697DCK-18-R-00406 Amend 0002.pdf

PDF 477 KB Posted

Attached to
AMENDMENT 0003: MAJOR MECHANICAL UPGRADES PROJECT AT FAA'S DENVER ARTCC FACILITY IN LONGMONT, CO
Solicitation number
697DCK-18-R-00406
Issued by

About this file

697DCK-18-R-00406 Amend 0002 (pdf)

View the file

Other files

File Type Posted
Question 30 - RMD-502-40479-A07.pdf PDF
697DCK-18-R-00406 Amend 0003.pdf PDF
Attachment 2 - Past Performance Survey.docx DOCX document
697DCK-18-R-00406.pdf PDF
697DCK-18-R-00406 Amend 0001.pdf PDF
Question 29 - List of Furniture.pdf PDF
Question 30 - RMD-502-40479-A05.pdf PDF
Attachment 1a - FINAL 100% Drawings 07-12-18.pdf PDF
Question 18 and 19 - ZDV-1401893-M901.pdf PDF
Question 61 - 23 21 23 Hydronic Pumps Amendment 10.10.pdf PDF
Attachment 1 - Final 100% Specifications 7-31-2018.pdf PDF
Question 30 - RMD-502-40479-A06.pdf PDF
Question 92 - FAA Order 6000.50E.pdf PDF
Attachment 4 - SF-1413 Subcontractor.pdf PDF
Question 52, 72, and 74 - FAA-STD-019f.pdf PDF
Attachment 3 - DB WD CO180027 dated 8-3-2018.pdf PDF
Question 30 - RMD-502-40479-A07.pdf PDF
Attachment 1a - FINAL 100% Drawings 07-12-18.pdf PDF
Question 52, 72, and 74 - FAA-STD-019f.pdf PDF
Question 30 - RMD-502-40479-A06.pdf PDF
Question 61 - 23 21 23 Hydronic Pumps Amendment 10.10.pdf PDF
Question 92 - FAA Order 6000.50E.pdf PDF
Attachment 4 - SF-1413 Subcontractor.pdf PDF
697DCK-18-R-00406 Amend 0002.pdf PDF
Question 18 and 19 - ZDV-1401893-M901.pdf PDF
Question 30 - RMD-502-40479-A05.pdf PDF
697DCK-18-R-00406.pdf PDF
Attachment 2 - Past Performance Survey.docx DOCX document
Attachment 1 - Final 100% Specifications 7-31-2018.pdf PDF
697DCK-18-R-00406 Amend 0001.pdf PDF
Attachment 3 - DB WD CO180027 dated 8-3-2018.pdf PDF
Question 29 - List of Furniture.pdf PDF
Attachment 1 - Final 100% Specifications 7-31-2018.pdf PDF
Attachment 1a - FINAL 100% Drawings 07-12-18.pdf PDF
697DCK-18-R-00406.pdf PDF
Attachment 4 - SF-1413 Subcontractor.pdf PDF
Attachment 3 - DB WD CO180027 dated 8-3-2018.pdf PDF
Attachment 2 - Past Performance Survey.docx DOCX document
697DCK-18-R-00406 Amend 0001.pdf PDF
697DCK-18-R-00406.pdf PDF
Attachment 4 - SF-1413 Subcontractor.pdf PDF
Attachment 2 - Past Performance Survey.docx DOCX document
Attachment 1a - FINAL 100% Drawings 07-12-18.pdf PDF
Attachment 1 - Final 100% Specifications 7-31-2018.pdf PDF
Attachment 3 - DB WD CO180027 dated 8-3-2018.pdf PDF
Attachment 3 - DB WD CO180027 dated 8-3-2018.pdf PDF
Attachment 1a - FINAL 100% Drawings 07-12-18.pdf PDF
Attachment 1 - Final 100% Specifications 7-31-2018.pdf PDF
Attachment 4 - SF-1413 Subcontractor.pdf PDF
697DCK-18-R-00406.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

697DCK‐18‐R‐00406

Denver Major Mechanical Project

Questions & Answers

1)Question:DrawingS102DetailA8indicatesthescaleof½”–1’0”asdoesthescaleonthedrawing,butthisdoesnot
coincidewiththedimensionsontheplans.Whichiscorrect?

Answer: Drawing was incorrectly labeled and should read ¼” = 1’‐0”

2) Question: Will panels TPS‐1 and TPS‐2 be a part of the temporary chiller package or part of the electrical contractor’s gear?

Answer: TPS‐1 and TPS‐2 are not part of the temporary chiller package. Contractor is to provide panels TPS‐1 and TPS‐2.

3)DeductOption1perSpecificationSection011000Part1.1.10.Acallsforunderground12”pipetobetested.Ifthedeductis
notselected:
a)Question:Whatistheextentofthepipingtoberemoved?Ifitisthepipingundertheexistingpumproomfloor,this
willalsoincludefloorremovalinthepumphouse.Correct?

Answer: If the deduct is not selected, all the piping from the chillers to the cooling towers will be replaced.

b)Question:Whataboutthe6”CTSandCTRthatexitsthebuildingtothesouth?Towhatextentwillthispipingneedto
bereplaced?

Answer: This piping will not be replaced.

c)Question:ElectricalDrawingE104sheetnotesindicateundergroundcircuitandwiringtoremain.Thisconduitwill
beremovedifthefloorisremovedtoreplacetheunderground12”pipe.Howshouldwefigurethiswork?

Answer: Replacement of the 12” pipe will stop at the foundation. The floor will not be removed.

4)Question:DrawingM104andM204talkaboutthesalvageandinstallationofnewscreens.Thedrawingsappearto
indicategratingoverthesumpsbuttherecurrentlyexistswoodplanksandtherearenonotessuggestingtheirreplacement.
Isittheintentoftheprojecttore‐usetheseplanksovertheexistingsumps?
Answer:ThescreensnotedonsheetsM104andM204aretheverticaltrash/filterscreenslocatedwithinthesump.New
screensaretobefabricatedtomatchtheexistingones.Thecoverpanelsarepartofthesystemcoveringtheflume(trough)
andisnotedonArchitecturalsheetA202.SeealsoanswertoQuestion11foradditionaldetail.
5)Question:Thereplacementoftheexistingchilledwatervalveswillrequireasystemshutdowntoaccomplishthiswork.
Whatistheextentofthetimethatwillbeavailableforthesystemtobedowntomakethesetransitions?
Answer:Systemshutdownsarenotanoption.Plantmustremainoperational24/7,withredundancy.Allbranchesforeachof
thechillerandpumpsneednewisolationvalves.Duringtemporarychilleroperation,theCWRheaderpipingforthechiller
anddischargeheaderforthepumpswillbedry,sotheisolationvalvescaneasilybereplacedduringthattime.Thechilled
watersupplyheaderoffthechillerandthechillerwaterheaderonthesuctionsideoftheCWpumpswillalwaysremainactive.
Thislinecannotbedisabled.Duetonotbeingabletoisolateflowandthevalves’closeproximitytotheirrespectiveheaders
(noroomforhottap/stopple),theseeight(8)valveswillneedtobeabandonedinplaceandnewisolationvalvesinstalled
downstreamoneachbranch,withabout2’ofspacebetweenoldandnewvalves.Thiswillincludethefour(4)valves(1per
chiller)ontheCWSlinesforeachchillerandthefour(4)valves(1perCWpump)foreachsuctionendofthepumps.
6)Question:DrawingM203showstheinstallationofa6”bypassinstalledinESUSSCOfficeB113A.Idonotbelievewewent
intothatroomduringthesitevisit.IsthereanopenceilinginthisareaorisitsimilartoESUSSCBreakRoomB113witha
droppedceiling?

Answer: ESU SSC Office B113A has a dropped ceiling similar to ESU SSC Break Room B113. Room B113A is to have a dropped ceiling.

7)Question:DrawingA201Notes6&8calloutfortheroomtobepainted.Note7indicatesthefloorsshouldbepaintedin
RoomsB115,B116,andB117.DoNotes6&8onlyapplytotheChillerRoomB115?
Answer:Notes6and8onlyapplytotheChillerRoomB115.Floorsarerepaintedinchillerroom,boilerroom,and
vestibule/ramp.Note7doesnotindicatefloorpaintinginBoilerRoomB116andvestibule/rampB118.RefertoRoomFinish
Schedule,DrawingA801forfloorfinishesinchillerroom,boilerroomandvestibule/ramp.
8)Question:WhereistheHeatExchangerlocatedandscheduledasdescribedinSpecificationSection011000Part1
(1.4)(A)(1)(d)(iv)?Thedescriptionistoprovideaheatexchangerinthepumphouse,butthereisonlyoneheatexchanger
scheduledanditisinthechillerroom.I’mnotsurewhatthisisreferencingbecauseIdon’tseeoneinthepumphouse.
Answer:HeatExchangerisinthechillerroom,notinpumphouse.RemoveSection011000Part1(1.4)(A)(1)(d)(iv)verbiage
“newflatplatheatexchanger(newfree‐coolingmethod)”fromspecifications.
9)Question:SpecificationSection011000Part1(1.5)(A)(2)indicatesweshouldcontactJohnsonControlsforworkonthe
legacyDDCControlSystemhoweverwhenIcontactedtheFortCollinsofficeforJohnsonControls,whooriginallyhadaservice
agreementonthechillers,theyindicatedtheyhadnotperformedworkatthefacilitysince2014.Whoiscurrentlyresponsible
fortheDDCcontrolsystemforthefacility?
Answer:SchneiderElectricistheDDCcontrolprovider.RefertoSection230900–InstrumentationandControlsforHVAC
Part1,1.1(D)(10)forcontactinformation.
10)Question:WhatismeantbythereferenceinSpecSection011000Part1(1.4)(A)(1)(c)(vii)“Provide,install,andmaintain
temporarycoolingtowerunitsandotherassociatedequipmentasneeded,incoordinationwithFAAfacilitypersonnel”?The
temporarychillersprovidedareair‐cooled.Istherearequirementtohavetemporarytowersfortheexistingequipment?

Answer: No temporary cooling towers required, just chillers. Error in specification wording.

11)WhatismeantbythereferenceinSpecSection011000Part1(a)(1)(c)(iii)“Redoingthetroughguardoutsideandinside
thepumphouse”andPart1(1.4)(A)(a)(d)(ii)“Newtroughguardthatwillsealbetterthanexisting”regardingredoingthe
troughguards?
Answer:Thereisaconcretetroughunderthecoolingtowersthatreturnswaterfromthetowerstothesumpforre‐use.This
troughandthesumphavecoversonthemtokeepdebrisoutandtokeeppeoplefromfallingin.Theyarealsousedtocontrol
freeevaporation.Thisiswhatwerefertoasthe“guard”.Theyarecurrentlymadeofwoodandaresubjecttorot.Thecovers
aretobereplacedwithamaterialthatismorerobustthanwood.Sofarasweknow,nocommercialproductspecificallyfor
thispurposeexists.Fiberglassorpolypropylene“planks”orsheetstockmightbeabletobecustomcuttofittheopenings.Or,
thecontractorisfreetoofferpotentialsolutiontothisproblembasedontheir(ortheirsub’s)pastexperience.
12)Question:WhatismeantbytheSpecSection011000Part1(1.4)(A)(1)(e)(xiv)“convertas‐builtshopdrawingstoFAA
standardbaselinedrawings”?
Answer:RefertoSpec.Section013100‐1.8.UsingFAAprovideddigitaldatafiles/drawings;theContractorwill
incorporate/converttheirapprovedas‐built/redlinedrawinginformationtofinaldigitalas‐builtCADdrawingsandsubmitto
theFAA.

13) Question: Please provide contact information for the fire alarm vendor for this facility.

Answer: Contractor may use any qualified, certified fire detection and suppression subcontractor for this purpose.

14) Question: Please provide contact information for the access control subcontractor for this facility.

Answer: Refer to Section 23 09 00 – Instrumentation and Controls for HVAC Part 1, 1.1(D)(10) for contact information.

15)Question:PleaseprovidecontactinformationforSchneiderElectrictogetontheirdistributionlistfortheDDCpricing.
Thecontactinformationinthespecbookdoesnotappeartobecurrent.

Answer: Refer to Section 23 09 00 – Instrumentation and Controls for HVAC Part 1, 1.1(D)(10) for contact information.

16)Question:Isthereanenvironmentalreportavailablethatwouldshowapproximatequantitiestohelpabatementvendors
withtheirscopeofwork?

Answer: The whole EOF area will need to be abated, approximately 1,400 SF. See Note 5 on drawing A111.

17) Question: Can abatement work be done during normal hours?

Answer:Yes,theextentofwhichwoulddependuponmethods,procedures,activitydurations,etc.,tobeidentifiedbythe
contractorintherequiredasbestosabatementplanthatissubjecttoapproval.
18)Question:Undergroundpipingreplacementfromthetowersiscalledoutasadeductivealternateinthespecifications.I
donotseeitlistedonthedrawingsorshownonthedrawings.Pleaseprovideplansforthisscope.

Answer: See attachment “Question 18 and 19 ‐ ZDV‐1401893‐M901”.

19) Question: Please identify the location and limits of the pipe testing area.

Answer: See attachment “Question 18 and 19 ‐ ZDV‐1401893‐M901”.

20) Question: Will the pipe testing agency be hired by the FAA direct?

Answer: The Contractor will hire the testing agency.

21) Question: Please confirm whether any arc flash studies are required for this project.

Answer: Yes all new panelboards will require Arc‐Flash labeling.

22) Question: Will the FAA remove all furniture, equipment, etc, from the EOF area?

Answer:No,contractorisrequiredtomoveallfurniture,equipment,etc.,fromtheEOFarea.SeeanswertoQuestion29for
additionaldetails.

23) Question: Does the temporary cooling piping, conduits, etc., need to be seismically restrained?

Answer: Yes.

24) Question: Does all plastic covering electronic equipment need to be static resistant?

Answer: Yes, all plastic covering electronic equipment needs to be static resistant and breathable.

25) Question: Is there any specification or specific acoustical wall panel called out in the spec? We did not see any.

Answer:Spec.Section098433‐2.1.Aidentifiesbasisfordesign.RefertoDrawingA801RoomFinishScheduleandInterior
ColorSchemeScheduleforspecificproductlisted.
26)Question:Towhatextentdoallpenetrationsneedfireproofinginthechillerroom?Doallexistingpenetrationsneedto
bedoneorredone?AccordingtothenoteonsheetA001weonlyneedtodonewpenetrations,correct?
Answer:Onlynewpenetrationsand/orexistingpenetrationsaffectedbyandrenderednon‐compliantbyactivitiesperformed
underthescopeofworkarerequired,perDrawingA001,tobefirestoppedorreworkedforcompliance.ChillerRoomisno

exception.

27)Question:A022–Thisnoteindicatesthereismoldbehindtheacousticalpanels.Howmuchmoldispresentsowecan
quantifyhowmuchworkneedstobedone?Also,willtheseacousticalpanelsneedtobereplacediftheyarecoatedin
mold?ThenoteonsheetA112onlyindicatestoreplacetheredandorangeacousticalpanels.Arethereanyvisualreferences
reflectinghowfarthemoldextendsorwhichcolorofpanelsareatthislocation?Pleaseprovideorclarify.
Answer:Estimatedsquarefootageofmoldisasfollows:HOSTMechanicalRoomB119approximately200SFbehindexisting
lightbrowncoloredpanels.Remove,cleanofmoldandreinstalllightbrownpanels.HOSTComputerRoomB134
approximately20SFmoldbehindorangepanelstobedemolished.RefertoDrawingsA701andA801astheyapplyto
elevationsandroomfinishes.If,duringtheprojectwork,additionalmoldisdiscoveredbeyondtheseestimatedSFs,achange
orderwillbeappropriate.
28)Question:A022–NoteD&Ecallsforthecontractorto“Testandabatemold”.IcannotpricethisifIdonotknowhowfar
itextends.Pleaseadvise.

Answer: See Question 27 answer.

29)Question:1–Note5&7indicatestoremoveallcoatingonthefloors(vestibulechillerroomandboilerroom)to
concrete.Thegeneralcontractorisresponsibletomoveallfurnitureandequipmentwithintheroomandthenreplaceafter
thenewfloorcoatingshavebeeninstalled.Howmuchfurnitureandequipmentneedstoberemovedandreinstalled.Please
providephotos.
Answer:SeeAttachment“Question29–Listoffurniture”foranestimateofitemsrequiredtobemovedbythecontractor.
Theitemswillbemovedtoadjacentroomsandwillnotrequiregoingupordownstairsorsignificantdistances.
30)Question:AsperdrawingA131‐Note2(as‐builtdrawingsoftheNEOFareaavailableuponrequest).Pleaseprovidethe
as‐builtdrawings.
Answer:Seeas‐builtdrawingAttachments“Question30–RMD‐502‐40449‐A05,‐A06,and‐A07).FAAdoesnotconsider
themtobeessentialforbiddingpurposes.Priceyourbid(offer)basedondrawingsprovidedinoriginalsolicitation.

31) Question: A132 – Does a HEPA vacuum need to be used to vacuum the acoustical ceiling before it is demolished?

Answer: Yes.

32)Question:A201–Note1indicatestofirestopexistingandnewpenetrationsinfireratedbarriers.Aswecannot
determinehowmanyorhowlargeanyexistingpenetrationsare,werequestanallowancebedeterminedforthisworkand
indicatedintheresponsetothequestions.Howmuchshouldthisallowancebe?
Answer:Noallowancewillbeallowed.Onlynewpenetrationsand/orexistingpenetrationsaffectedbyandrenderednon‐
compliantbyactivitiesperformedunderthescopeofworkarerequiredtobefirestoppedorreworkedforcompliance.Chiller
Roomandvestibulearenoexception.

33) Question: A201 – Note 6 Is this note for just the chiller room? Should the boiler room be done also?

Answer:Note6appliesonlytothechillerroom.ChillerroomB115istheonlyroomtohavewallspainted.BoilerroomB116
andvestibulewillnothavewallpatching.

34) Question: A211 – Note 3 Please confirm what the construction of the existing wall is? Metal stud & drywall, masonry?

Answer: Existing wall is metal stud and 5/8” fire rated drywall each side.

35) Question: A211 – Note 10 Please confirm what this cover plate is and what it will be. Steel?

Answer: Existing cover plate is steel. Coordinate replacement with floor finish requirements in accordance with Note 10.

36)Question:A201–Note4Pleaseprovideaphotooftheleak.Whatisthecauseoftheleakandhowlargeisitsowecan
determinewhatneedstobedonetocorrectit?
Answer:PhotosbelowshowexteriorandinteriorviewofleakinBoilerRoomsouthwall.Waterwicksunderthecurbforits
fulllength.Sincethepre‐bidmeetingonAugust28therehasnotbeennorwilltherebeasignificantchangeintheconditions.

Exterior view looking down

Exterior view looking West

Exterior view looking East

Interior view

37)Question:A212Note4indicatestoinspectexistingfirestoppingandrepairanythatfail.Wehavenowaytopricethis
itemaswedonotknowwhatwillorwillnotfail.Pleaseprovideanallowanceforthisitem.
Answer:Noallowance.TheFAAisunawareofanyfailingfirestoppings.Priceyourbid(offer)onnewpenetrationsonly.Any
failedfirestopping(s)discoveredduringtheprojectworkwillbenegotiatedinachangeorder.

38) Question: A212 Note 7 is this stair and handrail system part of the access floor system or a structural steel stair system?

Answer: The stair and handrail system is to be part of the raised floor system.

39)Question:A212Note12pleaseverifywhatworkneedstobedone.Itisaskingforaninspectionofthecolumnsandtobe
refinishedifnecessary.Wecannotquantifythisuntiltheinspectionhasbeendone.
Answer:Withtheexceptionofone(1)sideofonecolumnonwhichcabletrayispresent,resurfacingeachsideofallsix(6)
columnsisrequired.

40) Question: A212 Note 14 What type of fire extinguisher?

Answer: Dry chemical Type A‐B‐C.

41)Question:A212Note17Thisnoteindicatestoblocktheceilinglouversthatarestillworking.Isthiscorrect?Howmany
arethere?Howlargearethey?AretheseshownontheMechanicaldrawings?

Answer: There is only one louver. It is verified that it was blocked off in January 2015. Remove from scope of work.

42)Question:Plansindicatetoremoveandreplaceacousticalwallpanelsthatareredandorange.Astheplansarenotin
colorcanyouindicatewhichpanelsareredandorangesowecanquantifyhowmuchgetsremovedandneedstobereplaced?
Answer:ElevationsonsheetA701(note1)showtheextentoftheredandorangepanels.RefertoDrawingA801“Doorand
FinishSchedules”.
43)Question:OnA301,wherethenewadditiontothebuildingisbeingadded?Thereappearstobeutilitiesrunningthrough
thatspace.Arewerequiredtorelocatetheseutilities?Orarewetobuildontopofthem?Orwillthisbehandledbythe
government?Willthegroundingcounterposebeintheway?
Answer:Utilities,includingexistingcounterpoisedorunundergroundthroughthenewbuildingfootprint.Yes,theContractor
isresponsibletoperformutilitylocatesandtocoordinatewiththeFAA.TheFAAwillprovideas‐builtinformationtothe
Contractortothebestofourknowledgeandavailableinformationpriortoconstruction.However,theContractorremains
responsibleforthelocationandprotectionofundergroundutilities.

44) Question: A301 Who is the pre engineer building Manufacturer of the existing building?

Answer: Unknown. No manufacturer’s label is visible on or in the building.

45) Question: A701‐ requires to clean all acoustic panels. What will be the preferred method?

Answer: Dry extraction. Exact method is to be determined by the Contractor, subject to FAA approval.

46)Question:M211andM212‐willnewtiles,stringers,andpedestalsneedtobeprovidedfortheflooralteringorwillthe
FAAhaveatticstockthatcanbeused?Isthereanexistingratinginthefloor?
Answer:TheContractorisnotrequiredtoprovidenewtiles;FAAhasenoughinstock.TheContractorwillberequiredtofill
inaroundaffectedareawithexistingtilessuppliedbyFAA.TheContractorwillneedtoprovidetwo(2)pedestals,two(2)
pedestalheads,andone(1)stinger(manufacturerTateandproductnameConcor).

47) Question: E214 ‐ is there a requirement to paint conduits and ducts in this space?

Answer: If the reference is to the HOST Mechanical Room B119, there is no requirement to paint the duct and conduits in the space.

48) Question: Is there a requirement to be certified for fire caulking?

Answer: Yes.

49)Question:WillmechanicalprovidenewVFDsforchillers,pumps,&coolingtowers;wetypicallyexcludethem,as
mechanicalcontractorstypicallygetpackagedealswiththeirvendorstoensuretheyarecompatiblewithmotorloads;Ido
haveanRFIquestionontheratingoftheVFDenclosures,onenotesaysNEMA3RandanothersaysNEMA4Xstainlesssteel.
Pleaseclarify.Therecouldbeabigcostdifferenceontheseratings.
Answer:ContractorwillsupplytheVFDsforthecoolingtowerfansandpumpstomeetspecificationrequirements.Chiller
manufacturerwillsupplytheVFDstomeetthenewchillersystemrequirements.TheratingoftheVFDenclosuresshallbe
NEMA12stainlesssteel.
50)Question:Data/Comm,‐WedonotseeanyscopeordevicesshownonthedrawingsfornewData/Comm.Arethereany
newData/Commdevicestobeinstalled,andifso,howmanyandwherearetheylocated?
Answer:ThescopeoftheDataandCommunicationswillbeprovidedbytheSchneiderElectricProgramofficeaspartoftheir
design.RefertoSpecSection230900–INSTRUMENTATIONANDCONTROLSFORHVAC,Part1(1.1)(D)(10)forcurrent

information.

51)Question:AccessControl,don’treallyseeanyscopeshownontheelectricaldrawings,butrecallthemshowingusseveral
doorsthataretobereplacedandhavecardreadersinstalled.Doweneedtocoverboxes&racewaysonly?Willyoube
coveringthecablingviathepreferredFAAvendor?Doyouknowhowmanydoorsandtheextentofconduitthatwillneedto
beinstalled?

Answer: See Door Schedule in the drawing set A801 for location of doors. Honeywell is the current provider of these services.

52)Question:LightningProtection:Isthecontractorresponsibleforthis?ShouldwereachouttoNationalLightning
Protectiontocoverthis?
Answer:Contractorisresponsibleforprovidinglightningprotectionwork.Contractormustfollowthemostcurrentlightning
protectionstandardNFPA780–StandardsfortheInstallationofLightningProtectionSystemsandFAA‐STD‐019f–Lightning
andSurgeProtection,Grounding,Bonding,andShieldingRequirementsforFacilitiesandElectronicEquipment.Seeattachment
“Question52,72and74‐FAA‐STD‐019f”.
53)Question:Pleaseconfirmthattheengineeringteamhasverifiednewspecifiedchillerswillbeabletoberouteddowninto
theexistinglocationandthebestroute.
Answer:BestrouteforchillerpassagehasbeenconfirmedastheexteriorareawayonthesouthsideoftheboilerroomB116.
Thisisthesamelocationthathasbeenusedateveryothersiteandshouldprovideampleclearanceforequipmentpassage.
Exteriorstairassemblymustberemovedforclearance.

54) Question: Will the temporary fencing the contractor brings in be required to be grounded or have lighting protection?

Answer:Yes.Thecontractorwillprovidethetemporaryfencingaroundthetemporaryequipmentspaceforsecurityand
hazardrequirement.Thecontractorwillprovidegrounding,bondingandlightningprotectionforthetemporaryelectrical
equipmentandothermechanicalpipesinthetemporaryequipmentspace.
55)Question:M‐203showsanewChilledwaterbypass(notes5&6).Thecurrentlocationisabovedesksinadropceiling.
Thereissolittleroomthattheceilingtilesarecutouttoallowfortherollerhangerstostillspin.Pleaseadvisehowweareto
installa6”bypassline,completewithvalvesandwhereahottapmachinewillfit(zeroclearancesabovetoo).

Answer: This location can be adjusted for constructability, but may cause the need to move DP and flow sensors.

56)Question:PageZ131,Note1requiresa3rdtemporaryair‐cooledchillerwiththesamepipingconfigurationandspecsto
beonstandbylocallywiththeabilitytobehookedupandstartedontheLongmontcampuswithin24hours’notice.Theonly
possiblewayforthis3rdtemporarychillertobeguaranteedtobethatclosetotheprojectsite,andguaranteedtobethesame
specs,size,andpipingrequirementsisforthecontractortorentthatadditionalchillerandalreadyhaveitstoredonsitefor
thedurationofthetemporarychillerplants’existence.Twoquestions:

1. Is their space at the Longmont facility to accommodate the 3rd chiller?

Answer:Yes.
____________________________________________________________________________________________________________________

2. Is it the FAA’s intent to pay for and include the rental cost of the additional 3rd chiller in the GC’s pricing proposal?

Answer: Yes.

57)Question:Whatapproximatepercentageoftheworkonthecontractwillberequiredtobeperformedduringthenight
hours,approximately10:00PM‐6:00AM?
Answer:ItistheContractor’sresponsibilitytodetermine(andsubsequentlyidentifyontheirprojectschedule)thehours
requiredoutsideofthespecifiednormalworkinghours,usingspecifiedrequirementsandconstraintssuchasexplicit
languagepertainingtocutovers.
58)Question:SpecSection014000‐3statesthecontractor’sProjectQualityControlmanagershallnothaveotherproject
responsibilities.IstheFAA’sintenttohaveafulltime,on‐siteQCMforthedurationoftheprojectthatcannotbeeitherthe
Superintendent,SafetyManager,orProjectManager?

Answer: No, that is not the FAA’s intent. QCM and SSHO may be the same person. See also the answer to Question 59 below.

59)Question:SpecSection013529‐2statestheSSHOmustbeon‐siteduringworkinghourstoimplement,administer,and
enforceContractor’ssafetyandhealthprogramandAPP.

o SSHO may not be the Contractor’s superintendent.

o SSHO may be the Contractor’s quality control manager and must report to a senior Project or corporate official.

Thisverbiageconflictswithspecsection014000‐3thatstatesthattheQCMshallnothaveotherprojectresponsibilities.
Pleaseclarifythenumberoffulltimeemployeesisrequiringonsite.Myunderstandingisthatthecontract’sintentwould
requireafulltimesuperintendentandafulltimeQC/SafetyManageronsiteatalltimes.Or,areyourequiring3separatefull
timepersonnel(super,QC,Safety)onsiteatalltimes?
Answer:SpecSection013529,Part1(1.7)(B)iscorrect.TheSSHOmustbeonsiteduringworkinghours.Thesameperson
mayserveinboththeQCMandSSHOrolessimultaneously,butneithercanbethecontractor’sSuperintendentorProject
Managersimultaneously.
60)Question:Pleasedetailthesecurityrequirementsandtimelinesforbringinganewemployee/workeronsiteat
Longmont,includingthetimelinesforapprovalofthedifferenttypesofbadgingandhowlongaworkerwillbeallowedto
workonsiteunderatemporarybadge.
Answer:ContractorsubmitsnamesofpersonnelthatwillreceivePIVbadgestotheContractingOfficer’sRepresentative
(COR)andalsoenterstheinformationintotheFAA“VAP”securitysystem.Onceinformationisenteredintothesystem,itcan
takeuptofour(4)weeksforbackgroundandissuanceofbadges.Mostworkerswillbeprovidedtemporaryvisitorbadgeson
adailybasis.Personnelthatarebadgedwillhaveescortprivilegesandwillberequiredtoescortworkerswithadaily
temporarybadgesatalltimes.ItistheContractor’sresponsibilitytoensurethatenoughpersonnelarePIVbadgedsothat
escortingwillnotbeanissueinthecaseofworkbeingperformedindifferentareasofthefacilitysimultaneously.
61)Question:Pumpschedulecallsfor2‐stagepump(turbines),butthereisn’taspecsectionforthistypeofpump.Willone
beprovided?(Section232123–2.4doesnotapply).

Answer: See highlighted areas of revised specs section 23 21 23 attachment “Question 61 – 23 21 23 Hydronic Pumps Amendment”.

62)Question:CoolingTowerSchedulebasisofdesignisTowerTech(wearethelocalTowerTechrep),butthefollowing
itemsinthespecificationsdonotapplytoTowerTech(pleaseclarify):
a)Question:Page721ofthespecslistthetoweras“induceddraft”.Thereisnoprovisionfor“forceddraft”(Tower
Techisforceddraft).

Answer: The FAA requires a forced draft cooling tower.

b) Page 723 reiterates “induced draft” (Tower Tech is forced draft).

Answer:Sameasabovequestion(a).
________________________________________________________________________________________________________________________

c) Page 724 Section H lists louvers as part of the supply of the cooling tower (Tower Tech does not have louvers).

Answer:Louversareoptional,dependingonthecoolingtowertype.
_________________________________________________________________________________________________________________________
d)Page724SectionIsaysthatthefanneedstobebalancedafterassemblyandthatfanscreenshavetobe304SS
wiremesh(TowerTechutilizesindividualdirectdrivemotors,whichdonotrequirebalancing).

Answer: Fans should be balanced by the manufacturer. Upon building, they don’t need to be balanced onsite.

e) Page 725 Section J says that motors are TEFC (Tower Tech utilizes TEAO motors).

Answer:BothTEFCandTEAOarefine.
________________________________________________________________________________________________________________________

f) Page 725 Section K says to supply vibration switch (Tower Tech does not require).

Answer: FAA requires vibration switch. The switch is to be supplied by the controls’ contractor to ensure proper fan operation.

g) Page 725 Section M says to provide access doors for entering cooling tower (Tower Tech does not require).

Answer:Whetheraccessdoorsareneededwilldependuponthemanufacturer’sdesignofthecoolingtower.Ifthe
manufacturerisTowerTech,whosecoolingtowersdonotcontainagearbox,accessdoorswillnotberequired.Ifan
approvedequalmanufacturer’scoolingtowerisapproved,therequirementofaccessdoorswillbedependentupon
thedesignofthecoolingtower.
63)Question:TowerTechsuggestsrotatingthetowers90degreesinordertoreducepipingrequirementsandreducethe
riskofrecirculation.Seeattacheddrawingnotes.

Answer: To maintain seismic design, the proposed drawing will stand. Recirculation is not a primary concern.

64) Question: 230548 – 2.1 and 2.2 – can Vibro‐Acoustics be added to the list of acceptable manufacturers?

Answer:Listofmanufacturesisnotlimitedtothosevendorsonthelist.Thelistprovidedareknownmanufacturerstothe
FAA.Anymanufacturerthatmeetsthespecsmaybeapproved,evenifnotlisted.
65)Question:PleaseclarifyNEMAEnclosurerequirementsforthepumphouseelectricalequipment.GeneralNoteBon
DrawingZDV‐1401893‐E204saysVFDS&disconnectsinsideandoutsidethepumphousearetobeNEMA4Xstainlesssteel
andotherequipmentwithinthepumphouseshouldbeNEMA3R.Doesthatnoteapplytothenewelectricalroomadditionand
isthatroomconsideredpartofthepumphouse?Doallthenewelectricalpanels,transformer,potentialharmonicfilters,etc.,
withinthenewadditionneedtobeNEMA3RorNEMA12?ThenewwirewayshownonDrawingZDV‐1401893‐E302istobe
NEMA1perKeyNote4,andthetwonewelectricalpanelsaretobeNEMA12;noratingisshownforthetransformer.

Answer: All the VFDs, electrical panels and a step down transformer NEMA ratings are 12.

66)Question:PleaseclarifywhichtradeistoprovideallnewVariableFrequencyDrives.Typically,themechanicalcontactor
providesthemasapackagecomponentwithnewpumps,coolingtowers,chillers,etc.toensuretheyarecompatiblewiththe
motorloadstheyarecontrollingandtheelectricalcontractorinstallsthem.Isthatcorrect?
Answer:ContractorwillsupplytheVFDsforthecoolingtowerfansandpumpstomeetspecificationrequirement.Chiller
manufacturerwillsupplytheVFDstomeetthenewchillersystemrequirement.
67)Question:PleaseclarifyKeyNote12onDrawingsE204&E714regardingthepotentialharmonicfiltersforthe(3)
coolingtowersandthe(2)chillers.Whereitsayscontractorshouldtestcircuitandonlyinstalltheharmonicfiltersifthe
distortionexceedsFAAspecifications:shouldn’ttheseharmonicfilterspossiblybeconsideredasanAddAlternateorDeduct
Alternatetotheprojectpricingastheymaynotbenecessaryuntiltestinghasdeterminedtheywillberequired?
Answer:Forallcoolingtowerfansandpumps,use6‐pulseVFDdrives.Noneedtoinstalltheharmonicfilters.
Forthechiller,contractorshallprovidechillersincludingVFDsandfiltersthatmeettherequirementforreducingTHD.
68)Question:PleaseclarifyscopeofworkforPanelsHC3&HC4;thedrawingsindicatethatallloadsandfeedsaretobe
removedfromthesource.Howmanycircuitsarecurrentlyinstalledwithinthesetwopanels?Whatarethesecircuits
currentlyfeedingandwhatotherdemoisassociatedtothesecircuits?Arewetodemooutlets,equipment,etc.aswell?Also,
wherearePanelsCPC‐A,B,Clocatedthatfeedthesepanels?Whataretheconduit/wiresizes&lengthsofthefeedsbetween
thepanels?
Answer:PanelsHC2andHC3arethereconditionedpanels.HC1,HC2,HC3,andHC4have42circuitseach,butthereareno
activecircuitsonanyofthepanels.Demoallconduits,outlets,andbranchcircuitsforpanelsHC1,HC2,HC3,andHC4.
RemoveallfeedersbacktothesourceforpanelsHC1andHC4.PanelsCPC‐A,B,CarelocatedinB13intheAutomationWing
Basement,criticalpowervault.FeedersforpanelsHC1andHC4willberemovedtothesource.FeedersforHC2andHC3will
beretainedforre‐use.Nofeederconduitremovalisrequired.
69)Question:Pleaseclarifyscope&providepanelschedulesforPanelsHC1&HC2whicharetobereconditioned.Arethere
existingloadswithinthesepanelboardsthatmayneedtobetemporarilyfedfromanothersourcewhilethepanelsarebeing
reconditioned?Howmanyloadsarecurrentlyinstalledwithinthesepanels?Arethereanynewloadstobeinstalledwithin
thesepanels?Howmanynewcircuitbreakerswillberequiredandwhatarethesizes/ratings?Isallexistingwiretoremain
andbereused/terminatedtothereconditionedpanel?Whatifexistingwiringistooshort?Willthesepanelspossiblyhaveto
bereconditionedduringaspecialoutagetimeframe,possiblyatnight,requiringovertime?Also,pleaseclarifythescopetothe
GovernmentProvidedParagonTransferSwitchesassociatedwiththesetwopanels.Wherearetheytobeinstalled?Whatis
thesizeoftheseswitches?Aretheytobewallmounted,floormounted,recessednexttothesepanels?Whataretheconduit&
wiresizerequirementsfortheseswitchesastheonelinesdonotindicate.Aretheexistingtoremain?ItappearsthatCPC‐A&
Bmaybenewfeeds.
Answer:PanelsHC2andHC3arethepanelsthatwillbereconditioned.Therearenoexistingloadsforthesepanels,nonew
loadswillneedtobeinstalled,andthesepanelsdonotneednewcircuitbreakers.Onlythefeedersneedtoremain.Thereisno
specialoutagetimeframeforreconditioningpanelsHC2andHC3.TheGovernmentProvidedParagonTransferSwitchesare
wallmountedandrecessedabovethepanels.Theconduitandwiresizewillbethesamesizeasthefeeders.
70)Question:Pleaseprovidemoreinformation&specificationrequirementsforthenewSignalReferenceGrid(SRG)thatis
tobeinstalledundertheHostComputerRoomraisedfloor.Theredoesnotappeartobeanyspecificationsordetailsforthis
scope.Pleaseclarifymaterials,sizing,manufacturer,installationdetails,etc.,fortheSRG.
Answer:FAA‐STD‐019f,4.7.3.2.aSignalReferenceGroundGrid:SRGGshallconsistofagridof2‐inwidecopperstrips,26
gaugeorthicker,placedona2x2‐ftsquaregridandweldedateachgridintersection.
71)Question:Pleaseclarifyif4/0perimetergroundingloopisexistingornewtobeinstalledunderthisproject.Note1on
DrawingZDV‐1401893‐E215saysit’sexisting,butSpecificationSummaryPg.011000‐5_3_e_iisaystoinstall.Also,please
clarifyiftherearetobe(3)new4/0crossconnectsinstalledacrosstheroomrunningfromNorthtoSouthbondingtothe
perimetergroundringaswell,oriftheseareexisting?
Answer:4/0perimetergroundingloopisexisting.No,(3)new4/0crossconnectingtheperimetergroundontheNorthand
Southwallsisnotexistingandisnotrequiredtobeinstalled.ThedrawingandSpecificationsummarywillbeupdatedto
representthesechanges.
72)Question:PleaseclarifyifallPanelswithintheHostComputerRoomaretobebondedtothenew4/0perimeterground
ring,includingPanelsHC3&HC4.TherearenoboldpointsidentifyingtheexistingpanelslocatedalongtheEastWall,except
Note5onDrawingZDV‐1401893‐E215;however,whereNote5isshown,therearenoelectricalpanels.
Answer:PanelsHC2andHC3arethereconditionedpanels.PanelsB‐B134‐BS1,B‐B134‐BS2,HC2,andHC3arecurrentlynot
bondedtotheexisting4/0perimeterground,sothecontractorwillberequiredtobondfour(4)enclosurestoperimeter
groundingconductorbyexothermicweldinginaccordancewithFAA‐STD‐019f(seeAttachment“Question52,72,and74–

FAA‐STD‐019f”).

73)Question:PleaseclarifyifalltheMultigroundPlatesreferencedbyNote9onDrawingZDV‐1401893‐E215areexistingor
iftherearenewonesinstalledperthisproject.HowaretheexistingMultigroundPlatescurrentlybondedtogether?Areweto
demo/removeanyexistinggroundingsystemoncethenewsystemisinstalled?
Answer:AllthemultigroundplatesreferencedbyNote9areexistingmultigroundplates.Noneedtoinstallnewmultiground
plates.TheExistingmultigroundplatesareverifiedproperlybondedtoperimetergroundingconductorbyexothermic
weldinginaccordancewithFAA‐STD‐019f.Nofurtheractionneeded.
74)Question:Pleaseclarifyand/orprovidedetailsonhowtheexistingcabletrayistobegroundedandhowoften;istobe
connectedtothegroundloop,SRG,ormultigroundplate?

Answer: Refer to attachment “Question 52, 72, and 74 ‐ FAA‐STD‐019f”.

75)Question:PleaseclarifyifirreversiblecompressiongroundingconnectionscanbeutilizedfortheHostComputerRoom
newgroundingsystem,inlieuofexothermicwelding,asthiswillbeinsideandmaycauseissueswiththeFireAlarmSystem
andsmokedetectors.

Answer: The new grounding system is requires exothermic welding.

76)Question:PleaseclarifyiftheTypeRL&RL1lightfixtures,&ExitSignsintheHostComputerRoomshownonDrawing
ZDV‐1401893‐E212arenewlightfixtures,oriftheyareexistingtoremainwithnewlensesinstalledasidentifiedin
SpecificationSummaryPg.011000‐6_3_e_iv.

Answer: RL and RL1 are to be replaced with new light fixtures. Exit signs are to be replaced with new wall mounted LED exit signs.

77)Question:PleaseclarifyelectricaldemoscopesforthetemporaryofficesperNote6onDrawingZDV‐1401893‐E114.
Howmanyelectrical&data/commoutletsarelocatedwiththeseofficesthataretodemo?Also,whatistobedonewiththe
lightfixtures&lightswitches?Aretheyexistingtoremain?Willlightfixtureshavetoberelocatedandifso,howmany
fixturesarethere,andhowaretheytobecontrolled?
Answer:Allelectricalanddata/comm.outletsaretobedemoedintheofficelocations.Nolightfixturesorlightswitchesneed
tobedemo’d;theexistingaretoremain.Lightfixturesandswitchesdonotneedrelocationanditisnotnecessarytocontrol
themastheyarealreadycontrolled.
78)Question:PleaseclarifyscopesofworkassociatedwithMCCA,1A,B,1B,C,1C,&DSpecificationSummaryPg.011000‐
5_3_D_ithruiv.TheprojectsummarymakesreferencetoremovingandreplacingtheseMCC’sandtoprovideharmonic
testingonthefeedersidesoftheseMCC’s;however,atthejobwalkiswasmentionedthatreplacementoftheseMCC’sis
coveredunderaseparateprojectandnottobepartofthiscontract.Also,pleaseclarifyifreplacingcircuitbreakerswithin
theseMCC’sarerequired.SheetNote4onthevariousMCCone‐linediagramssaystoverifyfuse/breakersizetoensure
propercoordination.Arewetoreplacethecircuitbreakersiftheyarenotofthecorrectsize&ratingforthenewloads?
Answer:TheMCCs(A,B,C,1A,1B,1C&D)projectthatincludedtheharmonictestingtasksontheMCCs’feedersidesare
coveredunderaseparateproject.TheMCCsprojectisnottobepartoftheMajorMechanicalproject.Note4fromtheoneline
diagramisforfieldchecking.Whetherthefuse/circuitbreakerwillneedtobereplacedisdependentupontheproduct
submittalthatthecontractorsubmitsforapproval.Iftheyareofadifferentsizethanwhatisonthedrawings,theywillneed
tobereplaced.
79)Question:PleaseclarifyiflightningprotectionisrequiredforAHU‐400asidentifiedinSpecificationSummaryPg.
011000‐6_3_g_i.ItappearsthatthisAHUislocatedinsidethebuildinginMech.Rm.B129andthedrawingsdonotshowor
noteanylightningprotectionassociatedwiththisunit.

Answer: Lightning protection will not be required for AHU‐400.

80)Question:Pleaseclarifyexterioroutlets,unitheaters,&lightingrequirements/scopesofworkassociatedwiththe
temporarychillers.Arewetoprovidelightpoles,mountlightsuponthetemporarychillers,oronthetemporaryfence?
Wherewillelectricaloutletsberequiredandhowmany?
Answer:Thecontractorwillprovideexterioroutlets,unitheatersandtemporarylightingaroundthetemporaryequipment
space.Thecontractoristoprovideproperfoot‐candlelevels,adequatepoweroutlets,andheatersthatarerequiredforthe
serviceandmaintenancework.Thecontractorwillalsoprovidetemporaryfencingaroundthetemporaryequipmentspacefor
securityandhazardrequirement.
81)Question:Pleaseprovidespecificationsandclarifywaterlineheattracingrequirements/scopesofworkassociatedwith
thetemporarychillersandthenewcoolingtowers.Istheheattracetobecontrolledwithindividualthermostatsorone
commonheattracecontroller?AreanyalarmsormonitoringofheattracebyBASrequired?
Answer:Heattraceforthepipingonthepermanentcoolingtowersmaybeanycommerciallyavailable,industrialgrade,self‐
regulating,heatingcableproductdesignedtoprovidefreezeprotectiontometallicpiping.Inthistypeofproduct,theheat
outputofthecablevariesinresponsetothesurroundingconditionsalongtheentirelengthofcircuit.Whenevertheheatloss
oftheinsulatedpipeincreases(asambienttemperaturedrops),theheatoutputofthecableincreases.Conversely,whenthe
heatlossdecreases(astheambienttemperaturerisesorproductflows),thecablereactsbyreducingitsheatoutput.The
manufacturer’srecommendedmethodofcontrolistobeused.NomonitoringbytheBuildingAutomationSystem(BAS)is

required.

82)Question:Pleaseclarifywhereandhowthenewelectricalpanelsassociatedwiththetemporarychillersaretobe
installed.Willnewconcreteequipmentpadsberequired?Aretheytobeinstalledonfreestandingunitstrutracks?
Answer:Newconcreteequipmentpadsarenotrequiredforthetemporarychillers.Aportableequipmentpadissuitable.
Freestandingunitstrutrackstomounttemporarypanelsandastepdowntransformerareapossiblesolution.
83)Question:PleaseprovidemoredetailandclarificationforbranchcircuitconductorsfromtheI‐LinePaneltothe
temporarychillers.Note4onDrawingZDV‐1401893‐Z141saysthesearetobebythetemporarychillerprovider.Arethese
conductorstobeinstalledinconduit?Cantheyjustbetemporarycablesbundledtogether?Howaretheytoberoutedtothe
I‐LinePanelslayingontheground?
Answer:ConductorsfromtheI‐LinePaneltothetemporarychillersarebeinstalledinconduit(EMTfortemporaryisokay).
ThetemporaryconduitsroutedtotheI‐Linepanelaretobeelevatedofftheground,notlayingontheground.

84) Question: Will a light fixture schedule be provided?

Answer:ThelightfixtureschedulehasbeenprovidedinDrawingE601.Itprovidesadescriptionandknownacceptable
manufacturerandmodelnumber,butcontractorcanprovideequalproductsubjecttoapproval.
85)Question:WilltheVFDsbesuppliedfromtherespectiveequipmentmanufacturersorwilltheybepartoftheelectrical
contractor’sgear?
Answer:ContractorwillsupplytheVFDsforthecoolingtowerfansandpumpstomeetspecificationrequirement.Chiller
manufacturerwillsupplytheVFDstomeetnewchillersystemrequirement.
86)Questionsregardingchillerspecifications(section236416).MyassumptionisthatsomeoneworkedwithTraneonthe
chillerselectionandmostofthesequestionswillbeeasytoanswer(ifthespecswerewrittenbasedonTranespecs):
a)Question:Seismic–doyourequireOSHPDcertification?IwanttomakesurethatIdonotprovideaunitthatis
overkillinregardstoseismic.Inmyexperience,neopreneisolatorswillsufficebutIdon’twanttoassumethatincase
IammissingsomethingwithinASCE/SEI7.

Answer: Neoprene mounts are sufficient.

b)Question:Coordinatingwitnesstest.Whowouldbetheindividual(s)thatwillwitnessthetest?Canwe
coordinatewiththem?
Answer:ContractingOfficer’sRepresentative(COR),ProjectEngineer(PE),FAAsitepersonnel,etc.Yes,youwill
coordinatethroughtheCOR.

c) Question: Would a refrigerant‐cooled VFD be acceptable or is air‐cooled the only allowable option?

Answer:Thepreferredmethodisair‐cooled.Theconcernwouldbeifrefrigerantcoolingisused,andthe
temperatureisbelowDP,wecouldcondense.Ifthisisnotthecaseitwouldbeavalidmethodofcooling.

d) Question: Does this unit need to ship knockdown or would knockdown in the field be acceptable?

Answer: Either way is acceptable as long as it meets manufacturer recommendations.

87)Iamreviewingthedrawingsandjustnoticedthatthestructuraldrawingsdonotshowanewcatwalksystemwith
associatedfootingsifrequired.There’sasmallsetofstairsattheendofthecoolingtowers(sheetS104)butitdoesn’tappear
togiveaccesstoallofthecoolingtowers.Shouldtherebeanewcatwalkplatformincludedinthisproject?

Answer: No catwalk at the top of the cooling towers. Just the platform below all the cooling towers.

88) Chiller rental questions:

a) Question: What is the length of electrical run for each unit? To be provided by Trane rental service?

Answer:RefertoDrawingZ101,estimatedatapproximately100ft.Yes,tobeprovidedbyrentalservice.
_____________________________________________________________________________________________________________

b) Question: What is the length of hose runs for each unit? To be provided by Trane rental service or is hard‐piping required?

Answer:Hard‐pipingisrequired.RefertoDrawingZ101.
____________________________________________________________________________________________________________

c) Question: Would Trane provide startup/training of rental equipment?

Answer: Yes, startup/training of rental equipment is required.

89)Question:Willanymanufacturerbeacceptedotherthanthoselistedintheprojectspecificationdocument?Forexample,
isthereanyotherchillermanufacturerthatwouldbeacceptedotherthanTrane?
Answer:TheFAA’srequirementisforTRANEchillersonly.Thefacilityhasatotaloffour(4)chillersandonlytwo(2)are
beingreplaced.TheFAAisrequiringthesamemanufacturerforthenewchillersforconsistencyandstandardization.
90)Question:Withregardstothisproject,wouldanalternatecontrolssystembeaccepted?SpecificallySiemensTalon
Controlswhichisanopen“Tridium”basedsystemthatwouldbeanequaltothecurrentspecifiedsystem.
Answer:Noalternatecontrolssystemswillbeaccepted/approvedforthisproject.TheFAAisutilizingSchneiderElectric
controlsinallitsARTCCfacilitiesforconsistencyandstandardization.

92) Question: Where is FAA Order 6000.50E as per Section 011000 1.4.A.4.a.iv located? Please provide.

Answer: See attachment “Question 92 – FAA Order 6000.50E”.

93) Question: Is this project one that mechanical contractors are permitted to bid as the prime contractor?

Answer: Any contractor may submit an offer as the prime contractor.

94)Question:Atthesitevisit,itwasmentionedthatthesigninsheetswouldbemadeavailabletoattendees.Canthisbe
postedtothewebsite?

Answer: The site visit attendee list will be provided to whomever requests a copy. Email requests to cindi.tjelde@faa.gov.

95)Question:WilltheFAAprovideanyandallrequestedinformationorpaperworkasneededtoobtainsalestaxexemption
withtheStateofColorado?
Answer:No.TheFAA,asthefederalgovernment,istaxexempt.Theawardeecontractorisresponsibleforanyandalllocal,
state,and/orfederaltaxes,asstatedinSectionBoftheRFO:“Theofferedpricemustencompassallcostsrelatedto……(b)
federal,state,andlocaltaxes”.
96)Question:PertheRFO,weareallowed75pagesmaxforthetechnicalproposal.Doesthatincludecoverpage,tableof
contents,resumes,pagebreaks?

Answer: Yes, the entire technical proposal.