This document is an Amendment to Solicitation 6973GH-24-R-00131 for Technical, Management, & Admin Support for AAM-500. The amendment incorporates the pre-proposal conference minutes, revised Statement of Work and Section B, and Questions and Answers 1-27. It also revises the personnel substitution clause, deletes the Continuity of Services clause, and extends the proposal due date from July 23, 2024 to July 26, 2024.

The solicitation requires a contractor to provide technical, management, and administrative support to the FAA Civil Aerospace Medical Institute Human Factors Research Division, AAM-500. The work includes Task 1 - Technical Research Support (T&M), Task 2 - Program Management & Project Management Support (FFP), and Task 3 - Administrative Support (T&M). The Period of Performance is November 11, 2024 to November 10, 2028. This is a non-franchise acquisition for the Department of Transportation Federal Aviation Administration.

View the file

Other files for this federal contract opportunity

Other files attached to 6973GH-24-R-00131, Technical, Management, & Admin Support for AAM-500, newest first.
File Type Posted
Attachment 6 PPS.docx DOCX document
Amendment 0002.pdf PDF
Questions and Answers_7.15-24 Final Clean.pdf PDF
Technical Management and Admin AAM-500 Support SOW_07.11.24 Final Clean.pdf PDF
Qualifications of Personnel Appendix A_Updated 07.11.24 Final Clean.pdf PDF
Amendment 0001 Revised Attachment 2.xlsx XLSX spreadsheet
Attach 1 Technical Management and Admin AAM-500 Support SOW_05-23-24 with Appendix A.pdf PDF
Attachment 4 AMS 3.6.2-29 StatementofEquivalentRates.docx DOCX document
Attachment 3 Wage Determination.pdf PDF
Attachment 6-Client Authorization Letter.docx DOCX document
6973GH-24-R-00131 6-20-24.pdf PDF
Attachment 2 Section B 5-29-24.xlsx XLSX spreadsheet
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO.

PAGE OF PAGES

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

CODE

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

Items 8 and 15, and returning is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required.)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.

E. IMPORTANT: Contractor is not, is required to sign this document and return

ORDER NO. IN ITEM 10A.

1 4

0001 06/20/2024

AAQ-730 FAC. & AVIATION SAFETY ACQ

PO BOX 25082

BLDG 014-AHQ, ROOM 233A

OKLAHOMA CITY OK 73125

AAQ730-AFN

x

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ 1 x x

6973GH-24-R-00131

1 copies to the issuing office.

06/20/2024

(x)

The purpose of this amendment is to provide the minutes to the Pre-Proposal Conference, incorporate the Revised Attachment 1, Statement of Work, including Revised Appendix A, incorporate the Revised Attachment 2, Section B, incorporate Questions and Answers 1 through 27, make necessary changes to the SIR clauses and provisions and extend the due date for receipt of proposals.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Cynthia L. Cooper

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

6973GH-24-R-00131/0001

FIRST: Pre-Proposal Conference Minutes from July

9, 2024 and hereby incorporated into this SIR.

SECOND: SIR Attachment 1, Statement of Work

(including Appendix A), included with the SIR upon issuance is hereby superseded and replaced with Revised Attachment 1, Statement of Work

(including Appendix A), dated July 11, 2024.

THIRD: SIR Attachment 2, Section B, included with the SIR upon issuance is hereby superseded and replaced with Revised Attachment 2, Section

B, dated July 15, 2024.

FOURTH: Questions and Answers 1 through 27 are hereby incorporated into this SIR.

FIFTH: The following NOTE is added to SIR

Provision M.2, Sub-Factor 2c, Key Personnel (SOW

Section 7): NOTE: Offerors are allowed to place the resumes and letters of commitment in an

Appendix to Volume II and this information will not be subject to the page count.

SIXTH: SIR Clause 3.8.2-22, Substitution or

Addition of Personnel (Oct 2006), paragraph

(2)(a) is revised as follows:

(1) The Contractor must assign only those individuals whose resumes, personnel data, or personnel qualification statements have been submitted and determined by the Contracting

Officer to meet the minimum requirements of the contract. The Contractor must not substitute or add personnel except in accordance with this clause.

(2) Substitution of Personnel.

(a) For the first 90 days of contract performance, the Contractor must not substitute personnel for the individuals whose resumes or other personal qualification were submitted with its offer and that were determined by the

Contracting Officer to be acceptable at the time of contract award, unless such substitutions are because of an individual's sudden illness, death, or termination of employment. In any of these

Continued ...

3 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

6973GH-24-R-00131/0001

events, the Contractor must promptly notify the

Contracting Officer and propose substitute personnel as required by paragraph (4) below.

(b) If an individual becomes, for whatever reason, unavailable for work under the contract for a continuous period exceeding thirty (30) working days, or is expected to devote substantially less effort to the planned work, the Contractor must propose a substitute personnel as required by paragraph (4) below.

(3) Addition of Personnel. If an FAA requirement will increase the specified level of effort for a designated labor category, but not the overall level of effort of the contract, then the

Contractor must notify the Contracting Officer to add personnel to the designated labor category.

The Contractor must request added personnel as required by paragraph (4) below.

(4) Request and Review. The Contractor must submit the request for substitute or added personnel in writing to the Contracting Officer at least 15 days (if a security clearance must be obtained, at least 30 days) before the proposed date of substitution or addition. The

Contractor's request must provide a detailed explanation of the circumstances causing the proposed substitution or addition, a complete resume for the proposed substitute or added personnel, and any additional information required by the Contracting Officer. Proposed substitutes and added personnel must have qualifications equal to or higher than those stated in the contract for the labor category.

The Contracting Officer will evaluate the

Contractor's request and promptly notify the

Contractor of the decision to accept or reject the qualifications of the substitute or added personnel.

(5) The Contracting Officer may terminate the contract if the Contractor has not made suitable, timely, and reasonably forthcoming replacement of personnel who have been reassigned or terminated or otherwise become unavailable to work under the contract or the resulting loss of productive effort would impair the successful completion of the contract. Alternatively, if the Contracting

Continued ...

4 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

6973GH-24-R-00131/0001

Officer finds the Contractor to be at fault for the condition, then the Contracting Officer may equitably adjust (downward) the contract price or fixed fee to compensate the Government for any delay, loss or damage as a result of the

Contractor's action.

SEVENTH: AMS Clause 3.2.11.5-4,Continuity of

Services - Mission Critical Contracts (Jan 2008) is hereby deleted in its entirety.

EIGHTH: The due date for proposals is extended as follows:

From: July 23, 2024 at 1700 CT

To: July 26, 2024 at 17:00 CT

Period of Performance: 11/11/2024 to 11/10/2028

File details come from the government source that posted it. Updated .