Amendment 0005.pdf
PDF 186 KB Posted
- Attached to
- Replace Roof and Exhaust Fans - Houston ARTCC
- Solicitation number
- 697DCK-22-R-00018
About this file
This document consists of an amendment to a solicitation for replacing the roof and exhaust fans at the Houston Air Route Traffic Control Center. The Federal Aviation Administration is seeking offers for the project, which has an estimated construction value between $1,000,000 and $5,000,000. A pre-bid site visit was held on January 3, 2022, and requests for information were due by January 10th with responses provided via amendment. Offers for the project are due by January 24, 2022 and shall be emailed to the identified contracting officer. The amendment provides clarification regarding insulation and slope requirements for the new roof.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site Photos.pdf | ||
| 2. Drawings (1.31.22).pdf | ||
| 1. Specifications (1.31.22).pdf | ||
| RFI Responses.pdf | ||
| 4. Customer Satisfaction Survey.doc | DOC document | |
| Amendment 0004.pdf | ||
| Site Visit Presentation.pdf | ||
| 3. Wage Determination TX20210253 (1.21.22).pdf | ||
| Amendment 0003.pdf | ||
| Amendment 0002.pdf | ||
| Amendment 0001.pdf | ||
| 2. Drawings.pdf | ||
| 697DCK-22-R-00018.pdf | ||
| 4. Customer Satisfaction Survey.doc | DOC document | |
| 1. Specifications.pdf | ||
| 3. Wage Determination TX20210253-7.9.21.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO.
PAGE OF PAGES
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
CODE
9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
Items 8 and 15, and returning is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required.)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.
E. IMPORTANT: Contractor is not, is required to sign this document and return
ORDER NO. IN ITEM 10A.
1 2
0005 03/02/2022
FEDERAL AVIATION ADMINISTRATION
AAQ-500 - REGIONAL ACQUISITIONS
2200 S. 216TH STREET
DES MOINES WA 98198-6547
AAQ530ANM-AFN
x
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ 1 x x
697DCK-22-R-00018
1 copies to the issuing office.
12/15/2021
(x)
See attachment page.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Mark S. Salum
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Attachment Page
14. Description of Amendment (continued): It has been determined necessary and in the best interest of the Government to amend the solicitation to clarify the government’s RFI response to items 10, 12a, and 12b.
14.1. RFI Responses:
“Item 10: TPO Roofing 075423-11 C-7-C: Calls for minimum R value of R30, does this include tapered & cover boards?
Response: Yes. Insulation is required to ne in two or more layers with staggered joints.
Contractors must submit insulation plan for approval.
Item 12a: Is R-30 minimum required at drain or is it average required?
Response: It is average required. Insulation is tapered at the drain.
Item 12b: Is ¼”/ft tapered insulation required in addition to R-30 minimum bade layer?
Response: Tapered insulation is required. ½” slope is required per 20 feet. Insulation slope and layout must be submitted as part of the roofing submittals. Variations will be reviewed depending on the roof location and obstructions. The goal is to minimize water ponding.”
14.2. The following clarification is provided for informational purposes only:
“The roof insulation slope is consistent. The specifications use the slope recommended by the International Building Code, which is a minimum ¼” per foot, unless otherwise specified in the drawings. A slope of ½” per foot is specified to encourage positive drainage across the roof field.
As for the R-value, it is an average value because the height of insulation is going to vary across the roof field. The insulation is being tapered toward the roof drains. There is no insulation at the roof drains. The intent of the design is to encourage positive drainage on the roof and eliminate ponding.
The R-30 is a requirement for ALL areas. Because the insulation tapers around the roof drains, it is obviously less than R-30 near the drains. The tapered sections are required as part of the roofers submittal around the drains and for crickets; they need to figure out how much the tapered sections need to be in order to push the water into the roof drains or scuppers around the perimeter. The slope needs to start from the ridge lines to the roof drain. The goal is to avoid standing water, especially on a flat roof. This is stated in the specifications.
If the awardee can prove that 1/2” per foot is enough, they need to show it on their shop drawings; maybe ¼” per foot is all that is needed. The crickets are inexpensive sections, insulation configuration is what’s important from an R-Value perspective.”
14.3. The offer due date and time is not extended as a result of this amendment. All other terms and conditions of the original solicitation remain unchanged. Offerors shall submit signed/acknowledged copies of all amendments with their firm’s respective proposal.