This document contains questions and answers regarding solicitation number 6973GH-23-R-00006 from the United States Border Patrol. The solicitation requires technical design, engineering, geophysical and geotechnical services to provide the design, planning, management, and execution of up to thirty-two boreholes up to one hundred feet deep at locations within a five mile radius of the West Port of Entry in Calexico, California. Optional tasks may include cone penetration testing, technology deployment services, and technology support services. Equipment rental and operation, site work, reporting and coordination with stakeholders are required. Pricing will be impacted by anticipated cost increases and security services would be proposed under the change management contract line item if deemed necessary by the Government. The anticipated start date is around June 2023 pending operational approval.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers Round 1

6973GH-23-R-00006

Borehole and Drilling Services at Calexico, CA January 12, 2023

1. Can we be advised of the location of the drilling in order to determine if there is any surface asphalt, concrete or other that will need to be removed prior to drilling?

Answer: Source Selection sensitive but will be provided upon award.

2. What is the planned start date for this project? Pricing, especially for the drillers, fuel, and PVC piping is expected to continue to rise so pricing cannot be held indefinitely.

Answer: Anticipated start date will be around June 2023; pending operational approval from USBP Sector.

3. In 2.2.7 Optional Task 7, it notes "If it is deemed necessary by the government representative and/or local USB Representative, the contractor shall be prepared to provide physical security of the site at all times". Would you like this priced in the option or would it be done under the Change Management CLIN?

Answer: If deemed necessary by the Government, this would be proposed under the change management CLIN if the operational security of the area requires these services.