The file's text, extracted by GovTribe without its formatting.
697DCK‐18‐R‐00406
Denver Major Mechanical Project
Questions & Answers
| 1) | | Question: | | Drawing | S102 | Detail | A8 | indicates | the | scale | of | ½” | – | 1’0” | as | does | the | scale | on | the | drawing, | but | this | does | not |
| coincide | with | the | dimensions | on | the | plans. | | Which | is | correct? | | | | | | | | | | | | | | | |
Answer: Drawing was incorrectly labeled and should read ¼” = 1’‐0”
2) Question: Will panels TPS‐1 and TPS‐2 be a part of the temporary chiller package or part of the electrical contractor’s gear?
Answer: TPS‐1 and TPS‐2 are not part of the temporary chiller package. Contractor is to provide panels TPS‐1 and TPS‐2.
| 3) | | Deduct | Option | 1 | per | Specification | Section | 011000 | Part | 1.1.10.A | calls | for | underground | 12” | pipe | to | be | tested. | If | the | deduct | is |
| not | selected: | | | | | | | | | | | | | | | | | | | | | |
| a) | | Question: | | What | is | the | extent | of | the | piping | to | be | removed? | If | it | is | the | piping | under | the | existing | pump | room | floor, | this |
| will | also | include | floor | removal | in | the | pump | house. | | Correct? | | | | | | | | | | | | | | | |
Answer: If the deduct is not selected, all the piping from the chillers to the cooling towers will be replaced.
| b) | | Question: | What | about | the | 6” | CTS | and | CTR | that | exits | the | building | to | the | south? | To | what | extent | will | this | piping | need | to |
| be | replaced? | | | | | | | | | | | | | | | | | | | | | | | |
Answer: This piping will not be replaced.
| c) | | Question: | | Electrical | Drawing | E104 | sheet | notes | indicate | underground | circuit | and | wiring | to | remain. | | This | conduit | will |
| be | removed | if | the | floor | is | removed | to | replace | the | underground | 12” | pipe. | | How | should | we | figure | this | work? |
Answer: Replacement of the 12” pipe will stop at the foundation. The floor will not be removed.
| 4) | | Question: | | Drawing | M104 | and | M204 | talk | about | the | salvage | and | installation | of | new | screens. | | The | drawings | appear | to |
| indicate | grating | over | the | sumps | but | there | currently | exists | wood | planks | and | there | are | no | notes | suggesting | their | replacement. | | | |
| Is | it | the | intent | of | the | project | to | re‐use | these | planks | over | the | existing | sumps? | | | | | | | |
| Answer: | | The | screens | noted | on | sheets | M104 | and | M204 | are | the | vertical | trash/filter | screens | located | within | the | sump. | | New | | |
| screens | are | to | be | fabricated | to | match | the | existing | ones. | | The | cover | panels | are | part | of | the | system | covering | the | flume | (trough) |
| and | is | noted | on | Architectural | sheet | A202. | | See | also | answer | to | Question | 11 | for | additional | detail. | | | | | | |
| 5) | | Question: | | The | replacement | of | the | existing | chilled | water | valves | will | require | a | system | shut | down | to | accomplish | this | work. |
| What | is | the | extent | of | the | time | that | will | be | available | for | the | system | to | be | down | to | make | these | transitions? | |
| Answer: | | System | shutdowns | are | not | an | option. | | Plant | must | remain | operational | 24/7, | with | redundancy. | | All | branches | for | each | of | | |
| the | chiller | and | pumps | need | new | isolation | valves. | | During | temporary | chiller | operation, | the | CWR | header | piping | for | the | chiller | | | | |
| and | discharge | header | for | the | pumps | will | be | dry, | so | the | isolation | valves | can | easily | be | replaced | during | that | time. | | The | chilled | |
| water | supply | header | off | the | chiller | and | the | chiller | water | header | on | the | suction | side | of | the | CW | pumps | will | always | remain | active. | |
| This | line | cannot | be | disabled. | | Due | to | not | being | able | to | isolate | flow | and | the | valves’ | close | proximity | to | their | respective | headers | |
| (no | room | for | hot | tap/stopple), | these | eight | (8) | valves | will | need | to | be | abandoned | in | place | and | new | isolation | valves | installed | | | |
| downstream | on | each | branch, | with | about | 2’ | of | space | between | old | and | new | valves. | | This | will | include | the | four | (4) | valves | (1 | per |
| chiller) | on | the | CWS | lines | for | each | chiller | and | the | four | (4) | valves | (1 | per | CW | pump) | for | each | suction | end | of | the | pumps. |
| 6) | | Question: | | Drawing | M203 | shows | the | installation | of | a | 6” | bypass | installed | in | ESU | SSC | Office | B113A. | | I | do | not | believe | we | went | | |
| into | that | room | during | the | site | visit. | | Is | there | an | open | ceiling | in | this | area | or | is | it | similar | to | ESU | SSC | Break | Room | B113 | with | a |
| dropped | ceiling? | | | | | | | | | | | | | | | | | | | | | | | | | | |
Answer: ESU SSC Office B113A has a dropped ceiling similar to ESU SSC Break Room B113. Room B113A is to have a dropped ceiling.
| 7) | | Question: | | Drawing | A201 | Notes | 6 | & | 8 | call | out | for | the | room | to | be | painted. | Note | 7 | indicates | the | floors | should | be | painted | in |
| Rooms | B115, | B116, | and | B117. | | Do | Notes | 6 | & | 8 | only | apply | to | the | Chiller | Room | B115? | | | | | | | | | |
| Answer: | | Notes | 6 | and | 8 | only | apply | to | the | Chiller | Room | B115. | | Floors | are | repainted | in | chiller | room, | boiler | room, | and |
| vestibule/ramp. | | Note | 7 | does | not | indicate | floor | painting | in | Boiler | Room | B116 | and | vestibule/ramp | B118. | | Refer | to | Room | Finish | | |
| Schedule, | Drawing | A801 | for | floor | finishes | in | chiller | room, | boiler | room | and | vestibule/ramp. | | | | | | | | | | |
| 8) | | Question: | | Where | is | the | Heat | Exchanger | located | and | scheduled | as | described | in | Specification | Section | 011000 | Part | 1 | | | | | |
| (1.4)(A)(1)(d)(iv)? | | The | description | is | to | provide | a | heat | exchanger | in | the | pump | house, | but | there | is | only | one | heat | exchanger | | | | |
| scheduled | and | it | is | in | the | chiller | room. | | I’m | not | sure | what | this | is | referencing | because | I | don’t | see | one | in | the | pump | house. |
| Answer: | | Heat | Exchanger | is | in | the | chiller | room, | not | in | pump | house. | Remove | Section | 011000 | Part | 1 | (1.4)(A)(1)(d)(iv) | verbiage |
| “new | flat | plat | heat | exchanger | (new | free‐cooling | method)” | from | specifications. | | | | | | | | | | |
| 9) | | Question: | | Specification | Section | 011000 | Part | 1 | (1.5)(A)(2) | indicates | we | should | contact | Johnson | Controls | for | work | on | the | |
| legacy | DDC | Control | System | however | when | I | contacted | the | Fort | Collins | office | for | Johnson | Controls, | who | originally | had | a | service | |
| agreement | on | the | chillers, | they | indicated | they | had | not | performed | work | at | the | facility | since | 2014. | | Who | is | currently | responsible |
| for | the | DDC | control | system | for | the | facility? | | | | | | | | | | | | | |
| Answer: | | Schneider | Electric | is | the | DDC | control | provider. | Refer | to | Section | 23 | 09 | 00 | – | Instrumentation | and | Controls | for | HVAC |
| Part | 1, | 1.1(D)(10) | for | contact | information. | | | | | | | | | | | | | | | |
| 10) | | Question: | | What | is | meant | by | the | reference | in | Spec | Section | 011000 | Part | 1 | (1.4)(A)(1)(c)(vii) | “Provide, | install, | and | maintain |
| temporary | cooling | tower | units | and | other | associated | equipment | as | needed, | in | coordination | with | FAA | facility | personnel”? | | The | | | |
| temporary | chillers | provided | are | air‐cooled. | | Is | there | a | requirement | to | have | temporary | towers | for | the | existing | equipment? | | | |
Answer: No temporary cooling towers required, just chillers. Error in specification wording.
| 11) | | What | is | meant | by | the | reference | in | Spec | Section | 011000 | Part | 1 | (a)(1)(c)(iii) | “Redoing | the | trough | guard | outside | and | inside |
| the | pump | house” | and | Part | 1 | (1.4)(A)(a)(d)(ii) | “New | trough | guard | that | will | seal | better | than | existing” | regarding | redoing | the | | | |
| trough | guards? | | | | | | | | | | | | | | | | | | | | |
| Answer: | | There | is | a | concrete | trough | under | the | cooling | towers | that | returns | water | from | the | towers | to | the | sump | for | re‐use. | | This | | | |
| trough | and | the | sump | have | covers | on | them | to | keep | debris | out | and | to | keep | people | from | falling | in. | | They | are | also | used | to | control | |
| free | evaporation. | | This | is | what | we | refer | to | as | the | “guard”. | | They | are | currently | made | of | wood | and | are | subject | to | rot. | | The | covers |
| are | to | be | replaced | with | a | material | that | is | more | robust | than | wood. | | So | far | as | we | know, | no | commercial | product | specifically | for | | | |
| this | purpose | exists. | | Fiberglass | or | polypropylene | “planks” | or | sheet | stock | might | be | able | to | be | custom | cut | to | fit | the | openings. | | Or, | | | |
| the | contractor | is | free | to | offer | potential | solution | to | this | problem | based | on | their | (or | their | sub’s) | past | experience. | | | | | | | | |
| 12) | | Question: | What | is | meant | by | the | Spec | Section | 011000 | Part | 1 | (1.4)(A)(1)(e)(xiv) | “convert | as‐built | shop | drawings | to | FAA |
| standard | baseline | drawings”? | | | | | | | | | | | | | | | | | |
| Answer: | | Refer | to | Spec. | Section | 013100‐1.8. | | Using | FAA | provided | digital | data | files/drawings; | the | Contractor | will |
| incorporate/convert | their | approved | as‐built/redline | drawing | information | to | final | digital | as‐built | CAD | drawings | and | submit | to | | |
| the | FAA. | | | | | | | | | | | | | | | |
13) Question: Please provide contact information for the fire alarm vendor for this facility.
Answer: Contractor may use any qualified, certified fire detection and suppression subcontractor for this purpose.
14) Question: Please provide contact information for the access control subcontractor for this facility.
Answer: Refer to Section 23 09 00 – Instrumentation and Controls for HVAC Part 1, 1.1(D)(10) for contact information.
| 15) | | Question: | | Please | provide | contact | information | for | Schneider | Electric | to | get | on | their | distribution | list | for | the | DDC | pricing. |
| The | contact | information | in | the | spec | book | does | not | appear | to | be | current. | | | | | | | | |
Answer: Refer to Section 23 09 00 – Instrumentation and Controls for HVAC Part 1, 1.1(D)(10) for contact information.
| 16) | | Question: | | Is | there | an | environmental | report | available | that | would | show | approximate | quantities | to | help | abatement | vendors |
| with | their | scope | of | work? | | | | | | | | | | | | | | |
Answer: The whole EOF area will need to be abated, approximately 1,400 SF. See Note 5 on drawing A111.
17) Question: Can abatement work be done during normal hours?
| Answer: | | Yes, | the | extent | of | which | would | depend | upon | methods, | procedures, | activity | durations, | etc., | to | be | identified | by | the |
| contractor | in | the | required | asbestos | abatement | plan | that | is | subject | to | approval. | | | | | | | | |
| 18) | | Question: | | Underground | piping | replacement | from | the | towers | is | called | out | as | a | deductive | alternate | in | the | specifications. | I |
| do | not | see | it | listed | on | the | drawings | or | shown | on | the | drawings. | | Please | provide | plans | for | this | scope. | |
Answer: See attachment “Question 18 and 19 ‐ ZDV‐1401893‐M901”.
19) Question: Please identify the location and limits of the pipe testing area.
Answer: See attachment “Question 18 and 19 ‐ ZDV‐1401893‐M901”.
20) Question: Will the pipe testing agency be hired by the FAA direct?
Answer: The Contractor will hire the testing agency.
21) Question: Please confirm whether any arc flash studies are required for this project.
Answer: Yes all new panelboards will require Arc‐Flash labeling.
22) Question: Will the FAA remove all furniture, equipment, etc, from the EOF area?
| Answer: | | No, | contractor | is | required | to | move | all | furniture, | equipment, | etc., | from | the | EOF | area. | See | answer | to | Question | 29 | for |
| additional | details. | | | | | | | | | | | | | | | | | | | | |
23) Question: Does the temporary cooling piping, conduits, etc., need to be seismically restrained?
Answer: Yes.
24) Question: Does all plastic covering electronic equipment need to be static resistant?
Answer: Yes, all plastic covering electronic equipment needs to be static resistant and breathable.
25) Question: Is there any specification or specific acoustical wall panel called out in the spec? We did not see any.
| Answer: | | Spec. | Section | 098433‐2.1.A | identifies | basis | for | design. | Refer | to | Drawing | A801 | Room | Finish | Schedule | and | Interior |
| Color | Scheme | Schedule | for | specific | product | listed. | | | | | | | | | | | |
| 26) | | Question: | | To | what | extent | do | all | penetrations | need | fire | proofing | in | the | chiller | room? | Do | all | existing | penetrations | need | to |
| be | done | or | redone? | According | to | the | note | on | sheet | A001 | we | only | need | to | do | new | penetrations, | correct? | | | | |
| Answer: | | Only | new | penetrations | and/or | existing | penetrations | affected | by | and | rendered | non‐compliant | by | activities | performed | | | | | |
| under | the | scope | of | work | are | required, | per | Drawing | A001, | to | be | firestopped | or | reworked | for | compliance. | Chiller | Room | is | no |
exception.
| 27) | | Question: | | A022 | – | This | note | indicates | there | is | mold | behind | the | acoustical | panels. | | How | much | mold | is | present | so | we | can |
| quantify | how | much | work | needs | to | be | done? | | Also, | will | these | acoustical | panels | need | to | be | replaced | if | they | are | coated | in | | |
| mold? | | The | note | on | sheet | A112 | only | indicates | to | replace | the | red | and | orange | acoustical | panels. | | Are | there | any | visual | references | | |
| reflecting | how | far | the | mold | extends | or | which | color | of | panels | are | at | this | location? | | Please | provide | or | clarify. | | | | | |
| Answer: | | Estimated | square | footage | of | mold | is | as | follows: | HOST | Mechanical | Room | B119 | approximately | 200 | SF | behind | existing | | |
| light | brown | colored | panels. | Remove, | clean | of | mold | and | reinstall | light | brown | panels. | HOST | Computer | Room | B134 | | | | |
| approximately | 20 | SF | mold | behind | orange | panels | to | be | demolished. | | Refer | to | Drawings | A701 | and | A801 | as | they | apply | to |
| elevations | and | room | finishes. | | If, | during | the | project | work, | additional | mold | is | discovered | beyond | these | estimated | SFs, | a | change | |
| order | will | be | appropriate. | | | | | | | | | | | | | | | | | |
| 28) | | Question: | | A022 | – | Note | D | & | E | calls | for | the | contractor | to | “Test | and | abate | mold”. | I | can | not | price | this | if | I | do | not | know | how | far |
| it | extends. | | Please | advise. | | | | | | | | | | | | | | | | | | | | | | | | | | |
Answer: See Question 27 answer.
| 29) | | Question: | 1 | – | Note | 5 | & | 7 | indicates | to | remove | all | coating | on | the | floors | (vestibule | chiller | room | and | boiler | room) | to |
| concrete. | | The | general | contractor | is | responsible | to | move | all | furniture | and | equipment | within | the | room | and | then | replace | after | | | | |
| the | new | floor | coatings | have | been | installed. | | How | much | furniture | and | equipment | needs | to | be | removed | and | reinstalled. | | Please | | | |
| provide | photos. | | | | | | | | | | | | | | | | | | | | | | |
| Answer: | | See | Attachment | “Question | 29 | – | List | of | furniture” | for | an | estimate | of | items | required | to | be | moved | by | the | contractor. |
| The | items | will | be | moved | to | adjacent | rooms | and | will | not | require | going | up | or | down | stairs | or | significant | distances. | | |
| 30) | | Question: | As | per | drawing | A131 | ‐ | Note | 2 | (as‐built | drawings | of | the | NEOF | area | available | upon | request). | Please | provide | the |
| as‐built | drawings. | | | | | | | | | | | | | | | | | | | | |
| Answer: | | See | as‐built | drawing | Attachments | “Question | 30 | – | RMD‐502‐40449‐A05, | ‐A06, | and | ‐A07). | | FAA | does | not | consider |
| them | to | be | essential | for | bidding | purposes. | Price | your | bid | (offer) | based | on | drawings | provided | in | original | solicitation. |
31) Question: A132 – Does a HEPA vacuum need to be used to vacuum the acoustical ceiling before it is demolished?
Answer: Yes.
| 32) | | Question: | | A201 | – | Note | 1 | indicates | to | firestop | existing | and | new | penetrations | in | fire | rated | barriers. | | As | we | can | not |
| determine | how | many | or | how | large | any | existing | penetrations | are, | we | request | an | allowance | be | determined | for | this | work | and | | | | |
| indicated | in | the | response | to | the | questions. | | How | much | should | this | allowance | be? | | | | | | | | | | |
| Answer: | | No | allowance | will | be | allowed. | | Only | new | penetrations | and/or | existing | penetrations | affected | by | and | rendered | non‐ |
| compliant | by | activities | performed | under | the | scope | of | work | are | required | to | be | firestopped | or | reworked | for | compliance. | Chiller |
| Room | and | vestibule | are | no | exception. | | | | | | | | | | | | | |
33) Question: A201 – Note 6 Is this note for just the chiller room? Should the boiler room be done also?
| Answer: | | Note | 6 | applies | only | to | the | chiller | room. | Chiller | room | B115 | is | the | only | room | to | have | walls | painted. | Boiler | room | B116 |
| and | vestibule | will | not | have | wall | patching. | | | | | | | | | | | | | | | | | |
34) Question: A211 – Note 3 Please confirm what the construction of the existing wall is? Metal stud & drywall, masonry?
Answer: Existing wall is metal stud and 5/8” fire rated drywall each side.
35) Question: A211 – Note 10 Please confirm what this cover plate is and what it will be. Steel?
Answer: Existing cover plate is steel. Coordinate replacement with floor finish requirements in accordance with Note 10.
| 36) | | Question: | | A201 | – | Note | 4 | Please | provide | a | photo | of | the | leak. | What | is | the | cause | of | the | leak | and | how | large | is | it | so | we | can |
| determine | what | needs | to | be | done | to | correct | it? | | | | | | | | | | | | | | | | | | | | | |
| Answer: | | Photos | below | show | exterior | and | interior | view | of | leak | in | Boiler | Room | south | wall. | | Water | wicks | under | the | curb | for | its |
| full | length. | Since | the | pre‐bid | meeting | on | August | 28 | there | has | not | been | nor | will | there | be | a | significant | change | in | the | conditions. | |
Exterior view looking down
Exterior view looking West
Exterior view looking East
Interior view
| 37) | | Question: | | A212 | Note | 4 | indicates | to | inspect | existing | fire | stopping | and | repair | any | that | fail. | | We | have | no | way | to | price | this |
| item | as | we | do | not | know | what | will | or | will | not | fail. | | Please | provide | an | allowance | for | this | item. | | | | | | |
| Answer: | | No | allowance. | | The | FAA | is | unaware | of | any | failing | fire | stoppings. | | Price | your | bid | (offer) | on | new | penetrations | only. | Any |
| failed | fire | stopping(s) | discovered | during | the | project | work | will | be | negotiated | in | a | change | order. | | | | | | | | | |
38) Question: A212 Note 7 is this stair and handrail system part of the access floor system or a structural steel stair system?
Answer: The stair and handrail system is to be part of the raised floor system.
| 39) | | Question: | A212 | Note | 12 | please | verify | what | work | needs | to | be | done. | It | is | asking | for | an | inspection | of | the | columns | and | to | be |
| refinished | if | necessary. | We | can | not | quantify | this | until | the | inspection | has | been | done. | | | | | | | | | | | | |
| Answer: | | With | the | exception | of | one | (1) | side | of | one | column | on | which | cable | tray | is | present, | resurfacing | each | side | of | all | six | (6) |
| columns | is | required. | | | | | | | | | | | | | | | | | | | | | | |
40) Question: A212 Note 14 What type of fire extinguisher?
Answer: Dry chemical Type A‐B‐C.
| 41) | | Question: | | A212 | Note | 17 | This | note | indicates | to | block | the | ceiling | louvers | that | are | still | working. | Is | this | correct? | How | many |
| are | there? | | How | large | are | they? | | Are | these | shown | on | the | Mechanical | drawings? | | | | | | | | | |
Answer: There is only one louver. It is verified that it was blocked off in January 2015. Remove from scope of work.
| 42) | | Question: | | Plans | indicate | to | remove | and | replace | acoustical | wall | panels | that | are | red | and | orange. | | As | the | plans | are | not | in |
| color | can | you | indicate | which | panels | are | red | and | orange | so | we | can | quantify | how | much | gets | removed | and | needs | to | be | replaced? | | |
| Answer: | | Elevations | on | sheet | A701 | (note | 1) | show | the | extent | of | the | red | and | orange | panels. | Refer | to | Drawing | A801 | “Door | and |
| Finish | Schedules”. | | | | | | | | | | | | | | | | | | | | | |
| 43) | | Question: | | On | A301, | where | the | new | addition | to | the | building | is | being | added? | | There | appears | to | be | utilities | running | through | | | |
| that | space. | Are | we | required | to | relocate | these | utilities? | | Or | are | we | to | build | on | top | of | them? | | Or | will | this | be | handled | by | the |
| government? | | Will | the | grounding | counter | pose | be | in | the | way? | | | | | | | | | | | | | | | | |
| Answer: | | Utilities, | including | existing | counterpoise | do | run | underground | through | the | new | building | footprint. | Yes, | the | Contractor | | | | |
| is | responsible | to | perform | utility | locates | and | to | coordinate | with | the | FAA. | | The | FAA | will | provide | as‐built | information | to | the |
| Contractor | to | the | best | of | our | knowledge | and | available | information | prior | to | construction. | However, | the | Contractor | remains | | | | |
| responsible | for | the | location | and | protection | of | underground | utilities. | | | | | | | | | | | | |
44) Question: A301 Who is the pre engineer building Manufacturer of the existing building?
Answer: Unknown. No manufacturer’s label is visible on or in the building.
45) Question: A701‐ requires to clean all acoustic panels. What will be the preferred method?
Answer: Dry extraction. Exact method is to be determined by the Contractor, subject to FAA approval.
| 46) | | Question: | | M211 | and | M212 | ‐ | will | new | tiles, | stringers, | and | pedestals | need | to | be | provided | for | the | floor | altering | or | will | the |
| FAA | have | attic | stock | that | can | be | used? | Is | there | an | existing | rating | in | the | floor? | | | | | | | | | |
| Answer: | | The | Contractor | is | not | required | to | provide | new | tiles; | FAA | has | enough | in | stock. | | The | Contractor | will | be | required | to | fill |
| in | around | affected | area | with | existing | tiles | supplied | by | FAA. | | The | Contractor | will | need | to | provide | two | (2) | pedestals, | two | (2) | | |
| pedestal | heads, | and | one | (1) | stinger | (manufacturer | Tate | and | product | name | Concor). | | | | | | | | | | | | |
47) Question: E214 ‐ is there a requirement to paint conduits and ducts in this space?
Answer: If the reference is to the HOST Mechanical Room B119, there is no requirement to paint the duct and conduits in the space.
48) Question: Is there a requirement to be certified for fire caulking?
Answer: Yes.
| 49) | | Question: | | Will | mechanical | provide | new | VFDs | for | chillers, | pumps, | & | cooling | towers; | we | typically | exclude | them, | as | | | |
| mechanical | contractors | typically | get | package | deals | with | their | vendors | to | ensure | they | | are | compatible | with | motor | loads; | I | do | | | |
| have | an | RFI | question | on | the | rating | of | the | VFD | enclosures, | one | note | says | NEMA | 3R | and | another | says | NEMA | 4X | stainless | steel. |
| Please | clarify. | | There | could | be | a | big | cost | difference | on | these | ratings. | | | | | | | | | | |
| Answer: | | | Contractor | will | supply | the | VFDs | for | the | cooling | tower | fans | and | pumps | to | meet | specification | requirements. | | Chiller |
| manufacturer | will | supply | the | VFDs | to | meet | the | new | chiller | system | requirements. | | The | rating | of | the | VFD | enclosures | shall | be |
| NEMA | 12 | stainless | steel. | | | | | | | | | | | | | | | | | |
| 50) | | Question: | | Data/Comm, | ‐ | We | do | not | see | any | scope | or | devices | shown | on | the | drawings | for | new | Data/Comm. | Are | there | any |
| new | Data/Comm | devices | to | be | installed, | and | if | so, | how | many | and | where | are | they | located? | | | | | | | | |
| Answer: | The | scope | of | the | Data | and | Communications | will | be | provided | by | the | Schneider | Electric | Program | office | as | part | of | their |
| design. | Refer | to | Spec | Section | 23 | 09 | 00 | – | INSTRUMENTATION | AND | CONTROLS | FOR | HVAC, | Part | 1 | (1.1)(D)(10) | for | current | | |
information.
| 51) | | Question: | | Access | Control, | don’t | really | see | any | scope | shown | on | the | electrical | drawings, | but | recall | them | showing | us | several | | |
| doors | that | are | to | be | replaced | and | have | card | readers | installed. | | Do | we | need | to | cover | boxes | & | raceways | only? | Will | you | be |
| covering | the | cabling | via | the | preferred | FAA | vendor? | | Do | you | know | how | many | doors | and | the | extent | of | conduit | that | will | need | to |
| be | installed? | | | | | | | | | | | | | | | | | | | | | | |
Answer: See Door Schedule in the drawing set A801 for location of doors. Honeywell is the current provider of these services.
| 52) | | Question: | | Lightning | Protection: | Is | the | contractor | responsible | for | this? | Should | we | reach | out | to | National | Lightning |
| Protection | to | cover | this? | | | | | | | | | | | | | | | |
| Answer: | | Contractor | is | responsible | for | providing | lightning | protection | work. | | Contractor | must | follow | the | most | current | lightning |
| protection | standard | NFPA | 780 | – | Standards | for | the | Installation | of | Lightning | Protection | Systems | and | FAA‐STD‐019f | – | Lightning | |
| and | Surge | Protection, | Grounding, | Bonding, | and | Shielding | Requirements | for | Facilities | and | Electronic | Equipment. | | See | attachment | | |
| “Question | 52, | 72 | and | 74 | ‐ | FAA‐STD‐019f”. | | | | | | | | | | | |
| 53) | | Question: | | Please | confirm | that | the | engineering | team | has | verified | new | specified | chillers | will | be | able | to | be | routed | down | into |
| the | existing | location | and | the | best | route. | | | | | | | | | | | | | | | | |
| Answer: | | Best | route | for | chiller | passage | has | been | confirmed | as | the | exterior | areaway | on | the | south | side | of | the | boiler | room | B116. |
| This | is | the | same | location | that | has | been | used | at | every | other | site | and | should | provide | ample | clearance | for | equipment | passage. | | |
| Exterior | stair | assembly | must | be | removed | for | clearance. | | | | | | | | | | | | | | | |
54) Question: Will the temporary fencing the contractor brings in be required to be grounded or have lighting protection?
| Answer: | | Yes. | | The | contractor | will | provide | the | temporary | fencing | around | the | temporary | equipment | space | for | security | and |
| hazard | requirement. | The | contractor | will | provide | grounding, | bonding | and | lightning | protection | for | the | temporary | electrical | | | | |
| equipment | and | other | mechanical | pipes | in | the | temporary | equipment | space. | | | | | | | | | |
| 55) | | Question: | | M‐203 | shows | a | new | Chilled | water | bypass | (notes | 5 | & | 6). | | The | current | location | is | above | desks | in | a | drop | ceiling. | | |
| There | is | so | little | room | that | the | ceiling | tiles | are | cut | out | to | allow | for | the | roller | hangers | to | still | spin. | | Please | advise | how | we | are | to |
| install | a | 6” | bypass | line, | complete | with | valves | and | where | a | hot | tap | machine | will | fit | (zero | clearances | above | too). | | | | | | | | |
Answer: This location can be adjusted for constructability, but may cause the need to move DP and flow sensors.
| 56) | | Question: | | Page | Z131, | Note | 1 | requires | a | 3rd | temporary | air‐cooled | chiller | with | the | same | piping | configuration | and | specs | to | | |
| be | on | standby | locally | with | the | ability | to | be | hooked | up | and | started | on | the | Longmont | campus | within | 24 | hours’ | notice. | | The | only |
| possible | way | for | this | 3rd | temporary | chiller | to | be | guaranteed | to | be | that | close | to | the | project | site, | and | guaranteed | to | be | the | same |
| specs, | size, | and | piping | requirements | is | for | the | contractor | to | rent | that | additional | chiller | and | already | have | it | stored | on | site | for | | |
| the | duration | of | the | temporary | chiller | plants’ | existence. | | Two | questions: | | | | | | | | | | | | | |
1. Is their space at the Longmont facility to accommodate the 3rd chiller?
| Answer: | Yes. |
| ____________________________________________________________________________________________________________________ | |
2. Is it the FAA’s intent to pay for and include the rental cost of the additional 3rd chiller in the GC’s pricing proposal?
Answer: Yes.
| 57) | | Question: | | What | approximate | percentage | of | the | work | on | the | contract | will | be | required | to | be | performed | during | the | night |
| hours, | approximately | 10:00 | PM‐6:00 | AM? | | | | | | | | | | | | | | | | | |
| Answer: | | It | is | the | Contractor’s | responsibility | to | determine | (and | subsequently | identify | on | their | project | schedule) | the | hours |
| required | outside | of | the | specified | normal | working | hours, | using | specified | requirements | and | constraints | such | as | explicit | | |
| language | pertaining | to | cutovers. | | | | | | | | | | | | | | |
| 58) | | Question: | | Spec | Section | 014000‐3 | states | the | contractor’s | Project | Quality | Control | manager | shall | not | have | other | project | | | | | |
| responsibilities. | | Is | the | FAA’s | intent | to | have | a | full | time, | on‐site | QCM | for | the | duration | of | the | project | that | cannot | be | either | the |
| Superintendent, | Safety | Manager, | or | Project | Manager? | | | | | | | | | | | | | | | | | | |
Answer: No, that is not the FAA’s intent. QCM and SSHO may be the same person. See also the answer to Question 59 below.
| 59) | | Question: | | Spec | Section | 013529‐2 | states | the | SSHO | must | be | on‐site | during | working | hours | to | implement, | administer, | and |
| enforce | Contractor’s | safety | and | health | program | and | APP. | | | | | | | | | | | | |
o SSHO may not be the Contractor’s superintendent.
o SSHO may be the Contractor’s quality control manager and must report to a senior Project or corporate official.
| This | verbiage | conflicts | with | spec | section | 014000‐3 | that | states | that | the | QCM | shall | not | have | other | project | responsibilities. | | | | | | |
| Please | clarify | the | number | of | full | time | employees | is | requiring | onsite. | | My | understanding | is | that | the | contract’s | intent | would | | | | |
| require | a | full | time | superintendent | and | a | full | time | QC/Safety | Manager | on | site | at | all | times. | | Or, | are | you | requiring | 3 | separate | full |
| time | personnel | (super, | QC, | Safety) | on | site | at | all | times? | | | | | | | | | | | | | | |
| Answer: | | Spec | Section | 013529, | Part | 1 | (1.7)(B) | is | correct. | | The | SSHO | must | be | onsite | during | working | hours. | The | same | person |
| may | serve | in | both | the | QCM | and | SSHO | roles | simultaneously, | but | neither | can | be | the | contractor’s | Superintendent | or | Project | | | |
| Manager | simultaneously. | | | | | | | | | | | | | | | | | | | | |
| 60) | | Question: | | Please | detail | the | security | requirements | and | timelines | for | bringing | a | new | employee/worker | on | site | at | | |
| Longmont, | including | the | timelines | for | approval | of | the | different | types | of | badging | and | how | long | a | worker | will | be | allowed | to |
| work | onsite | under | a | temporary | badge. | | | | | | | | | | | | | | | |
| Answer: | | Contractor | submits | names | of | personnel | that | will | receive | PIV | badges | to | the | Contracting | Officer’s | Representative | | | | | |
| (COR) | and | also | enters | the | information | into | the | FAA | “VAP” | security | system. | | Once | information | is | entered | into | the | system, | it | can |
| take | up | to | four | (4) | weeks | for | background | and | issuance | of | badges. | | Most | workers | will | be | provided | temporary | visitor | badges | on |
| a | daily | basis. | | Personnel | that | are | badged | will | have | escort | privileges | and | will | be | required | to | escort | workers | with | a | daily |
| temporary | badges | at | all | times. | | It | is | the | Contractor’s | responsibility | to | ensure | that | enough | personnel | are | PIV | badged | so | that | |
| escorting | will | not | be | an | issue | in | the | case | of | work | being | performed | in | different | areas | of | the | facility | simultaneously. | | |
| 61) | | Question: | | Pump | schedule | calls | for | 2‐stage | pump | (turbines), | but | there | isn’t | a | spec | section | for | this | type | of | pump. | Will | one |
| be | provided? | | (Section | 232123 | – | 2.4 | does | not | apply). | | | | | | | | | | | | | | |
Answer: See highlighted areas of revised specs section 23 21 23 attachment “Question 61 – 23 21 23 Hydronic Pumps Amendment”.
| 62) | | Question: | | Cooling | Tower | Schedule | basis | of | design | is | Tower | Tech | (we | are | the | local | Tower | Tech | rep), | but | the | following |
| items | in | the | specifications | do | not | apply | to | Tower | Tech | (please | clarify): | | | | | | | | | | | |
| a) | | Question: | | Page | 721 | of | the | specs | list | the | tower | as | “induced | draft”. | There | is | no | provision | for | “forced | draft” | (Tower |
| Tech | is | forced | draft). | | | | | | | | | | | | | | | | | | | |
Answer: The FAA requires a forced draft cooling tower.
b) Page 723 reiterates “induced draft” (Tower Tech is forced draft).
| Answer: | Same | as | above | question | (a). |
| ________________________________________________________________________________________________________________________ | | | | | |
c) Page 724 Section H lists louvers as part of the supply of the cooling tower (Tower Tech does not have louvers).
| Answer: | Louvers | are | optional, | depending | on | the | cooling | tower | type. |
| _________________________________________________________________________________________________________________________ | | | | | | | | | |
| d) | | Page | 724 | Section | I | says | that | the | fan | needs | to | be | balanced | after | assembly | and | that | fan | screens | have | to | be | 304 | SS |
| wire | mesh | (Tower | Tech | utilizes | individual | direct | drive | motors, | which | do | not | require | balancing). | | | | | | | | | | | |
Answer: Fans should be balanced by the manufacturer. Upon building, they don’t need to be balanced onsite.
e) Page 725 Section J says that motors are TEFC (Tower Tech utilizes TEAO motors).
| Answer: | Both | TEFC | and | TEAO | are | fine. |
| ________________________________________________________________________________________________________________________ | | | | | | |
f) Page 725 Section K says to supply vibration switch (Tower Tech does not require).
Answer: FAA requires vibration switch. The switch is to be supplied by the controls’ contractor to ensure proper fan operation.
g) Page 725 Section M says to provide access doors for entering cooling tower (Tower Tech does not require).
| Answer: | | Whether | access | doors | are | needed | will | depend | upon | the | manufacturer’s | design | of | the | cooling | tower. | | If | the | |
| manufacturer | is | Tower | Tech, | whose | cooling | towers | do | not | contain | a | gearbox, | access | doors | will | not | be | required. | | If | an |
| approved | equal | manufacturer’s | cooling | tower | is | approved, | the | requirement | of | access | doors | will | be | dependent | upon | | | | | |
| the | design | of | the | cooling | tower. | | | | | | | | | | | | | | | |
| 63) | | Question: | Tower | Tech | suggests | rotating | the | towers | 90 | degrees | in | order | to | reduce | piping | requirements | and | reduce | the |
| risk | of | recirculation. | See | attached | drawing | notes. | | | | | | | | | | | | | |
Answer: To maintain seismic design, the proposed drawing will stand. Recirculation is not a primary concern.
64) Question: 230548 – 2.1 and 2.2 – can Vibro‐Acoustics be added to the list of acceptable manufacturers?
| Answer: | List | of | manufactures | is | not | limited | to | those | vendors | on | the | list. | | The | list | provided | are | known | manufacturers | to | the |
| FAA. | Any | manufacturer | that | meets | the | specs | may | be | approved, | even | if | not | listed. | | | | | | | | |
| 65) | | Question: | | Please | clarify | NEMA | Enclosure | requirements | for | the | pumphouse | electrical | equipment. | | General | Note | B | on | | | | | |
| Drawing | ZDV‐1401893‐E204 | says | VFDS | & | disconnects | inside | | and | outside | the | pumphouse | are | to | be | NEMA | 4X | stainless | steel | | | | | |
| and | other | equipment | within | the | pumphouse | should | be | NEMA | 3R. | | Does | that | note | apply | to | the | new | electrical | room | addition | and | | |
| is | that | room | considered | part | of | the | pumphouse? | | Do | all | the | new | electrical | panels, | transformer, | potential | harmonic | filters, | etc., | | | | |
| within | the | new | addition | need | to | be | NEMA | 3R | or | NEMA | 12? | | The | new | wireway | shown | on | Drawing | ZDV‐1401893‐E302 | is | to | be | |
| NEMA | 1 | per | Key | Note | 4, | and | the | two | new | electrical | panels | are | to | be | NEMA | 12; | no | rating | is | shown | for | the | transformer. |
Answer: All the VFDs, electrical panels and a step down transformer NEMA ratings are 12.
| 66) | | Question: | | Please | clarify | which | trade | is | to | provide | all | new | Variable | Frequency | Drives. | | Typically, | the | mechanical | contactor |
| provides | them | as | a | package | component | with | new | pumps, | cooling | towers, | chillers, | etc. | to | ensure | they | are | compatible | with | the | |
| motor | loads | they | are | controlling | and | the | electrical | contractor | installs | them. | | Is | that | correct? | | | | | | |
| Answer: | | Contractor | will | supply | the | VFDs | for | the | cooling | tower | fans | and | pumps | to | meet | specification | requirement. | Chiller |
| manufacturer | will | supply | the | VFDs | to | meet | the | new | chiller | system | requirement. | | | | | | | |
| 67) | | Question: | | Please | clarify | Key | Note | 12 | on | Drawings | E204 | & | E714 | regarding | the | potential | harmonic | filters | for | the | (3) |
| cooling | towers | and | the | (2) | chillers. | | Where | it | says | contractor | should | test | circuit | and | only | install | the | harmonic | filters | if | the |
| distortion | exceeds | FAA | specifications: | shouldn’t | these | harmonic | filters | possibly | be | considered | as | an | Add | Alternate | or | Deduct | | | | | |
| Alternate | to | the | project | pricing | as | they | may | not | be | necessary | until | testing | has | determined | they | will | be | required? | | | |
| Answer: | | For | all | cooling | tower | fans | and | pumps, | use | 6‐pulse | VFD | drives. | | No | need | to | install | the | harmonic | filters. |
| For | the | chiller, | contractor | shall | provide | chillers | including | VFDs | and | filters | that | meet | the | requirement | for | reducing | THD. | | | |
| 68) | | Question: | | Please | clarify | scope | of | work | for | Panels | HC3 | & | HC4; | the | drawings | indicate | that | all | loads | and | feeds | are | to | be |
| removed | from | the | source. | | How | many | circuits | are | currently | installed | within | these | two | panels? | | What | are | these | circuits | | | | | |
| currently | feeding | and | what | other | demo | is | associated | to | these | circuits? | | Are | we | to | demo | outlets, | equipment, | etc. | as | well? | Also, | | | |
| where | are | Panels | CPC‐ | A,B,C | located | that | feed | these | panels? | | What | are | the | conduit/wire | sizes | & | lengths | of | the | feeds | between | | | |
| the | panels? | | | | | | | | | | | | | | | | | | | | | | | |
| Answer: | | Panels | HC2 | and | HC3 | are | the | reconditioned | panels. | HC1, | HC2, | HC3, | and | HC4 | have | 42 | circuits | each, | but | there | are | no | | |
| active | circuits | on | any | of | the | panels. | | Demo | all | conduits, | outlets, | and | branch | circuits | for | panels | HC1, | HC2, | HC3, | and | HC4. | | | |
| Remove | all | feeders | back | to | the | source | for | panels | HC1 | and | HC4. | | Panels | CPC‐A, | B, | C | are | located | in | B13 | in | the | Automation | Wing |
| Basement, | critical | power | vault. | | Feeders | for | panels | HC1 | and | HC4 | will | be | removed | to | the | source. | | Feeders | for | HC2 | and | HC3 | will | |
| be | retained | for | re‐use. | | No | feeder | conduit | removal | is | required. | | | | | | | | | | | | | | |
| 69) | Question: | | Please | clarify | scope | & | provide | panel | schedules | for | Panels | HC1 | & | HC2 | which | are | to | be | reconditioned. | | Are | there | | |
| existing | loads | within | these | panel | boards | that | may | need | to | be | temporarily | fed | from | another | source | while | the | panels | are | being | | | | |
| reconditioned? | | How | many | loads | are | currently | installed | within | these | panels? | | Are | there | any | new | loads | to | be | installed | within | | | | |
| these | panels? | | How | many | new | circuit | breakers | will | be | required | and | what | are | the | sizes/ratings? | | Is | all | existing | wire | to | remain | | |
| and | be | reused/terminated | to | the | reconditioned | panel? | | What | if | existing | wiring | is | too | short? | | Will | these | panels | possibly | have | to | | | |
| be | reconditioned | during | a | special | outage | timeframe, | possibly | at | night, | requiring | overtime? | Also, | please | clarify | the | scope | to | the | | | | | | |
| Government | Provided | Paragon | Transfer | Switches | associated | with | these | two | panels. | | Where | are | they | to | be | installed? | | What | is | | | | | |
| the | size | of | these | switches? | | Are | they | to | be | wall | mounted, | floor | mounted, | recessed | next | to | these | panels? | | What | are | the | conduit | & |
| wire | size | requirements | for | these | switches | as | the | onelines | do | not | indicate. | | Are | the | existing | to | remain? | | It | appears | that | CPC‐A | & | |
| B | may | be | new | feeds. | | | | | | | | | | | | | | | | | | | | |
| Answer: | | Panels | HC2 | and | HC3 | are | the | panels | that | will | be | reconditioned. | There | are | no | existing | loads | for | these | panels, | no | new | |
| loads | will | need | to | be | installed, | and | these | panels | do | not | need | new | circuit | breakers. | Only | the | feeders | need | to | remain. | There | is | no |
| special | outage | timeframe | for | reconditioning | panels | HC2 | and | HC3. | The | Government | Provided | Paragon | Transfer | Switches | are | | | | | | | | |
| wall | mounted | and | recessed | above | the | panels. | The | conduit | and | wire | size | will | be | the | same | size | as | the | feeders. | | | | |
| 70) | | Question: | | Please | provide | more | information | & | specification | requirements | for | the | new | Signal | Reference | Grid | (SRG) | that | is | | | |
| to | be | installed | under | the | Host | Computer | Room | raised | floor. | | There | does | not | appear | to | be | any | specifications | or | details | for | this |
| scope. | | Please | clarify | materials, | sizing, | manufacturer, | installation | details, | etc., | for | the | SRG. | | | | | | | | | | |
| Answer: | | FAA‐STD‐019f, | 4.7.3.2.a | Signal | Reference | Ground | Grid: | SRGG | shall | consist | of | a | grid | of | 2‐in | wide | copper | strips, | 26 |
| gauge | or | thicker, | placed | on | a | 2x2‐ft | square | grid | and | welded | at | each | grid | intersection. | | | | | |
| 71) | | Question: | | Please | clarify | if | 4/0 | perimeter | grounding | loop | is | existing | or | new | to | be | installed | under | this | project. | | Note | 1 | on |
| Drawing | ZDV‐1401893‐E215 | says | it’s | existing, | but | Specification | Summary | Pg. | 011000‐5_3_e_ii | says | to | install. | | Also, | please | | | | | | | | | |
| clarify | if | there | are | to | be | (3) | new | 4/0 | cross | connects | installed | across | the | room | running | from | North | to | South | bonding | to | the | | |
| perimeter | ground | ring | as | well, | or | if | these | are | existing? | | | | | | | | | | | | | | | |
| Answer: | | 4/0 | perimeter | grounding | loop | is | existing. | | No, | (3) | new | 4/0 | cross | connecting | the | perimeter | ground | on | the | North | and |
| South | walls | is | not | existing | and | is | not | required | to | be | installed. | | The | drawing | and | Specification | summary | will | be | updated | to |
| represent | these | changes. | | | | | | | | | | | | | | | | | | | |
| 72) | | Question: | | Please | clarify | if | all | Panels | within | the | Host | Computer | Room | are | to | be | bonded | to | the | new | 4/0 | perimeter | ground |
| ring, | including | Panels | HC3 | & | HC4. | | There | are | no | bold | points | identifying | the | existing | panels | located | along | the | East | Wall, | except | | |
| Note | 5 | on | Drawing | ZDV‐1401893‐E215; | however, | where | Note | 5 | is | shown, | there | are | no | electrical | panels. | | | | | | | | |
| Answer: | | Panels | HC2 | and | HC3 | are | the | reconditioned | panels. | | Panels | B‐B134‐BS1, | B‐B134‐BS2, | HC2, | and | HC3 | are | currently | not |
| bonded | to | the | existing | 4/0 | perimeter | ground, | so | the | contractor | will | be | required | to | bond | four | (4) | enclosures | to | perimeter |
| grounding | conductor | by | exothermic | welding | in | accordance | with | FAA‐STD‐019f | (see | Attachment | “Question | 52, | 72, | and | 74 | – | | | |
FAA‐STD‐019f”).
| 73) | | Question: | | Please | clarify | if | all | the | Multiground | Plates | referenced | by | Note | 9 | on | Drawing | ZDV‐1401893‐E215 | are | existing | or | | |
| if | there | are | new | ones | installed | per | this | project. | | How | are | the | existing | Multiground | Plates | currently | bonded | together? | | Are | we | to |
| demo/remove | any | existing | grounding | system | once | the | new | system | is | installed? | | | | | | | | | | | | |
| Answer: | | All | the | multiground | plates | referenced | by | Note | 9 | are | existing | multiground | plates. | | No | need | to | install | new | multiground |
| plates. | | The | Existing | multiground | plates | are | verified | properly | bonded | to | perimeter | grounding | conductor | by | exothermic | | | | | |
| welding | in | accordance | with | FAA‐STD‐019f. | | No | further | action | needed. | | | | | | | | | | | |
| 74) | | Question: | | Please | clarify | and/or | provide | details | on | how | the | existing | cable | tray | is | to | be | grounded | and | how | often; | is | to | be |
| connected | to | the | ground | loop, | SRG, | or | multiground | plate? | | | | | | | | | | | | | | | | |
Answer: Refer to attachment “Question 52, 72, and 74 ‐ FAA‐STD‐019f”.
| 75) | | Question: | | Please | clarify | if | irreversible | compression | grounding | connections | can | be | utilized | for | the | Host | Computer | Room | | | |
| new | grounding | system, | in | lieu | of | exothermic | welding, | as | this | will | be | inside | and | may | cause | issues | with | the | Fire | Alarm | System |
| and | smoke | detectors. | | | | | | | | | | | | | | | | | | | |
Answer: The new grounding system is requires exothermic welding.
| 76) | | Question: | | Please | clarify | if | the | Type | RL | & | RL1 | light | fixtures, | & | Exit | Signs | in | the | Host | Computer | Room | shown | on | Drawing |
| ZDV‐1401893‐E212 | are | new | light | fixtures, | or | if | they | are | existing | to | remain | with | new | lenses | installed | as | identified | in | | | | | | |
| Specification | Summary | Pg. | 011000‐6_3_e_iv. | | | | | | | | | | | | | | | | | | | | | |
Answer: RL and RL1 are to be replaced with new light fixtures. Exit signs are to be replaced with new wall mounted LED exit signs.
| 77) | | Question: | | Please | clarify | electrical | demo | scopes | for | the | temporary | offices | per | Note | 6 | on | Drawing | ZDV‐1401893‐E114. | | | | | | | |
| How | many | electrical | & | data/comm | outlets | are | located | with | these | offices | that | are | to | demo? | | Also, | what | is | to | be | done | with | the | | |
| light | fixtures | & | light | switches? | | | Are | they | existing | to | remain? | | | Will | light | fixtures | have | to | be | relocated | and | if | so, | how | many |
| fixtures | are | there, | and | how | are | they | to | be | controlled? | | | | | | | | | | | | | | | | |
| Answer: | | All | electrical | and | data/comm. | outlets | are | to | be | demoed | in | the | office | locations. | No | light | fixtures | or | light | switches | need | |
| to | be | demo’d; | the | existing | are | to | remain. | Light | fixtures | and | switches | do | not | need | relocation | and | it | is | not | necessary | to | control |
| them | as | they | are | already | controlled. | | | | | | | | | | | | | | | | | |
| 78) | | Question: | | Please | clarify | scopes | of | work | associated | with | MCC | A, | 1A, | B, | 1B, | C, | 1C, | & | D | Specification | Summary | Pg. | 011000‐ |
| 5_3_D_i | thru | iv. | | The | project | summary | makes | reference | to | removing | and | replacing | these | MCC’s | and | to | provide | harmonic | | | | | |
| testing | on | the | feeder | sides | of | these | MCC’s; | however, | at | the | job | walk | is | was | mentioned | that | replacement | of | these | MCC’s | is | | |
| covered | under | a | separate | project | and | not | to | be | part | of | this | contract. | | Also, | please | clarify | if | replacing | circuit | breakers | within | | |
| these | MCC’s | are | required. | | Sheet | Note | 4 | on | the | various | MCC | one‐line | diagrams | says | to | verify | fuse/breaker | size | to | ensure | | | |
| proper | coordination. | | Are | we | to | replace | the | circuit | breakers | if | they | are | not | of | the | correct | size | & | rating | for | the | new | loads? |
| Answer: | | | | The | MCCs | (A,B,C, | 1A, | 1B, | 1C | & | D) | project | that | included | the | harmonic | testing | tasks | on | the | MCCs’ | feeder | sides | are |
| covered | under | a | separate | project. | The | MCCs | project | is | not | to | be | part | of | the | Major | Mechanical | project. | | Note | 4 | from | the | one | line |
| diagram | is | for | field | checking. | | Whether | the | fuse/circuit | breaker | will | need | to | be | replaced | is | dependent | upon | the | product | | | | | |
| submittal | that | the | contractor | submits | for | approval. | | If | they | are | of | a | different | size | than | what | is | on | the | drawings, | they | will | need | |
| to | be | replaced. | | | | | | | | | | | | | | | | | | | | | | |
| 79) | | Question: | | Please | clarify | if | lightning | protection | is | required | for | AHU‐400 | as | identified | in | Specification | Summary | Pg. | | | | |
| 011000‐6_3_g_i. | | It | appears | that | this | AHU | is | located | inside | the | building | in | Mech. | Rm. | B129 | and | the | drawings | do | not | show | or |
| note | any | lightning | protection | associated | with | this | unit. | | | | | | | | | | | | | | | |
Answer: Lightning protection will not be required for AHU‐400.
| 80) | | | Question: | | Please | clarify | exterior | outlets, | unit | heaters, | & | lighting | requirements/scopes | of | work | associated | with | the | |
| temporary | chillers. | | Are | we | to | provide | light | poles, | mount | lights | upon | the | temporary | chillers, | or | on | the | temporary | fence? |
| Where | will | electrical | outlets | be | required | and | how | many? | | | | | | | | | | | |
| Answer: | | The | contractor | will | provide | exterior | outlets, | unit | heaters | and | temporary | lighting | around | the | temporary | equipment | | | |
| space. | | The | contractor | is | to | provide | proper | foot‐candle | levels, | adequate | power | outlets, | and | heaters | that | are | required | for | the |
| service | and | maintenance | work. | The | contractor | will | also | provide | temporary | fencing | around | the | temporary | equipment | space | for | | | |
| security | and | hazard | requirement. | | | | | | | | | | | | | | | | |
| 81) | | Question: | | Please | provide | specifications | and | clarify | water | line | heat | tracing | requirements/scopes | of | work | associated | with | | | |
| the | temporary | chillers | and | the | new | cooling | towers. | | Is | the | heat | trace | to | be | controlled | with | individual | thermostats | or | one |
| common | heat | trace | controller? | | Are | any | alarms | or | monitoring | of | heat | trace | by | BAS | required? | | | | | |
| Answer: | | Heat | trace | for | the | piping | on | the | permanent | cooling | towers | may | be | any | commercially | available, | industrial | grade, | self‐ | | |
| regulating, | heating | cable | product | designed | to | provide | freeze | protection | to | metallic | piping. | | In | this | type | of | product, | the | heat | | |
| output | of | the | cable | varies | in | response | to | the | surrounding | conditions | along | the | entire | length | of | circuit. | | Whenever | the | heat | loss |
| of | the | insulated | pipe | increases | (as | ambient | temperature | drops), | the | heat | output | of | the | cable | increases. | | Conversely, | when | the | | |
| heat | loss | decreases | (as | the | ambient | temperature | rises | or | product | flows), | the | cable | reacts | by | reducing | its | heat | output. | | The | |
| manufacturer’s | recommended | method | of | control | is | to | be | used. | | No | monitoring | by | the | Building | Automation | System | (BAS) | is | | | |
required.
| 82) | Question: | | Please | clarify | where | and | how | the | new | electrical | panels | associated | with | the | temporary | chillers | are | to | be |
| installed. | Will | new | concrete | equipment | pads | be | required? | | Are | they | to | be | installed | on | freestanding | unit | strut | racks? | |
| Answer: | | New | concrete | equipment | pads | are | not | required | for | the | temporary | chillers. | | A | portable | equipment | pad | is | suitable. |
| Freestanding | unit | strut | racks | to | mount | temporary | panels | and | a | step | down | transformer | are | a | possible | solution. | | | |
| 83) | | Question: | | Please | provide | more | detail | and | clarification | for | branch | circuit | conductors | from | the | I‐Line | Panel | to | the | | | | |
| temporary | chillers. | | Note | 4 | on | Drawing | ZDV‐1401893‐Z141 | says | these | are | to | be | by | the | temporary | chiller | provider. | | Are | these | | | |
| conductors | to | be | installed | in | conduit? | | Can | they | just | be | temporary | cables | bundled | together? | | How | are | they | to | be | routed | to | the |
| I‐Line | Panels | laying | on | the | ground? | | | | | | | | | | | | | | | | | | |
| Answer: | | Conductors | from | the | I‐Line | Panel | to | the | temporary | chillers | are | be | installed | in | conduit | (EMT | for | temporary | is | okay). |
| The | temporary | conduits | routed | to | the | I‐Line | panel | are | to | be | elevated | off | the | ground, | not | laying | on | the | ground. | |
84) Question: Will a light fixture schedule be provided?
| Answer: | | The | light | fixture | schedule | has | been | provided | in | Drawing | E601. | | It | provides | a | description | and | known | acceptable |
| manufacturer | and | model | number, | but | contractor | can | provide | equal | product | subject | to | approval. | | | | | | | |
| 85) | | Question: | Will | the | VFDs | be | supplied | from | the | respective | equipment | manufacturers | or | will | they | be | part | of | the | electrical |
| contractor’s | gear? | | | | | | | | | | | | | | | | | | | |
| Answer: | | Contractor | will | supply | the | VFDs | for | the | cooling | tower | fans | and | pumps | to | meet | specification | requirement. | Chiller |
| manufacturer | will | supply | the | VFDs | to | meet | new | chiller | system | requirement. | | | | | | | | |
| 86) | | Questions | regarding | chiller | specifications | (section | 23 | 64 | 16). | | My | assumption | is | that | someone | worked | with | Trane | on | the |
| chiller | selection | and | most | of | these | questions | will | be | easy | to | answer | (if | the | specs | were | written | based | on | Trane | specs): |
| a) | Question: | | Seismic | – | do | you | require | OSHPD | certification? | | I | want | to | make | sure | that | I | do | not | provide | a | unit | that | is |
| overkill | in | regards | to | seismic. | | In | my | experience, | neoprene | isolators | will | suffice | but | I | don’t | want | to | assume | that | in | case | | | |
| I | am | missing | something | within | ASCE/SEI | 7. | | | | | | | | | | | | | | | | | | |
Answer: Neoprene mounts are sufficient.
| b) | | Question: | Coordinating | witness | test. | Who | would | be | the | individual(s) | that | will | witness | the | test? | Can | we |
| coordinate | with | them? | | | | | | | | | | | | | | | |
| Answer: | | Contracting | Officer’s | Representative | (COR), | Project | Engineer | (PE), | FAA | site | personnel, | etc. | Yes, | you | will |
| coordinate | through | the | COR. | | | | | | | | | | | | |
c) Question: Would a refrigerant‐cooled VFD be acceptable or is air‐cooled the only allowable option?
| Answer: | | The | preferred | method | is | air‐cooled. | | The | concern | would | be | if | refrigerant | cooling | is | used, | and | the | | |
| temperature | is | below | DP, | we | could | condense. | If | this | is | not | the | case | it | would | be | a | valid | method | of | cooling. |
d) Question: Does this unit need to ship knockdown or would knockdown in the field be acceptable?
Answer: Either way is acceptable as long as it meets manufacturer recommendations.
| 87) | | I | am | reviewing | the | drawings | and | just | noticed | that | the | structural | drawings | do | not | show | a | new | catwalk | system | with | | |
| associated | footings | if | required. | | There’s | a | small | set | of | stairs | at | the | end | of | the | cooling | towers | (sheet | S104) | but | it | doesn’t | appear |
| to | give | access | to | all | of | the | cooling | towers. | | Should | there | be | a | new | catwalk | platform | included | in | this | project? | | | |
Answer: No catwalk at the top of the cooling towers. Just the platform below all the cooling towers.
88) Chiller rental questions:
a) Question: What is the length of electrical run for each unit? To be provided by Trane rental service?
| Answer: | Refer | to | Drawing | Z101, | estimated | at | approximately | 100 | ft. | Yes, | to | be | provided | by | rental | service. |
| _____________________________________________________________________________________________________________ | | | | | | | | | | | | | | | | |
b) Question: What is the length of hose runs for each unit? To be provided by Trane rental service or is hard‐piping required?
| Answer: | Hard‐piping | is | required. | Refer | to | Drawing | Z101. | |
| | | | | | | | ____________________________________________________________________________________________________________ |
c) Question: Would Trane provide startup/training of rental equipment?
Answer: Yes, startup/training of rental equipment is required.
| 89) | | Question: | | Will | any | manufacturer | be | accepted | other | than | those | listed | in | the | project | specification | document? | For | example, |
| is | there | any | other | chiller | manufacturer | that | would | be | accepted | other | than | Trane? | | | | | | | |
| Answer: | | The | FAA’s | requirement | is | for | TRANE | chillers | only. | | The | facility | has | a | total | of | four | (4) | chillers | and | only | two | (2) | are |
| being | replaced. | | The | FAA | is | requiring | the | same | manufacturer | for | the | new | chillers | for | consistency | and | standardization. | | | | | | | |
| 90) | | Question: | | With | regards | to | this | project, | would | an | alternate | controls | system | be | accepted? | | Specifically | Siemens | Talon |
| Controls | which | is | an | open | “Tridium” | based | system | that | would | be | an | equal | to | the | current | specified | system. | | |
| Answer: | | No | alternate | controls | systems | will | be | accepted/approved | for | this | project. | The | FAA | is | utilizing | Schneider | Electric |
| controls | in | all | its | ARTCC | facilities | for | consistency | and | standardization. | | | | | | | | |
92) Question: Where is FAA Order 6000.50E as per Section 011000 1.4.A.4.a.iv located? Please provide.
Answer: See attachment “Question 92 – FAA Order 6000.50E”.
93) Question: Is this project one that mechanical contractors are permitted to bid as the prime contractor?
Answer: Any contractor may submit an offer as the prime contractor.
| 94) | | Question: | | At | the | site | visit, | it | was | mentioned | that | the | sign | in | sheets | would | be | made | available | to | attendees. | Can | this | be |
| posted | to | the | website? | | | | | | | | | | | | | | | | | | | | | |
Answer: The site visit attendee list will be provided to whomever requests a copy. Email requests to cindi.tjelde@faa.gov.
| 95) | | Question: | | Will | the | FAA | provide | any | and | all | requested | information | or | paperwork | as | needed | to | obtain | sales | tax | exemption |
| with | the | State | of | Colorado? | | | | | | | | | | | | | | | | | |
| Answer: | | No. | | The | FAA, | as | the | federal | government, | is | tax | exempt. | | The | awardee | contractor | is | responsible | for | any | and | all | local, |
| state, | and/or | federal | taxes, | as | stated | in | Section | B | of | the | RFO: | | “The | offered | price | must | encompass | all | costs | related | to……(b) | | |
| federal, | state, | and | local | taxes”. | | | | | | | | | | | | | | | | | | | |
| 96) | | Question: | | Per | the | RFO, | we | are | allowed | 75 | pages | max | for | the | technical | proposal. | Does | that | include | cover | page, | table | of |
| contents, | resumes, | page | breaks? | | | | | | | | | | | | | | | | | | | | |
Answer: Yes, the entire technical proposal.
| 697DCK-18-R-00406 Amend 0002 |
| Questions and Answers |