This is a Specifications document for a building refurbishment project at the HTI ARSR facility in Hutchinson, Kansas under FAA solicitation 6973GH-26-R-00147. The Federal Aviation Administration seeks a contractor to provide comprehensive refurbishment services including all labor, materials, equipment, transportation, insurance, notifications, licenses, permits, and supervision necessary to complete the work. The contract is anticipated to be awarded on a firm-fixed-price basis. Proposals must be submitted via email to Rikki Pickel at RIKKI.D-CTR.PICKEL@FAA.GOV no later than 5:00 p.m. CT on September 11, 2026, with the solicitation number included in the subject line. All questions regarding the project scope, work plans, and specifications must be submitted in writing by 5:00 p.m. CT on September 4, 2026.
Contractors must be registered with the System for Award Management (SAM.gov) by the September 11, 2026 proposal deadline, as unregistered offerors may be rejected in favor of the next otherwise successful registered offeror. Site visit instructions are provided in the solicitation information request (SIR) Section L, 3.2.2.3-63. Offerors are required to complete and return all attached forms by the closing date. The FAA reserves the right to review and verify each offeror's program eligibility. The contract is governed by the FAA's Acquisition Management System (AMS) rather than the Federal Acquisition Regulation (FAR).
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL AVIATION ADMINISTRATION
CENTRAL SERVICE AREA
ENGINEERING SERVICES AJW-2C18D
FORT WORTH, TEXAS
PROJECT SPECIFICATIONS
Refurbish Exterior of ARSR Building and Upgrades
JCN 23002285
HTI ARSR, Hutchinson, KS Coordinates:
37.922847, -97.887799
FOR OFFICIAL USE ONLY
Property of the United States Government Copying, Dissemination or Distribution of These Documents to Unauthorized Personnel is Prohibited
Public availability to be determined under 5 USC 552
HTI-ARSR-22002285
HUTCHINSON, KANSAS
FOR OFFICIAL USE ONLY TABLE OF CONTENTS
00 02 00 - 1
TABLE OF CONTENTS
Div./Section Title
DIVISION 1 – GENERAL REQUIREMENTS
SECTION 01 11 00 SUMMARY OF WORK
SECTION 01 31 13 PROJECT COORDINATION
SECTION 01 32 00 CONSTRUCTION PROJECT DOCUMENTATION
SECTION 01 33 00 SUBMITTAL PROCEDURES
SECTION 01 45 00 QUALITY CONTROL
SECTION 01 56 00 DUST CONTROL
SECTION 01 63 00 SUBSTITUTION AND PRODUCT OPTIONS
SECTION 01 71 00 CLEANING
SECTION 01 73 00 EXECUTION
SECTION 01 77 00 CLOSEOUT PROCEDURES
SECTION 01 78 10 PROJECT RECORD DOCUMENTS
DIVISION 2 – EXISTING CONDITIONS
SECTION 02 41 00 DEMOLITION
SECTION 02 41 19 SELECTIVE DEMOLITION AND DUST CONTROL
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
SECTION 07 42 13 METAL WALL PANELS
SECTION 07 92 00 JOINT SEALANTS
DIVISION 9 – FINISHES
SECTION 09 90 00 PAINTING AND COATINGS
DIVISION 26 - ELECTRICAL
SECTION 26 05 00 BASIC ELECTRICAL MATERIALS AND METHODS
SECTION 26 05 05 SELECTIVE DEMOLITION FOR ELECTRICAL
SECTION 26 05 19 LOW VOLTAGE CABLES
SECTION 26 05 23 CONTROL-VOLTAGE ELECTRICAL POWER CABLES
SECTION 26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
SECTION 26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
SECTION 26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
SECTION 26 05 53 IDENTIFICATION OF ELECTRICAL SYSTEMS
SECTION 26 08 00 TESTING AND INSPECTING ELECTRICAL EQUIPMENT
SECTION 26 24 16 PANELBOARDS
SECTION 26 27 26 LOW VOLTAGE WIRING DEVICES
SECTION 26 41 13 LIGHTNING PROTECTION FOR STRUCTURES
DIVISION 32 – SECURITY FENCE AND GATES
SECTION 32 31 00 HEAVY DUTY CANTILEVER SLIDE GATE SYSTEM (CHAIN LINK)
SECTION 32 31 13 CHAIN LINK FENCE AND GATE
ATTACHMENTS – HAZMAT ABATEMENT SOW
--END OF SECTION--
FOR OFFICIAL USE ONLY
SUMMARY OF WORK
01 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 - GENERAL
1.1 Summary
A. The Following specifications and advisements constitute the working portion of the contract between the contractor and the Federal Aviation Administration, an Agency of the United States Government. The Contracting Officer assigned to this contract shall be the only individual with authority to speak for and contractually bind the FAA. All communications, authorizations, approvals, changes, modifications, etc., involving this contract shall be through the Contracting Officer. Any action not approved by the Contracting Officer shall not bind the FAA.
Contracting Officers Technical Representative (COTR):The Contracting Officer (CO) may assign a COTR to oversee the work on the project and act as a technical point of contact. A letter dating the COTR's responsibilities and authority will be issued when a COTR is assigned.
B. Unless otherwise specified, contractor shall provide labor, materials and equipment necessary to fully meet all requirements of this Summary of Work, Construction Specifications, Construction Drawings and all other Contract Documents related to and/or titled: HTI ARSR JCN 22002285 “Refurbish Exterior of ARSR Building and Upgrades”
C. This Section includes the following:
1. Work covered by the Contract Documents.
2. Use of premises.
3. Work restrictions.
1.2 Work covered by contract documents
A. Project Identification: JCN 22002285 HTI ARSR, refurbish exterior structure, close unused openings, reseal exterior and re-paint, Hutchinson, KS.
B. FAA's Representative: FAA Resident Engineer/Contracting Officers Representative (RE/COR)
a. All work performed and all materials and equipment used are subject to approval by the “Contracting Officer and/or Resident Engineer/Contracting Officer’s Representative (RE/COR)”.
C. Contractor shall perform a subsurface utility search prior to any digging. All cables, piping, and utilities in the work area must be located using ground penetrating radar (GPR) method. The recommended method of trench digging is hydrovac excavation if cables are within 3 feet. Any damage above or below ground shall be repaired at no additional cost to the FAA. Coordinate with the local FAA personnel and contact the Kansas DIG (811) or 800-344-7233 before start of work/excavation to get the site cabling/utilities marked.
Utilities must be located at minimum five days in advance of trenching.
D. Contractor shall review and sign environment assessment forms with the RE prior the beginning of and during the work.
E. Manifest of debris must be supplied to the RE
F. Designers: Engineering Services, AJW-2C18D and Kansas Licensed Professional Engineer (PE) hired by the Contractor (refer to drawing notes)
G. The Scope of Work in this package includes:
1. ELECTRICAL
Contractor shall selectively demolish, remove, and replace the following equipment/items (Protect existing structures in place to remain around the item being demolished. Preserve breaker control wiring
01 11 00 - 2 to be re-used with new breakers to re-integrated with the existing system). System phase rotation must be field verified and noted before and after any electrical connection:
1.1. Demolish existing MDPE-1 feeder, current E/G panel feeder and gate power circuit back to their corresponding power sources. Selectively demolish MDP feeder by preserving junction boxes on the current E/G building wall to be re-used to reroute the feed to MDPE1 on the ARSR building first floor.
1.2. Remove and replace the 600A MDPE1 panel on the first floor of the ARSR building with an 800A panel. The new panel shall include new breakers, enclosure, and doors as specified in the drawing set. Protect and preserve branch circuits to be re-connected on the new panel. Damaged conductors shall be replaced with new conductors for the entire length without splices.
1.3. Reroute the ATS feed on the outside of the new E/G building currently going to the MDP panel in the old E/G building, to the new 800 Amp MDPE1 panel in the ARSR building. Provide new conductors, conduits and trenching to reach MDPE1. Resurface new trenched area to match existing pavement.
1.4. Reroute EDPE1 feed from MDP to the new MDPE1 panel. Field verify existing conductors, and conduits for adjustment to match the new set up.
1.5. Reroute panel E/G feed from MDP to tap from existing ATS. Field verify the length of the new feed to comply with NEC tap rules. Install a new 200Amps fused at 150 amps E/G panel disconnect switch between the ATS and the E/G panel. The disconnect switch shall be installed as close as practical to the ATS. Provide a new 60 Amp breaker with a new surge protection device (SPD) for the E/G panel.
1.6. Remove and replace gate power circuit from the old E/G building panel to the current E/G panel.
Provide a new 20 Amp circuit breaker for the gate circuit, conductors, and conduit. Resurface trenched area to match existing pavement.
1.7. Remove and replace service entrance SPD located in the E/G building above the service entrance disconnect switch.
1.8. Provide arc flash analysis per NFPA-70E and IEEE-1584. Contractor shall be responsible to perform a short circuit analysis, protective device coordination study, and arc flash hazard analysis for the entire site. Contractor shall provide arc flash labels on all panels and safety disconnects.
Work shall be performed in accordance with the current FAA order 6950.27 and FAA order 3900.64 latest editions. Once the report has been approved by the FAA, provide project data files for the model in a compatible format for use with SKM power tools for windows.
1.9. The contractor shall provide grounding for the newly installed panelboards in accordance with
(IAW) the latest edition of FAA-STD-019.
1.10. Trace, label, and correct any improper wiring for all equipment affected by this scope of work.
Labels must be shrunk embossed. Panels must have updated panel schedules. All circuits must be traced and properly labeled in panel schedules. Any improper color coding of phase conductors must be corrected.
01 11 00 - 3
2. DEMOLITION
2.1. Demolish west side ladder from level 1 to level 4
2.2. Demolish all unused vents, windows & any other penetrations as described in the drawings.
2.3. Demolish security fence and gates. Coordinate demolition work to ensure only perimeter fence or gates that can be replaced by new fence or gates during the same workday.
3. PAINTING AND SEALANTS
3.1. Remove all existing sealants, coat galvanized surfaces, loose paint and rust with rust grip by superior products international.
3.2. Reseal, prime and paint exterior parts of the building and the radome catwalk for the entire exterior building.
3.3. Remove and replace two windows on the first floor with new non-operable burglar proof windows.
3.4. Install new door stripping and repaint doors leading to building exterior as described in the drawings.
4. NEW SIDING AND INSULATION
4.1. Contractor to hire Kansas licensed professional engineer to design the new siding attached to the existing structure with grounding
4.2. Provide new Kynar finished horizontal metal wall panels and matching trims to cover the entire existing exterior siding with sub-girts for panel support
4.3. Provide new inside insulation where hoods, vents and all penetrations have been removed
5. PERIMETER FENCE AND GATES
5.1. Replace the entire perimeter fence and gates with new FAA compliant fence and gates. Ensure the new fence extends over the electrical utility pole.
5.2. Furnish and install grounding for the new security fence IAW FAA-STD-19 latest edition.
5.3. Furnish and install FAA warning signage around the fence as indicated in the drawings.
6. OTHER MISCELLANEOUS
6.1. Furnish and install door latch guards for the radar building.
6.2. Furnish and install door signs (Entrance into the building: No weapons & Notice of inspection door signs, 2nd and 3rd floor landings: Critical Area door signs).
H. Drawing Convention – All drawings dimensions, equipment, utility piping/cabling, and location presented on the drawing are for informational purposes only and must be field verified by the Contractor.
I. Omissions from the drawings or specifications or the misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work, but shall be performed as if fully and correctly set forth and described in the drawings and specifications.
J. Where conflicts between the drawings and specifications occur, specifications shall govern in accordance with FAR 52.236-21.
K. The contractor is responsible for accomplishing all items of work in accordance with the applicable drawings, specifications, and conditions of the contract. Any additional labor, materials, equipment, and/or appurtenances not specifically detailed or specified, but required to complete the project, must be provided by the contractor as an integral part of the scope of work specified.
01 11 00 - 4
1.3 Type of Contract
A. Project will be constructed under a single prime contract.
B. All potential bidders shall perform a field inspection of the site prior to bid submission to inform themselves of the specific working conditions applicable at the site and to ascertain the correct types/amounts of work to be performed. Bidders shall examine the site location, and haul route to determine appropriate methods, tools, and equipment for performance of this scope of work. It is the contractor’s responsibility to familiarize themselves with the latest edition of the FAA-STD-019 and advisory circular 150/5210-20; these documents can be provided upon request. If the bidder chooses not to visit the site, they will nevertheless be charged with knowledge of conditions, which a reasonable inspection would have disclosed. Work defined in this scope must not exceed 60 working days. The coordinates of the HTI ARSR in LAT/LON decimal degrees are 37.92285 / -97.8878 . A site visit for prospective bidders will be scheduled by the Contracting Officer (CO) prior to the bid due date. Request for inspections shall be made to Michael Harman, Wichita SSC Manager at (316)-941-1267.
1.4 Work Phases
A. The Work will be conducted in one (1) phase:
1. Phase one: The facility will not be operational during construction activities affecting the electrical main power distribution system. This will be coordinated with the FAA and Wichita SSC management.
All work per the construction document must be conducted in 1 phase and substantially complete and ready for occupancy within 30 calendar days after the Notice to Proceed. Any shutdowns need to be coordinated with the FAA, FAA will need a minimum of 45 days for shutdown that last more than 24 hours and any shutdowns that are consecutive days of over 4 hours per day will need to go through the shutdown committee.
2. Normal work hours are 7:00 am to 3:30 pm Monday through Friday. It is required that any work be done with extreme care, and that all work be done in a manner that does not interfere with FAA operations, or the duties of the AT Controllers, Airways Facilities or Administrative personnel of the FAA. Any late-night work may require that the following day be an off day for work.
1.5 Protection:
A. Upon beginning work on the existing facility, Contractor shall protect existing buildings, equipment, pavement, sidewalks, fencing, gates, and landscaping as required.
B. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
C. Repair or replace portions of existing work, which have been altered during construction operations to match existing or adjoining work, as approved by the Project Engineer and/or Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
D. Contractor shall protect all Government property against damage, to include but not limited to dust, fumes, impact, scratching, water, paint, joint compound, power failure, power surges, weather, heavy equipment, et cetera. Especially protect sensitive equipment from dust or damage, see Section 01 56 00. All damages caused by the Contractor, whether to equipment, furniture, roads, landscaping, building components or any other type of Government property encountered at or near the project site shall be repaired or replaced to match existing to the satisfaction of the RE/COR at no cost to the Government.
1.6 Use of premises
01 11 00 - 5
A. General: Contractor shall have limited and restricted use of the premises for construction operations as indicated by RE/COR in coordination with facility operations personnel. Any potential impacts are to be brought to the attention of the RE/COR immediately.
1.7 Owner's occupancy requirements
A. Full FAA Access: FAA will provide Contractor access to the site and building during entire construction period. Cooperate with FAA during construction operations to minimize conflicts and facilitate FAA usage.
Perform the Work so as not to interfere with FAA's day-to-day operations. Maintain existing exits, unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from FAA and authorities having jurisdiction.
2. Provide not less than 72 hours advance notice in writing to RE/COR of activities that will affect FAA's operations.
1.8 Work restrictions
A. Contractor shall complete this project, including final clean-up of the premises and storage and equipment areas within the duration approved in the contract schedule. This shall include operational testing of new exhaust fans and controls systems.
B. Work Hours:
1. Regular Work Hours: Monday through Friday from 07:00 to 16:00 hours. Notify the RE/COR 48 hours in advance of any changes in work hours, shift changes, or anticipated overtime work.
2. Holiday Work Hours: The Contractor shall observe all federal holidays and weekends. No work shall be planned for these days unless approved in writing by the Contracting Officer.
3. No Work Moratoriums: There shall be no work done during the FAA Moratoriums unless a waiver has been granted. Coordinate with local SSC, RE/COR for dates/times of moratoriums.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by FAA or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify the RE/COR 72 Hours prior to proposed utility interruptions or outage.
2. Do not proceed with utility interruptions without the RE/COR written permission.
1.9 Security requirements
A. Site Access and Security: Access to the site shall be determined by the RE/COR through coordination with SSC personnel and will be given to the Contractor at the Pre-Construction Meeting. The Contractor shall maintain the security integrity. SSC personnel with the required security clearance are required to escort the RE/COR and Contractor personnel for access inside of the ARSR building.
B. Personnel list: Contractor shall provide the facility FAA SSC and RE/COR with a list of contractors personnel who will require access to the site. The list shall be kept current during project work.
C. Security investigation: Contractor’s personnel may have a security investigation by the FAA. Upon request by the RE/COR, the contractor shall promptly complete all security forms provided the by RE/COR.
D. Weather Delay: The Contractor shall obtain the approval of the RE/COR each day prior to beginning the next day’s work activity. The RE/COR may suspend all work activity in the event that outdoor weather conditions pose a threat of damage to the site work, the equipment or the building.
01 11 00 - 6
E. Construction Safety: The Contractor is responsible for providing a safe work environment for all construction and inspection personal working on site. The Contractor shall follow all national, state, and local safety procedures mandated by FAA, OSHA, law, and local ordinance.
F. Right to search: Current procedures at FAA facilities include the “right to search.” If in the judgment of the
FAA, a reason to search a vehicle or person exists, such search will be made.
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 Submittals Required for Notice to Proceed
A. Start of project work cannot occur until the Contractor has been provided with a written NTP from the CO.
Submittals required for NTP must be submitted to the PEL prior to the Pre-Construction Meeting. Work cannot commence until interim or final approval is provided for submittals required for NTP. Payment and Performance Bonds (if required) and Certificates of Insurance must be submitted to the CO. The CO will advise the Contractor if bonds or insurance submittals are not acceptable.
B. Submittals required for NTP are discussed in this section as well as other sections of the General
Requirements (Division 1) and Contract. Required submittals of NTP include:
1. Payment and Performance Bonds are required.
2. Project Specific Insurance Requirements.
3. Construction material specifications
4. Construction equipment on site
5. Risk Management Plan
6. Construction Progress Schedule
7. Schedule of Values
8. Submittal Schedule
9. List of Lower tier subcontractors, Suppliers, and Fabricators
10. Initial List of personnel working On-Site
11. List of contractor Staff Assignments and Project Organization Chart
12. Excavation plans
Note: Approval of submittals does not relieve the contractor the responsibility to meet applicable industry standards, codes, installation methods, quality, fit and finishes unless the contractor has specifically called those out in writing.
FOR OFFICIAL USE ONLY HTI-ARSR-22002285
PROJECT COORDINATION
01 31 13 - 1
SECTION 01 31 13
PROJECT COORDINATION
PART 1 GENERAL
1.1 Summary
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Coordination.
2. Submittals.
3. Administrative and supervisory personnel.
4. Project meetings.
5. Requests for Interpretation (RFIs).
1.2 Definitions
A. RFI: Request from Contractor seeking interpretation or clarification of the Contract Documents.
1.3 Coordination
A. Coordination: Coordinate construction operations included in different Sections of the
Specifications to ensure efficient and orderly installation of each part of the Work.
1. Schedule construction operations in sequence are required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.
C. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials.
1. Salvage materials and equipment involved in performance of, but not actually incorporated into, the Work. All salvaged materials shall be placed in a designated area for review by the RE/COR prior to disposal.
1.4 Project meetings
A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.
1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date, time and location of each meeting. Notify the FAA Contracting Officer (CO), RE/COR, Project Engineer, and subcontractors of dates, times and location of the meeting.
B. Pre-construction Conference: A pre-construction conference will be held before starting construction. Location and time designated by FAA. The meeting will review responsibilities and personnel assignments.
01 31 13 - 2
1. Attendees: Contracting Officer, Project Engineer, RE/COR, FAA SSCM and other authorized representatives of the FAA, Contractor and his superintendent; major subcontractors;
suppliers; and other concerned parties shall attend the conference. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Discuss items of significance that could affect progress, including the following:
a. Sign in sheet.
b. Tentative overall construction schedule.
c. Designation of key personnel and their duties.
d. Procedures for processing field decisions and Change Orders.
e. Procedures for RFIs.
f. Submittal procedures. (Submittal Log & Numbering)
g. Preparation of Record Documents. (Maintain Red Line drawings for immediate review)
h. Use of the premises and existing facility.
i. Work restrictions.
j. Owner's occupancy requirements.
k. Responsibility for temporary facilities and controls.
l. Parking availability and location.
m. Equipment deliveries and priorities.
n. Security.
o. Progress cleaning.
p. Working hours.
q. Safety Management System (SMS).
r. Lay down area for Contractor temporary office facilities, any trailers and staging area.
(utilize open space on site as directed by RE/COR)
s. Notice to Proceed Letter (NTP) by Contracting Officer.
t. Final clean up and punch list.
u. Letter designating RE/COR by Contracting Officer.
v. Schedule of Values.
w. Review Form 3900-18, FAA Pre-Construction and Maintenance Project Safety and
Health Checklist. Form 3900-18 at end of Section 01 31 00.
3. Minutes: Record and distribute meeting minutes.
C. Progress Meetings:
Review progress since the last meeting. Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to the approved Contractor's Construction Schedule.
Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
a. Review present and future needs of each entity present, including the following:
tatus of submittals.
2) Deliveries.
3) Access.
4) Site utilization.
5) Work hours.
6) Hazards and risks including any proposed utility outages or cutovers.
7) Progress cleaning.
8) Quality and work standards.
9) Status of correction of deficient items.
10) Field observations.
11) RFIs.
01 31 13 - 3
12) Status of proposal requests.
13) Pending changes.
14) Status of Change Orders. (Maintain change order log with status)
15) Pending claims and disputes.
1.5 Requests for interpretation (RFIS).
A. Procedure: Immediately on discovery of the need for interpretation of the Contract Documents, prepare and submit all RFI’s in the form specified.
1. RFIs shall originate with Contractor. RFIs submitted by entities other than Contractor will be returned with no response.
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.
B. Hard-Copy RFIs:
1. Identify each page of attachments with the RFI number and sequential page number.
C. FAA's Action: The CO will review each RFI, determine action required, and return it. Allow five (5) working days for the CO's response for each RFI. RFIs received after 1:00 p.m. will be considered as received the following working day.
1. The following RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for coordination information already indicated in the Contract Documents.
d. Requests for adjustments in the Contract Time or the Contract Sum.
e. Requests for interpretation of the engineering's actions on submittals.
f. Incomplete RFIs or RFIs with numerous errors.
2. CO's action may include a request for additional information.
D. On receipt of the CO's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify the CO within three (3) working days if Contractor disagrees with response.
E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.
Submit log at each updated meeting.
END OF SECTION 01 31 00
SUBMITTAL PROCEDURES
01 33 00 - 1
SECTION 01 33 00
PART 1 – GENERAL
1.1 SUBMITTALS
A. Catalog cut sheets, brochures, shop drawings and/or samples shall be clearly marked/indicated by the Contractor and submitted to the Project Engineer for the items on the schedule, drawings and other sections of the specifications.
B. All salient features of materials required to be submitted shall be easily found in the submittal package for each item and not require research on the part of the Government to determine compliance with Contract requirements.
C. Related items such as mechanical/electrical components shall be submitted at one time for coordination purposes.
D. Color coordinated items such as paint, vinyl composition tile, and so forth shall be submitted at one time to facilitate color comparison/selection by the RE/COR. Different categories of submittal items are not to be grouped on the same form.
E. All related submittals have to be submitted all together in one package. Submit the following items for approval after contract award.
1. Paint manufacturer’s technical data sheet including instructions for its applications and use of the interior/exterior primer and interior/exterior paint.
2. Construction schedule/sequence of work. The schedule shall be arranged in chronical order.
3. Letter of certification to certify that only lead-free paint is to be/was used.
4. Name and number of persons on site shall be submitted to RE/COR before the starting date.
F. All items shall be approved by the Project Engineer prior to purchase, delivery or installation.
G. All items shall be submitted electronically in pdf format not more than twenty (20) calendar days after Contractor's notification that they can proceed with construction. Samples of all items requiring color selection shall be submitted along with the electronic submittal. Operations and Maintenance (O&M) manuals shall be submitted for approval by the RE/COR, prior to final inspection.
H. Not less than ten (10) business days shall be allowed for review of submittals by the Government.
I. Submittals will be returned to the Contractor unless otherwise specified. A sample of all items requiring color selection will be retained by the Contracting Officer’s Representative for reference.
J. Refer to Section 01 63 00 - Substitutions and Product Options.
1.2 OPERATION AND MAINTENANCE MANUALS
A. The Contractor shall furnish three (3) copies, one (1) hard copy and two (2) CD ROM, of all operation and maintenance (O&M) manuals. O&M manuals shall contain complete instructions for the operation, inspection, testing and maintenance of the system, and shall include complete parts breakdown diagrams.
Manuals shall also contain complete wiring schematics and diagrams. Manuals shall be in booklet form with binder and shall be arranged in logical sections for easy reference.
1. MATERIAL SAFETY DATA SHEET (MSDS)/SAFETY DATA SHEET (SDS) SUBMITTALS
a. All submittals for products shall include the MSDS/SDS when an MSDS/SDS is required by law for that product.
01 33 00 - 2
b. MSDS/SDS’s shall also be submitted on FAA “Approval-Disapproval form of Contract Materials” for all products to be used during the course of the project, not otherwise requiring a submittal, but which may be of a toxic, hazardous, flammable or otherwise dangerous nature.
c. Approval by the RE/COR is required before bringing the materials on site. All hazardous waste shall be disposed of per all local, state and federal regulations.
--END OF SECTION—
QUALITY CONTROL
01 45 00 - 1
SECTION 01 45 00
PART 1 - GENERAL
1.1 WORKMANSHIP
All materials and equipment shall be installed in a manner accepted by standard trade practice. Workmen skilled in the type of work required shall accomplish the installation.
1.2 TRAFFIC SAFETY
Special efforts shall be made not to interfere with traffic flow or create safety hazards to traffic.
1.3 ENVIRONMENTAL MANAGEMENT SYSTEM
Environmental Management System (EMS) is an ISO 14,001 tool used to identify and mitigate threats to our environment. Ultimate goal is to protect our environment (work environment and the natural environment) while accomplishing our mission. All Contractors working on FAA projects are expected to acknowledge their role in EMS while completing their mission.
Threats associated with construction sites include, but are not limited to: hazardous materials, spills, equipment leaks, air-born dust, soil erosion, track- out, and lack of recycling. This will be communicated and documented initially for each project with monthly updates provided to the FAA Contracting Officer’s Representative.
1.4 DEBRIS DISPOSAL
A. Debris shall be removed from the project site promptly, and as feasible, all equipment and materials shall be removed or secured at the end of each day. The Contractor is responsible for the daily cleanup of all construction areas and construction debris that has escaped from the construction site.
B. The Contractor shall exercise caution in not disturbing adjacent facilities, finishes, materials, grounds and other items not a part of this project. The Contractor shall clean daily all areas outside the project area of dirt, dust, and debris generated by this contract.
C. The Contractor shall use designated haul routes for both delivery and removals. Haul routes are noted on the drawings.
D. All debris generated by the contract shall be properly disposed of by the Contractor off the project site. Removal of debris and other material shall be handled, transported, stored, and disposed of by the Contractor and his sub-contractors in accordance with all applicable federal, state or local laws, ordinances, regulations, court orders or other types of rules or rulings having the effect of laws.
These restrictions shall apply both on and off FAA facilities.
E. The Contractor shall submit with the regular progress reports a Government supplied Contractor
Construction and Demolition Debris Report. This form lists the amount of materials disposed at a landfill, recycled or otherwise reused. This submittal is required before progress payments can be made and also applies to any debris by sub-contractors.
F. The Contractor shall take all precautions to prevent spillage of materials from Contractor vehicles on
FAA facility pavements. The Contractor shall provide adequate labor and equipment to keep paved areas free of debris, and to contain loose materials at all times.
1.5 RECYCLING MATERIALS
A. All removed ceiling tile shall be recycled and the Contractor shall provide written certification that the ceiling was not placed in a landfill. Contractor certification shall indicate how the material was recycled and provide the address where it was delivered.
1.6 CULTURAL RESOURCE MANAGEMENT
For the protection of cultural, historic and prehistoric resources, the Contractor shall submit a signed
01 45 00 - 2 certification that the selected land borrow area is free of all materials of this type. This includes anything of an archeological nature as well as any Native American sites to include tribal burial grounds.
1.7 WARRANTY REQUIREMENTS
The Contractor shall provide a standard Warranty of Construction for all work associated with this contract in accordance with FAR Clause 52.246-21 and any other additional warranties outlined within this Statement of Work/Specifications.
1.8 FINAL INSPECTION AND ACCEPTANCE OF WORK
As construction nears completion, the Contracting Officer’s Representative and the Contractor's Quality Control representative and Superintendent shall thoroughly inspect the work and generate a deficiency (punch) list. When this list has been cleared, the Contractor shall request a preliminary inspection through the Contracting Officer; then the Contracting Officer’s Representative will schedule the preliminary inspection using Government specialists of the systems installed under the Contract.
When all deficiencies are corrected, the Contractor shall request a final inspection through the Contracting Officer, to be conducted by the Contracting Officer and Contracting Officer’s Representative. For phased work, this process may be repeated for each phase.
DUST CONTROL
01 56 00 - 1
SECTION 01 56 00
DUST CONTROL
PART 1 GENERAL
1.1 SUMMARY
A. The work covered by this section consists of furnishing all labor, materials and equipment and performing all work required for the control and prevention of fugitive dust during and as the result of construction operations under this contract. Except for those measures set forth in other Technical Provisions of these specifications.
For the purpose of this specification, fugitive dust entails the generation of solid particles by the forces of wind or machinery acting upon exposed materials. Provisions of this specification shall prevent fugitive dust from adversely affecting human health or welfare; unfavorably altering ecological balances of importance to human life; affecting other species of importance to man; or degrading the utility of the environment for aesthetic and recreational purposes.
B. Dust Control is a requirement in the EPA and state pollutants discharge elimination system or permit for discharging storm water during construction. Contain dust around all ARSR electronic equipment with PVC sheets suspended from the ceilings. Do not cover the equipment as that would cause the electronic equipment to overheat.
1.2 REFERENCES
A. The publications listed below form a part of this section to the extent referenced. The publications are referenced in the text by basic designation only.
1. FAA ORDER 3900.19 National Policy (latest version): Occupational Safety and Health Policy
1.3 SUBMITTALS
A. Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
1. SD-01 Preconstruction Submittals
2. Dust Control; G.
3. Products and Procedures; G
B. Prior to commencement of the work, submit in writing a proposal to the Contracting Officer for implementing the provisions of this section for fugitive dust control. Address the plans, and the products to be used, to prevent and control fugitive dust through specific mitigative and preventative measures.
The effectiveness of the dust control program shall be periodically checked and reviewed. Revisions to the dust control plan shall be submitted to the Contracting Officer as changes are necessary during the duration of this contract.
1. Material Safety Data Sheet; G.
2. Material Safety Data Sheets include those for soil stabilization products.
3. Sandblasting; G.
4. SD-02 Shop Drawings
C. Recordkeeping: Maintain and furnish records in accordance with PART 1 paragraph 1.7 recordkeeping.
1.4 IMPLEMENTATION MEETING
Prior to commencement of the work the Contractor shall meet with representatives of the Contracting Officer. In the Preconstruction Meeting will be an appropriate time to address dust control implementation. Develop a mutual understanding relative to compliance with these provisions and administration of the Contractor dust control measures.
1.5 APPLICABLE REGULATIONS
In order to prevent and to provide control of pollution arising from the construction activities of the Contractor and his subcontractors in the performance of this contract, all applicable Federal, State, and
01 56 00 - 2 local laws and regulations concerning environmental pollution control and abatement. And all applicable provisions of the FAA ORDER 3900.19C as well as the specific requirements stated in this section and elsewhere in the contract specifications. Compliance with the provisions of this section by subcontractors will be the responsibility of the Contractor.
1.6 NOTIFICATION OF NON-COMPLIANCE
The Contracting Officer will notify the Contractor in writing of any observed non-compliance with the foregoing provisions. The Contractor shall, after receipt of such notice, immediately take corrective action. Such notice, when delivered to the Contractor or his authorized representative at the site of the work, shall be deemed sufficient for the purpose. If the Contractor fails or refuses to promptly take corrective action, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such stop orders shall be made the subject of a claim for extension of time or for excess costs or damages by the Contractor unless it was later determined that the Contractor was in compliance.
1.7 RECORDKEEPING
The Contractor shall, at a minimum, maintain records indicating dust control measures taken.
Information provided shall be sufficient to answer any questions regarding control methods utilized, products used, application rates, inspections performed. Additional information to be recorded, but not limited to reporting, includes treated area, operator, date and time of treatment, meteorological conditions and inspection and monitoring reports. Records shall be submitted every 30 days to the Contracting Officer.
PART 2 PRODUCTS
2.1 PRODUCTS AND PROCEDURES
Products and procedures used in controlling particulates and dust shall be in accordance with the Contractor's Environmental Protection Plan and the dust control plan required by this Section. Material Safety Data Sheets for soil binders for use in dust control shall be approved prior to application. Soil binders containing carcinogenic substances (e.g. acrylamides) are prohibited.
3.1 DUST CONTROL
Control techniques for fugitive dust sources shall involve watering. For arid regions and dusty work areas, dust control shall include water application with soil binders that is environmentally sustainable and non-toxic. The methods utilized shall be cost effective, water conservation, and appropriate for the size and scope of the fugitive dust source. Methods and controls shall not have an adverse effects on plant and animal life, ecosystem, and facility air intakes, or contaminate the treated material.
Repeat methods at such intervals as to keep all parts of the disturbed area(s) treated at all times. Have sufficient competent equipment on the job to accomplish control techniques. Products shall provide a method to reduce dust-related environmental concerns and aid in complying with applicable regulations.
Products shall not in any form produce any adverse environmental effects through their use and shall provide an effective, clean, safe control of airborne dust and protection against soil erosion.
3.1.1 Preventative Techniques
The reduction of source extent, the incorporation of process modifications, or adjusted work practices, which reduce the amount of dust-generation, are preventative techniques for the control of fugitive dust emissions. These techniques include the elimination of mud and dirt carry-out onto paved roads at construction sites.
3.1.2 Mitigative Techniques
01 56 00 - 3
Mitigative measures entail the periodic removal of dust-producing material. Examples of mitigative control measures include clean-up of spillage on paved or unpaved travel surfaces and clean-up of material spillage at transfer points.
3.2 MATERIALS HANDLING
The Contractor shall take the following minimum precautions to limit fugitive dust emissions from material handling and transportation to achieve control of dust emissions to the extent practicable.
a. Transportation: At a minimum, complete covering, maintain a minimum 12 inch free-board space, and moistening of materials hauled from the construction site. Open truck beds, since they create airborne particulate matter, are prohibited. Additional application of water with approved soil binder shall be required if additional controls are considered necessary by the Contracting Officer.
3.3 CONSTRUCTION AND DEMOLITION
Control dust resulting from demolition and construction activities. No person may cause, suffer, allow, or permit a structure, road, street, alley, or parking area to be constructed, altered, repaired, or demolished, or land to be cleared without taking minimum precautions to achieve control of dust emissions.
3.3.1 Demolition
Control the amount of dust resulting from demolition to prevent the spread of dust to occupied portions of the construction site and to avoid creation of a nuisance in the surrounding area. The use of water, oil, or chemical treatment for control of dust in the demolition of structures, in construction operations, in work performed on a road, parking area, or in the clearing of land is required.
3.3.2 Sandblasting
Utilize adequate methods, including enclosure of work areas and debris, to prevent airborne particulate matter during sandblasting of painted and non-painted structures or other similar operations. Blast media and containment systems shall be approved prior to use.
3.4 ACCESS ROADS AND PARKING LOTS
No person may cause, suffer, allow, or permit any public, industrial, commercial, or private road, street, or alley to be used without taking precautions to achieve control of dust emissions.
In addition to mitigation and control techniques, the removal of soil or other materials shall be periodically performed by mechanical sweepers or their equivalent. Spot clean dirty roadways and parking lots. These activities shall be performed as deemed necessary. Remove sand which is applied for the specific purpose of snow or ice control as soon as such control is no longer necessary.
-- END OF SECTION –
SUBSTITUTIONS AND PRODUCT OPTIONS
01 63 00 - 1
SECTION 01 63 00
SUBSTITUTIONS AND PRODUCT OPTIONS
PART 1 – GENERAL
1.1 BRAND NAMES
"Brand Names" are specified in several places throughout the specifications. The use of specific "names" is intended only to define type, quality, size, and other salient features required. Therefore, all brand name items listed are to be interpreted as "or approved equivalent or better" unless specifically noted otherwise.
1.2 PROPOSED SUBSTITUTIONS
A. The burden of ascertaining product/performance equality of proposed substitutions from those specified items is to be borne by the Contractor.
B. Product substitutions will be accepted for review, and potential acceptance, by the Contracting Officer and /or Project Engineer.
C. If data provided by the Contractor is deemed inadequate to make a determination as to the equality of the proposed substitute, without additional research by the Government, it will be rejected.
D. Approval by the Contracting Officer shall not relieve the Contractor from responsibility for any errors or omissions, nor from responsibility for complying with the requirements of this contract, except with respect to variations described and approved by the Contracting Officer and/or Project Engineer.
1.3 EXACT PRODUCT SPECIFIED
A. If exact products are specified in the construction drawings or construction specifications, and the Contractor intends to use those same products in the construction work, submittal requirements in Schedule of Material Submittals and the technical specifications for catalog cuts, manufacturer's literature, and samples are waived.
B. The Contractor shall provide a list of products that fall into this "intended use of exact product specified" category along with the manufacturer's installation/application instruction, for each product on the list.
C. This list and manufacturer's installation application instructions shall be provided within twenty
(20) days after the Notice-to-Proceed (NTP) for review and approval by the Contracting Officer and /or Project Engineer. Note that this will not take the place or affect the requirement for operations and maintenance (O&M) manuals.
PART 2 – PRODUCTS
1.1 MATERIAL SHIPMENTS
A. The Government will not receive material shipments for construction and the Contractor shall not ship materials to himself addressed in care of SSC Coordinator or RE/COR. Receiving and storage of all construction shipments is entirely the responsibility of the Contractor.
1.2 SHIPMENT AND PROTECTION OF MATERIAL AND EQUIPMENT
A. Shipments shall be addressed to the Contractor who shall be responsible for their receipt, unloading, handling, and storage at the site. Government will not accept deliveries on behalf of the Contractor or his sub-contractors or assume responsibility for security of materials, equipment, or supplies delivered to the site. Contractor shall protect and preserve materials, supplies, and equipment of every description (including property which may be Government furnished or owned) and work performed.
CLOSEOUT PROCEDURES
01 77 00 - 1
SECTION 01 77 00
CLOSEOUTPROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following:
1. Inspection procedures.
2. Warranties.
3. Final cleaning.
1.2 SUBSTANTIAL COMPLETION
A. Preliminary Procedures: Before requesting inspection for determining date of Substantial Completion, complete the following. List items below that are incomplete in request.
1. Prepare a list of items to be completed and corrected (punch list), the value of items on the list, and reasons why the Work is not complete.
2. Advise the Resident Engineer (RE) of pending insurance changeover requirements.
3. Submit specific warranties, workmanship bonds, maintenance service agreements, final certifications, and similar documents.
4. Prepare and submit Project Record Documents, operation and maintenance manuals, Final
Completion construction photographs, and similar final record information.
5. Deliver tools, spare parts, extra materials, and similar items to location designated by the RE Label with manufacturer's name and model number where applicable.
6. Complete final cleaning requirements, including touchup painting.
7. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects.
B. Inspection: Submit a written request for inspection for Substantial Completion. On receipt of request, the RE will either proceed with inspection or notify Contractor of unfulfilled requirements. The RE will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by the FAA, that must be completed or corrected before certificate will be issued.
1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.
2. Results of completed inspection will form the basis of requirements for Final Completion.
1.3 FINAL COMPLETION
A. Preliminary Procedures: Before requesting final inspection for determining date of Final
Completion, complete the following:
1. Submit certified copy of the RE's Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by the RE. The copy of the list shall state that each item has been completed or otherwise resolved for acceptance.
B. Inspection: Submit a written request for final inspection…