer's Estimate ALL LPSM Lump Sum $71,250.00

A0120 15401-0000 CONTRACTOR TESTING

Structures Inc. Lump Sum $22,800.00 Groundhog Excavating Inc. Lump Sum $35,040.00 VITAL Consulting Group, LLC Lump Sum $33,400.00 Engineer's Estimate ALL LPSM Lump Sum $95,000.00

3 out of 13Source Selection Information - See FAR 2.101 & 3.104

Project No: NM FLAP US60(1)

Project Name: Old US 60 Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0140 15501-0000 CONSTRUCTION SCHEDULE

Structures Inc. Lump Sum $4,520.00 Groundhog Excavating Inc. Lump Sum $4,370.00 VITAL Consulting Group, LLC Lump Sum $22,200.00 Engineer's Estimate ALL LPSM Lump Sum $23,750.00

A0160 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

Structures Inc. $5.15 $15,913.50 Groundhog Excavating Inc. $3.70 $11,433.00 VITAL Consulting Group, LLC $4.00 $12,360.00 Engineer's Estimate 3,090 LNFT $7.50 $23,175.00

A0180 15706-0200 SOIL EROSION CONTROL, CHECK DAM

Structures Inc. $226.00 $2,034.00 Groundhog Excavating Inc. $329.00 $2,961.00 VITAL Consulting Group, LLC $120.00 $1,080.00 Engineer's Estimate 9 EACH $180.00 $1,620.00

A0200 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION EXIT

Structures Inc. $2,266.00 $4,532.00 Groundhog Excavating Inc. $3,043.00 $6,086.00 VITAL Consulting Group, LLC $3,350.00 $6,700.00 Engineer's Estimate 2 EACH $2,500.00 $5,000.00

A0220 15802-0000 WATERING FOR DUST CONTROL

Structures Inc. Lump Sum $68,160.00 Groundhog Excavating Inc. Lump Sum $80,512.00 VITAL Consulting Group, LLC Lump Sum $123,750.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00

A0240 20101-0000 CLEARING AND GRUBBING

Structures Inc. $5,280.00 $25,344.00 Groundhog Excavating Inc. $3,763.00 $18,062.40 VITAL Consulting Group, LLC $10,000.00 $48,000.00 Engineer's Estimate 4.8 ACRE $5,000.00 $24,000.00

4 out of 13Source Selection Information - See FAR 2.101 & 3.104

Project No: NM FLAP US60(1)

Project Name: Old US 60 Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0260 20301-0600 REMOVAL OF CATTLE GUARD

Structures Inc. $3,756.00 $3,756.00 Groundhog Excavating Inc. $1,375.00 $1,375.00 VITAL Consulting Group, LLC $3,500.00 $3,500.00 Engineer's Estimate 1 EACH $2,600.00 $2,600.00

A0280 20301-2400 REMOVAL OF SIGN

Structures Inc. $56.50 $791.00 Groundhog Excavating Inc. $133.00 $1,862.00 VITAL Consulting Group, LLC $35.00 $490.00 Engineer's Estimate 14 EACH $95.00 $1,330.00

A0300 20302-0700 REMOVAL OF FENCE

Structures Inc. $5.50 $660.00 Groundhog Excavating Inc. $9.00 $1,080.00 VITAL Consulting Group, LLC $4.00 $480.00 Engineer's Estimate 120 LNFT $6.00 $720.00

A0320 20304-2000 REMOVAL OF BRIDGE

Structures Inc. Lump Sum $111,750.00 Groundhog Excavating Inc. Lump Sum $46,766.00 VITAL Consulting Group, LLC Lump Sum $97,000.00 Engineer's Estimate ALL LPSM Lump Sum $150,000.00

A0340 20420-0000 EMBANKMENT CONSTRUCTION

Structures Inc. $18.50 $342,250.00 Groundhog Excavating Inc. $14.00 $259,000.00 VITAL Consulting Group, LLC $12.25 $226,625.00 Engineer's Estimate 18,500 CUYD $25.00 $462,500.00

A0360 20803-0000 STRUCTURAL BACKFILL

Structures Inc. $63.00 $4,158.00 Groundhog Excavating Inc. $287.00 $18,942.00 VITAL Consulting Group, LLC $57.00 $3,762.00 Engineer's Estimate 66 CUYD $65.00 $4,290.00

5 out of 13Source Selection Information - See FAR 2.101 & 3.104

Project No: NM FLAP US60(1)

Project Name: Old US 60 Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0380 21101-1000 ROADWAY OBLITERATION, METHOD 1

Structures Inc. $2.75 $4,125.00 Groundhog Excavating Inc. $8.00 $12,000.00 VITAL Consulting Group, LLC $11.00 $16,500.00 Engineer's Estimate 1,500 SQYD $4.00 $6,000.00

A0400 25101-2200 PLACED RIPRAP, METHOD B, CLASS 2

Structures Inc. $85.00 $80,750.00 Groundhog Excavating Inc. $104.00 $98,800.00 VITAL Consulting Group, LLC $140.00 $133,000.00 Engineer's Estimate 950 CUYD $130.00 $123,500.00

A0420 30202-2000 ROADWAY AGGREGATE, METHOD 2

Structures Inc. $36.00 $50,400.00 Groundhog Excavating Inc. $27.00 $37,800.00 VITAL Consulting Group, LLC $46.00 $64,400.00 Engineer's Estimate 1,400 TON $60.00 $84,000.00

A0440 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1

Structures Inc. $107.00 $60,990.00 Groundhog Excavating Inc. $152.00 $86,640.00 VITAL Consulting Group, LLC $225.00 $128,250.00 Engineer's Estimate 570 TON $140.00 $79,800.00

A0460 40601-0000 FOG SEAL

Structures Inc. $642.00 $1,284.00 Groundhog Excavating Inc. $1,249.00 $2,498.00 VITAL Consulting Group, LLC $825.00 $1,650.00 Engineer's Estimate 2.0 TON $1,700.00 $3,400.00

A0480 41102-1000 PRIME COAT, METHOD 1

Structures Inc. $0.60 $2,160.00 Groundhog Excavating Inc. $1.60 $5,760.00 VITAL Consulting Group, LLC $18.00 $64,800.00 Engineer's Estimate 3,600 SQYD $2.00 $7,200.00

6 out of 13Source Selection Information - See FAR 2.101 & 3.104

Project No: NM FLAP US60(1)

Project Name: Old US 60 Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0500 41105-0000 BLOTTER

Structures Inc. $239.00 $956.00 Groundhog Excavating Inc. $327.00 $1,308.00 VITAL Consulting Group, LLC $1,500.00 $6,000.00 Engineer's Estimate 4 TON $60.00 $240.00

A0520 41201-0000 TACK COAT

Structures Inc. $885.00 $1,770.00 Groundhog Excavating Inc. $989.00 $1,978.00 VITAL Consulting Group, LLC $1,500.00 $3,000.00 Engineer's Estimate 2.0 TON $1,200.00 $2,400.00

A0540 55101-2200 STEEL PIPE PILE, IN PLACE (24" x 1")

Structures Inc. $375.00 $415,125.00 Groundhog Excavating Inc. $691.00 $764,937.00 VITAL Consulting Group, LLC $905.00 $1,001,835.00 Engineer's Estimate 1,107 LNFT $300.00 $332,100.00

A0560 55104-1000 DYNAMIC PILE LOAD TEST

Structures Inc. $2,008.00 $8,032.00 Groundhog Excavating Inc. $7,103.00 $28,412.00 VITAL Consulting Group, LLC $3,350.00 $13,400.00 Engineer's Estimate 4 EACH $5,000.00 $20,000.00

A0580 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)

Structures Inc. $880.00 $554,400.00 Groundhog Excavating Inc. $762.00 $480,060.00 VITAL Consulting Group, LLC $980.00 $617,400.00 Engineer's Estimate 630 CUYD $1,300.00 $819,000.00

A0600 55235-0000 EXPANSION JOINTS

Structures Inc. $247.00 $14,326.00 Groundhog Excavating Inc. $233.00 $13,514.00 VITAL Consulting Group, LLC $200.00 $11,600.00 Engineer's Estimate 58 LNFT $200.00 $11,600.00

7 out of 13Source Selection Information - See FAR 2.101 & 3.104

Project No: NM FLAP US60(1)

Project Name: Old US 60 Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0620 55401-1000 REINFORCING STEEL

Structures Inc. $1.20 $14,100.00 Groundhog Excavating Inc. $1.80 $21,150.00 VITAL Consulting Group, LLC $1.25 $14,687.50 Engineer's Estimate 11,750 LB $1.50 $17,625.00

A0640 55401-2000 REINFORCING STEEL, EPOXY COATED

Structures Inc. $1.36 $233,539.20 Groundhog Excavating Inc. $1.70 $291,924.00 VITAL Consulting Group, LLC $1.40 $240,408.00 Engineer's Estimate 171,720 LB $1.70 $291,924.00

A0660 55502-0000 STRUCTURAL STEEL, FURNISHED, FABRICATED, AND ERECTED

Structures Inc. $2.95 $2,254,685.00 Groundhog Excavating Inc. $2.92 $2,231,756.00 VITAL Consulting Group, LLC $3.15 $2,407,545.00 Engineer's Estimate 764,300 LB $1.80 $1,375,740.00

A0680 55601-0900 BRIDGE RAILING, STEEL (NM TYPE A32)

Structures Inc. $244.00 $292,800.00 Groundhog Excavating Inc. $262.00 $314,400.00 VITAL Consulting Group, LLC $260.00 $312,000.00 Engineer's Estimate 1,200 LNFT $225.00 $270,000.00

A0700 56401-1000 BEARING DEVICE, ELASTOMERIC (EXPANSION)

Structures Inc. $4,030.00 $32,240.00 Groundhog Excavating Inc. $2,540.00 $20,320.00 VITAL Consulting Group, LLC $2,200.00 $17,600.00 Engineer's Estimate 8 EACH $1,500.00 $12,000.00

A0720 56401-1000 BEARING DEVICE, ELASTOMERIC (FIXED)

Structures Inc. $2,905.00 $23,240.00 Groundhog Excavating Inc. $2,540.00 $20,320.00 VITAL Consulting Group, LLC $2,650.00 $21,200.00 Engineer's Estimate 8 EACH $1,200.00 $9,600.00

8 out of 13Source Selection Information - See FAR 2.101 & 3.104

Project No: NM FLAP US60(1)

Project Name: Old US 60 Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0740 60801-0400 PAVED WATERWAY, TYPE 4

Structures Inc. $180.00 $900.00 Groundhog Excavating Inc. $439.00 $2,195.00 VITAL Consulting Group, LLC $230.00 $1,150.00 Engineer's Estimate 5 SQYD $150.00 $750.00

A0760 60901-1100 CURB, CONCRETE, 13-INCH DEPTH

Structures Inc. $29.00 $2,465.00 Groundhog Excavating Inc. $41.00 $3,485.00 VITAL Consulting Group, LLC $30.00 $2,550.00 Engineer's Estimate 85 LNFT $35.00 $2,975.00

A0780 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS

Structures Inc. $86.00 $2,150.00 Groundhog Excavating Inc. $56.00 $1,400.00 VITAL Consulting Group, LLC $55.00 $1,375.00 Engineer's Estimate 25 LNFT $85.00 $2,125.00

A0800 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT

Structures Inc. $3,038.00 $12,152.00 Groundhog Excavating Inc. $3,084.00 $12,336.00 VITAL Consulting Group, LLC $3,000.00 $12,000.00 Engineer's Estimate 4 EACH $3,400.00 $13,600.00

A0820 61707-0000 STRUCTURE TRANSITION RAILING

Structures Inc. $41.00 $8,200.00 Groundhog Excavating Inc. $93.00 $18,600.00 VITAL Consulting Group, LLC $92.00 $18,400.00 Engineer's Estimate 200 LNFT $125.00 $25,000.00

A0840 61801-0000 CONCRETE BARRIER (PRECAST)

Structures Inc. $80.00 $3,200.00 Groundhog Excavating Inc. $101.00 $4,040.00 VITAL Consulting Group, LLC $85.00 $3,400.00 Engineer's Estimate 40 LNFT $155.00 $6,200.00

9 out of 13Source Selection Information - See FAR 2.101 & 3.104

Project No: NM FLAP US60(1)

Project Name: Old US 60 Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0860 61901-0600 FENCE, BARBED WIRE (TYPE 3)

Structures Inc. $20.00 $10,400.00 Groundhog Excavating Inc. $16.60 $8,632.00 VITAL Consulting Group, LLC $7.00 $3,640.00 Engineer's Estimate 520 LNFT $8.00 $4,160.00

A0880 61903-1500 CATTLE GUARD, 40 FEET

Structures Inc. $28,350.00 $28,350.00 Groundhog Excavating Inc. $43,764.00 $43,764.00 VITAL Consulting Group, LLC $48,000.00 $48,000.00 Engineer's Estimate 1 EACH $32,000.00 $32,000.00

A0900 62201-0200 DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY

Structures Inc. $103.00 $2,060.00 Groundhog Excavating Inc. $107.00 $2,140.00 VITAL Consulting Group, LLC $125.00 $2,500.00 Engineer's Estimate 20 HOUR $110.00 $2,200.00

A0920 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY

Structures Inc. $113.00 $2,260.00 Groundhog Excavating Inc. $98.00 $1,960.00 VITAL Consulting Group, LLC $125.00 $2,500.00 Engineer's Estimate 20 HOUR $115.00 $2,300.00

A0940 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE

Structures Inc. $154.00 $3,080.00 Groundhog Excavating Inc. $128.00 $2,560.00 VITAL Consulting Group, LLC $190.00 $3,800.00 Engineer's Estimate 20 HOUR $150.00 $3,000.00

A0960 62301-0000 GENERAL LABOR

Structures Inc. $39.00 $1,560.00 Groundhog Excavating Inc. $43.00 $1,720.00 VITAL Consulting Group, LLC $63.00 $2,520.00 Engineer's Estimate 40 HOUR $45.00 $1,800.00

10 out of 13Source Selection Information - See FAR 2.101 & 3.104

Project No: NM FLAP US60(1)

Project Name: Old US 60 Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0980 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES

Structures Inc. $62.00 $1,240.00 Groundhog Excavating Inc. $188.00 $3,760.00 VITAL Consulting Group, LLC $190.00 $3,800.00 Engineer's Estimate 20 HOUR $150.00 $3,000.00

A1000 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES

Structures Inc. $154.00 $3,080.00 Groundhog Excavating Inc. $201.00 $4,020.00 VITAL Consulting Group, LLC $370.00 $7,400.00 Engineer's Estimate 20 HOUR $170.00 $3,400.00

A1020 62406-0200 PLACING CONSERVED TOPSOIL, 3-INCH DEPTH

Structures Inc. $6,180.00 $11,124.00 Groundhog Excavating Inc. $1,660.00 $2,988.00 VITAL Consulting Group, LLC $3,125.00 $5,625.00 Engineer's Estimate 1.8 ACRE $3,000.00 $5,400.00

A1040 62510-1000 SEEDING, DRY METHOD

Structures Inc. $2,502.00 $4,503.60 Groundhog Excavating Inc. $1,752.00 $3,153.60 VITAL Consulting Group, LLC $3,300.00 $5,940.00 Engineer's Estimate 1.8 ACRE $3,400.00 $6,120.00

A1060 62515-1000 MULCHING, DRY METHOD

Structures Inc. $2,502.00 $4,503.60 Groundhog Excavating Inc. $2,232.00 $4,017.60 VITAL Consulting Group, LLC $3,300.00 $5,940.00 Engineer's Estimate 1.8 ACRE $3,000.00 $5,400.00

A1080 62635-2000 CUTTINGS, WILLOW STAKING

Structures Inc. $21.00 $210.00 Groundhog Excavating Inc. $169.00 $1,690.00 VITAL Consulting Group, LLC $335.00 $3,350.00 Engineer's Estimate 10 EACH $25.00 $250.00

11 out of 13Source Selection Information - See FAR 2.101 & 3.104

Project No: NM FLAP US60(1)

Project Name: Old US 60 Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1100 62901-0700 ROLLED EROSION CONTROL PRODUCT, TYPE 2.C

Structures Inc. $3.35 $18,760.00 Groundhog Excavating Inc. $2.50 $14,000.00 VITAL Consulting Group, LLC $5.00 $28,000.00 Engineer's Estimate 5,600 SQYD $4.00 $22,400.00

A1120 63301-0000 SIGN SYSTEM

Structures Inc. $198.00 $396.00 Groundhog Excavating Inc. $463.00 $926.00 VITAL Consulting Group, LLC $400.00 $800.00 Engineer's Estimate 2 EACH $420.00 $840.00

A1140 63308-3000 OBJECT MARKER, TYPE 3

Structures Inc. $107.00 $856.00 Groundhog Excavating Inc. $77.00 $616.00 VITAL Consulting Group, LLC $75.00 $600.00 Engineer's Estimate 8 EACH $170.00 $1,360.00

A1160 63309-0000 DELINEATOR

Structures Inc. $28.00 $1,232.00 Groundhog Excavating Inc. $32.00 $1,408.00 VITAL Consulting Group, LLC $31.00 $1,364.00 Engineer's Estimate 44 EACH $85.00 $3,740.00

A1180 63316-1000 REMOVE AND RESET SIGN

Structures Inc. $186.00 $372.00 Groundhog Excavating Inc. $718.00 $1,436.00 VITAL Consulting Group, LLC $245.00 $490.00 Engineer's Estimate 2 EACH $50.00 $100.00

A1200 63402-0300 PAVEMENT MARKINGS, TYPE B, SOLID

Structures Inc. $670.00 $1,876.00 Groundhog Excavating Inc. $3,578.00 $10,018.40 VITAL Consulting Group, LLC $4,300.00 $12,040.00 Engineer's Estimate 2.8 MILE $1,550.00 $4,340.00

12 out of 13Source Selection Information - See FAR 2.101 & 3.104

Project No: NM FLAP US60(1)

Project Name: Old US 60 Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1220 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE

Structures Inc. $21.00 $1,050.00 Groundhog Excavating Inc. $32.00 $1,600.00 VITAL Consulting Group, LLC $37.00 $1,850.00 Engineer's Estimate 50 EACH $25.00 $1,250.00

A1240 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM

Structures Inc. $34.00 $1,700.00 Groundhog Excavating Inc. $98.00 $4,900.00 VITAL Consulting Group, LLC $55.00 $2,750.00 Engineer's Estimate 50 EACH $70.00 $3,500.00

A1260 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B

Structures Inc. $9.00 $36.00 Groundhog Excavating Inc. $149.00 $596.00 VITAL Consulting Group, LLC $4,500.00 $18,000.00 Engineer's Estimate 4 EACH $90.00 $360.00

A1280 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN

Structures Inc. $6,700.00 $13,400.00 Groundhog Excavating Inc. $12,371.00 $24,742.00 VITAL Consulting Group, LLC $11,000.00 $22,000.00 Engineer's Estimate 2 EACH $10,000.00 $20,000.00

A1300 63503-0300 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3

Structures Inc. $98.00 $3,920.00 Groundhog Excavating Inc. $63.00 $2,520.00 VITAL Consulting Group, LLC $190.00 $7,600.00 Engineer's Estimate 40 LNFT $60.00 $2,400.00

A1320 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

Structures Inc. $16.00 $2,720.00 Groundhog Excavating Inc. $13.00 $2,210.00 VITAL Consulting Group, LLC $33.00 $5,610.00 Engineer's Estimate 170 SQFT $32.00 $5,440.00

13 out of 13Source Selection Information - See FAR 2.101 & 3.104

Project No: NM FLAP US60(1)

Project Name: Old US 60 Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1340 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER

Structures Inc. $40.00 $32,000.00 Groundhog Excavating Inc. $32.00 $25,600.00 VITAL Consulting Group, LLC $88.00 $70,400.00 Engineer's Estimate 800 HOUR $50.00 $40,000.00

A1360 65001-1000 CONSTRUCT AND MAINTAIN DIVERSION

Structures Inc. Lump Sum $129,500.00 Groundhog Excavating Inc. Lump Sum $230,242.00 VITAL Consulting Group, LLC Lump Sum $150,000.00 Engineer's Estimate ALL LPSM Lump Sum $350,000.00

Total Schedule - All Items

Structures Inc. $5,468,432.20 Groundhog Excavating Inc. $6,048,371.96 VITAL Consulting Group, LLC $6,971,521.00 Engineer's Estimate $5,520,000.00