16 Attachment 1 Statement of Work.pdf
PDF 261 KB Posted
- Solicitation number
- 6973GH-23-R-00006
About this file
This statement of work outlines geotechnical surveying and drilling services required by the United States Border Patrol in Calexico, California. The contractor will be responsible for technical design, engineering, geophysical testing, and drilling up to thirty-two boreholes up to one hundred feet deep. Additionally, the contractor must case and monument five boreholes as permanent observation wells. Optional tasks include cone penetration testing, technology deployment and support services. The contractor will also be responsible for equipment rental, spoils management, safety barriers, traffic control, security, site restoration, inspections, and as-built and geotechnical reports. Work will take place within five miles of the West Port of Entry in Calexico under the direction of USBP personnel. The statement of work specifies requirements for the base tasks of observation well installation and optional tasks such as borehole drilling and technology services. It also outlines deliverables, schedule, security protocols, and points of contact for questions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 21 6973GH-23-R-00006-001.pdf | ||
| 17 Questions and Answers.pdf | ||
| 16 Attachment 4 Payment Bond.pdf | ||
| 16 6973GH-23-R-00006.pdf | ||
| 16 Attachment 5 Performance Bond.pdf | ||
| 16 Attachment 3 Contractor Release Form.doc | DOC document | |
| 16 Attachment 6 Past Experience Form.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
i
U.S. Department of Homeland Security (DHS)
U.S. Customs and Border Protection (CBP)
Statement of Work
For
Calexico, CA
Geotechnical Surveying Services
U.S. Border Patrol
Program Management Office Directorate (PMOD)
Date: 06/30/2022 ii
Table of Contents
1.0 BACKGROUND
2.0 SCOPE
2.1 Base Tasks
2.2 Optional Tasks
2.2.1 Optional Task 1: Cone Penetration Testing (CPT)
2.2.2 Optional Task 2: Uncased Borehole Drilling
2.2.3 Optional Task 3: Uncased Borehole Drilling
2.2.4 Optional Task 4: Uncased Borehole Drilling
2.2.5 Optional Task 5: Uncased Borehole Drilling
2.2.6 Optional Task 6: Uncased Borehole Drilling
2.2.7 Optional Task 7: Lined Large Borehole Drilling
2.2.8 Optional Task 8: Lined Large Borehole Drilling
2.2.9 Optional Task 9: Technology Support Services
2.2.10 Optional Task 10: Technology Deployment Services
2.2.11 Optional Task 11: Change Management Contingency
2.2.12 Mobilization and Demobilization
2.2.13 Surface Marking of Underground Utilities
2.2.14 Spoils
3.0 Applicable Documents
4.0 Specific Tasks
4.1 General Requirements
4.2 Delivery and Inspection Instructions
5.0 Deliverables and Delivery Schedule
5.1 Deliverable Submittals
5.1.1 Additional Deliverable Requirements
5.2 Types of Deliverable
5.2.2 Safety, Health and Accident Prevention Plan
5.2.3 Progress Reports/Daily Reports
5.2.4 Post – Construction Submittals
6.0 Government Furnished Equipment and Property
7.0 Place of Performance
8.0 Period of Performance
9.0 Security
9.1.1 Security – Work Clearance
9.2 Physical Security
10.0 Hours of Operation
11.0 General Information
11.2 Other/Meetings
11.3 Special Considerations
11.4 Points of Contact
12.0 Questions or Concerns
1.0 BACKGROUND
The United States Border Patrol (USBP) requires technical design, engineering, geophysical and geotechnical services to provide the design, planning, management, and execution of all critical tasks required to provide up to thirty-two (32) boreholes of up to forty-two (42”) in diameter up to one hundred (100’) feet deep. Additionally, the vendor will be required to provide casing and monuments to maintain five (5) boreholes as permanent observation wells. Optional tasks that may be required include:
cone penetration testing (or an excepted alternative), technology deployment services, and technology support services.
The completion of the work will also require the rental and operation of several different types of light and heavy equipment that may not be specifically called out in the SOW but should be planned for during the technical design and pre-project planning phase of this effort. Executing the work safely and efficiently will begin with close coordination with CBP/local USBP representatives, property managers, utility locators, DigAlert, concrete/asphalt contractors, drillers, heavy equipment providers and operators, and rental equipment providers. The vendor will be responsible for all aspects of executing the SOW outlined below, including (but not limited to): scheduling deliveries and pickups of equipment, spoils management, vertical and horizontal safety barriers, traffic control, site security, site restoration, final inspection of the completed sites and providing as-built and geotechnical reports. The work will be completed at specific locations as directed by USBP personnel within the Roosevelt easement within a
5.00 mile radius of the West Port of Entry, Calexico, CA (1 E 1st St, Calexico, CA 92231).
2.0 SCOPE
2.1 Base Tasks
2.1.1 Technical Design and Pre-project Planning
Due to the overall complexity of the project, the contractor will need to execute technical research and design activities in addition to the coordination of multiple suppliers, vendors, and subcontractors (See below) prior to field work taking place. The contractor shall plan for these activities in order to ensure efficient execution of the remainder of the scope once on-site activities begin.
2.1.2 Cased Borehole Drilling
The Contractor shall drill five (5) observation wells to a depth of sixty (60’) feet at specific locations as indicated by USBP/CBP representative. Each observation well will be completed by drilling an eight (8) inch diameter precision borehole, lowering an uncapped and continuous six (6) inch schedule 40 PVC well casing (threaded) into the borehole with a surface termination twelve (12”) inches below the finish grade. At surface termination, the borehole casing shall be capped with a watertight Torquer locking well cap. To provide space for the Torquer plug, the manhole cover will be set approximately six (6”) inches above the casing termination and approximately six (6”) inches below the finish grade. Threaded well casing, with O-rings present for a watertight installation, shall be used and all joints will be secured following the manufacturer’s torque recommendations for permanent installations. The annulus between the casing and the borehole shall be filled with native soil (i.e., spoils from drilling) which have been sieved to remove any material larger than three (3”) inches. Water may be necessary to reduce voids and promote even settling of the soil. The top of each borehole shall be housed in a sequentially numbered plastic manhole cover (EMCO Wheaton Retail A0721-001) which is flush-mounted in a thirty-six (36”) inch by thirty-six (36”) inch concrete monument twelve (12”) inches thick. 3M GP programmable RFID marker ball shall be buried so that it is covered by the monument and consistently placed under a designated corner (i.e., SW, NW, etc.) so that it may be easily located. The Contractor is required to purchase RFID marker balls and a 3M locator/reader. The deviation of the installed observation wells shall be confirmed by inclinometer measurements performed by the Contractor and shall not deviate more than 5% from vertical. The method of computing deviation from vertical shall be to divide the closure distance by the measured depth at 1/10th foot depth intervals. The deviation data will be presented in Bull’s Eye plots, Closure plots and in an Excel file. All recorded drill log data along with locations of each borehole to sub-centimeter accuracy GPS coordinates shall be delivered at completion of project.
Description of Boreholes
Count PVC Casing
Gov Provided
Precision Drilled (max 5%)
Terminated 12” below grade
Plastic Access Cap
8” diameter x 60’ 5 Yes No Yes Yes No
NOTE: While equipment selection is left to the discretion of the Contractor. It is recommended that the use of a dual rotary air-driven drill rig be considered for this project given the challenges of the geology and the site conditions. Bentonite, drilling mud, or other cementing agents/binders may not be used in the execution of this project.
2.2 Optional Tasks
2.2.1 Optional Task 1: Cone Penetration Testing (CPT)
The Contractor shall perform ten (10) CPTs to a depth of one-hundred (100’) feet at specific locations as indicated by USBP/CBP representative. The contractor shall deploy magnetometer-based sensors, electrical resistivity sensors, seismic sensors, or a probe-based camera at the direction of USBP/CBP representative to record data as a function of depth. All recorded data along with locations of each test to sub-centimeter accuracy GPS coordinates shall be delivered at completion of project. If the geology is not suited to CPT, another exploratory geophysical technique may be proposed such as traditional geotechnical borings with sampling/data logging
2.2.2 Optional Task 2: Uncased Borehole Drilling
The Contractor shall drill five (5) boreholes to a depth of one-hundred (100’) feet at specific locations as indicated by USBP/CBP representative. Each borehole will be completed by drilling a twenty-four
(24) inch diameter borehole within industry best practices for standard deviation from vertical. Before drilling the borehole it will be necessary to excavate the borehole locations to a depth of approximately six (6’) feet to mitigate the potential presence of both surface and underground obstructions that could be damaged or cause damage to the drilling equipment. This may require concrete/asphalt cutting and restoration. At the conclusion of the work, the borehole will be backfilled with the spoils reserved from the original drilling (water and/or soil compaction may be necessary) and the surface shall be returned to the original condition. The positions of any/all boreholes will be recorded with sub-centimeter accuracy GPS and this information will be provided as part of the as-built report.
Description of Boreholes
Count PVC Casing
Gov Provided
Precision Drilled (max 5%)
Terminated 12” below grade
Plastic Access Cap
24” diameter x 100’
5 No No No No No
2.2.3 Optional Task 3: Uncased Borehole Drilling
The Contractor shall drill five (5) boreholes to a depth of one-hundred (100’) feet at specific locations as indicated by USBP/CBP representative. Each borehole will be completed by drilling a twenty-four (24) inch diameter borehole within industry best practices for standard deviation from vertical. Before drilling the borehole it will be necessary to excavate the borehole locations to a depth of approximately six (6’) feet to mitigate the potential presence of both surface and underground obstructions that could be damaged or cause damage to the drilling equipment. This may require concrete/asphalt cutting and restoration. At the conclusion of the work, the borehole will be backfilled with the spoils reserved from the original drilling (water and/or soil compaction may be necessary) and the surface shall be returned to the original condition. The positions of any/all boreholes will be recorded with sub-centimeter accuracy GPS and this information will be provided as part of the as-built report.
2.2.4 Optional Task 4: Uncased Borehole Drilling
The Contractor shall drill five (5) boreholes to a depth of one-hundred (100’) feet at specific locations as indicated by USBP/CBP representative. Each borehole will be completed by drilling a twenty-four
(24) inch diameter borehole within industry best practices for standard deviation from vertical. Before drilling the borehole it will be necessary to excavate the borehole locations to a depth of approximately six (6’) feet to mitigate the potential presence of both surface and underground obstructions that could be damaged or cause damage to the drilling equipment. This may require concrete/asphalt cutting and restoration. At the conclusion of the work, the borehole will be backfilled with the spoils reserved from the original drilling (water and/or soil compaction may be necessary) and the surface shall be returned to the original condition. The positions of any/all
2.2.5 Optional Task 5: Uncased Borehole Drilling
The Contractor shall drill five (5) boreholes to a depth of one-hundred (100’) feet at specific locations as indicated by USBP/CBP representative. Each borehole will be completed by drilling a twenty-four
(24) inch diameter borehole within industry best practices for standard deviation from vertical.
Before drilling the borehole it will be necessary to excavate the borehole locations to a depth of approximately six (6’) feet to mitigate the potential presence of both surface and underground obstructions that could be damaged or cause damage to the drilling equipment. This may require concrete/asphalt cutting and restoration. At the conclusion of the work, the borehole will be backfilled with the spoils reserved from the original drilling (water and/or soil compaction may be necessary) and the surface shall be returned to the original condition. The positions of any/all boreholes will be recorded with sub-centimeter accuracy GPS and this information will be provided as part of the as-built report.
2.2.6 Optional Task 6: Uncased Borehole Drilling
The Contractor shall drill five (5) boreholes to a depth of one-hundred (100’) feet at specific locations as indicated by USBP/CBP representative. Each borehole will be completed by drilling a twenty-four
(24) inch diameter borehole within industry best practices for standard deviation from vertical.
Before drilling the borehole it will be necessary to excavate the borehole locations to a depth of approximately six (6’) feet to mitigate the potential presence of both surface and underground obstructions that could be damaged or cause damage to the drilling equipment. This may require concrete/asphalt cutting and restoration. At the conclusion of the work, the borehole will be backfilled with the spoils reserved from the original drilling (water and/or soil compaction may be necessary) and the surface shall be returned to the original condition. The positions of any/all
2.2.7 Optional Task 7: Lined Large Borehole Drilling
The Contractor shall drill four (4) lined boreholes of forty-two inch (42”) diameter up to a depth of one hundred (100’) feet. Before drilling the borehole it may be necessary to excavate the borehole location to a depth of approximately six (6’) feet to mitigate the potential presence of both surface and underground obstructions that could be damaged or cause damage to the drilling equipment (this will not be necessary if the large borehole is located in the same location as one of the boreholes drilled in the previously described tasks). There may be unforeseen construction debris below grade (i.e., metal landing mat and/or concrete). This may require concrete/asphalt cutting and restoration to the original condition. The borehole will be lined with government furnished thirty-six inch (36”) diameter corrugated pipe, or other approved material. The corrugated pipe will require welding and will be secured at the surface so as to render the casing self-supporting above the bottom of the borehole. At the conclusion of each work day, the contractor shall secure the worksite with trench plates and bolts if relevant (traffic-rated). At the end of each day, spoils will be positioned as to not hinder any private egress for relevant/impacted businesses/residences/public roadways. If it is deemed necessary by the government representative and/or local USBP representative, the contractor shall be prepared to provide physical security of the site at all times.
At the conclusion of the work, the corrugated pipe will be removed and retained by the government for future projects, the borehole will be backfilled with the soils reserved from the original drilling (water and/or soil compaction may be necessary), and the surface shall be returned to the original condition. The positions of any/all boreholes will be recorded with sub-centimeter accuracy GPS and this information will be provided as part of the as-built report.
2.2.8 Optional Task 8: Lined Large Borehole Drilling
The Contractor shall drill four (4) lined boreholes of forty-two inch (42”) diameter up to a depth of one hundred (100’) feet. Before drilling the borehole it may be necessary to excavate the borehole location to a depth of approximately six (6’) feet to mitigate the potential presence of both surface and underground obstructions that could be damaged or cause damage to the drilling equipment (this will not be necessary if the large borehole is located in the same location as one of the boreholes drilled in the previously described tasks). There may be unforeseen construction debris below grade (i.e., metal landing mat and/or concrete). This may require concrete/asphalt cutting and restoration to the original condition. The borehole will be lined with government furnished thirty-six inch (36”) diameter corrugated pipe, or other approved material. The corrugated pipe will require welding and will be secured at the surface so as to render the casing self-supporting above the bottom of the borehole. At the conclusion of each work day, the contractor shall secure the worksite with trench plates and bolts if relevant (traffic-rated). At the end of each day, spoils will be positioned as to not hinder any private egress for relevant/impacted businesses/residences/public roadways. If it is deemed necessary by the government representative and/or local USBP representative, the contractor shall be prepared to provide physical security of the site at all times.
At the conclusion of the work, the corrugated pipe will be removed and retained by the government for future projects, the borehole will be backfilled with the soils reserved from the original drilling (water and/or soil compaction may be necessary), and the surface shall be returned to the original condition. The positions of any/all boreholes will be recorded with sub-centimeter accuracy GPS and this information will be provided as part of the as-built report.
2.2.9 Optional Task 9: Technology Support Services
The Contractor shall provide up to six (6) days of technology deployment support services. The type of technology deployed shall be by direction of the CBP/USBP representative. The Government will supply the technology (hardware, software, supplies), however, the Contractor shall be responsible for providing support services during the deployment of the technology and the processing of the data. At the conclusion of technology deployment, the contractor shall supply a technology deployment site map and relevant notes as a deliverable/”as-built”.
2.2.10 Optional Task 10: Technology Deployment Services
The Contractor shall provide up to six (6) days of technology deployment and provide the analyzed data output to the on-site Government representative to inform the placement, sequence, and depth of the boreholes. The type of technology deployed shall be by direction of the USBP. The Government may supply the technology (hardware, software, supplies), however, the Contractor shall be responsible for providing the sensor subject matter experts and technicians necessary for the technology deployment and data analysis/interpretation.
2.2.11 Optional Task 11: Change Management Contingency
Due to the highly unpredictable nature of this work, the Contractor shall establish a change management contingency of up to 10% of the total project costs. This will allow the Contractor to be agile and quickly adapt to urgent needs of the project as needs arise or priorities change. Use of the change management contingency funds will be at the written direction of the CO or COR.
2.2.12 Mobilization and Demobilization
The Contractor shall assume one mobilization and demobilization to support the entire Scope of Work, regardless of equipment type. Any additional/unforeseen mobilization/travel costs should be included in the individual optional task which they are associated with.
2.2.13 Surface Marking of Underground Utilities
Surface marking of any underground utilities must be in place prior to the start of work.
2.2.14 Spoils
Any remaining spoils shall be graded within the work area and not removed.
3.0 Applicable Documents
3.1 This Statement of Work
4.0 Specific Tasks
The Contractor, in completing these tasks, shall follow the requirements of this SOW, and where not specifically defined, comply with government regulations and industry standards.
4.1 General Requirements
4.1.1 General Information
4.1.1.1 No utilities will be provided by the Government.
4.1.1.2 The Contractor’s material/product selection, installation means and methods shall only be completed by qualified personnel.
4.1.1.3 Damage to property owned by others and caused by the Contractor shall be repaired by the Contractor and shall be returned to its original condition.
4.1.2 Contractor shall:
4.1.2.1 Follow all Federal, State, and Local codes during the completion of this project. Refer to Section
3.0 Applicable Documents.
4.1.2.2 Survey areas with the Contracting Officer’s Representative (COR) or authorized Facility Point of Contact (POC) to verify final location of all work prior to work commencing.
4.1.2.3 Protect and safeguard the site from all damage. Any corrective action to repair damaged areas shall be the responsibility of the Contractor.
4.1.2.4 Provide all temporary sanitary facilities, such as, hand wash and portable toilets.
4.1.2.5 Provide environmental protection measures as necessary to prevent polluting discharges of any type, or to be a source of nuisance or interference to operations or other Government personnel in the proximity of the work.
4.1.2.6 Be fully responsible for securing and payment of any necessary State or local permit or other form of approval documentation. In the event that no such permit or documentation is required, the Contractor shall attest to that fact in writing.
4.1.2.7 Workers shall be aware of, and consent to, either being under constant physical escort or video surveillance by closed circuit cameras at all times.
4.1.2.8 Be responsible for all temporary services and/or other accommodations, as well as, all direct and indirect management effort and expenses required to execute this project.
4.1.2.9 Obtain prior approval from the COR/POC prior to commencing with any on-site work.
4.1.2.10 Provide trucks for proper disposal of all construction debris and spoils. Truck waiting locations on site shall be coordinated with the COR/POC prior to arriving on site.
Contractor shall be responsible for the proper disposal of waste/debris associated with this project.
4.1.2.11 Be responsible to secure its equipment and materials stored on site.
4.2 Delivery and Inspection Instructions
4.2.1 The Government:
4.2.1.1 Reserves the right to refuse equipment not meeting the aforementioned requirements.
4.2.2 The Contractor shall:
4.2.2.1 Be responsible for the delivery, offloading and mobilization of all equipment to be used for this project.
4.2.2.2 Be responsible for conducting a physical check of the equipment, jointly with the COR/POC, to determine that all mechanical and safety inspections have been performed on each piece of equipment and proof of those inspections are up to date.
4.2.2.3 Document all discrepancies and shall be responsible for either repair or replacement of any equipment that does not have, or cannot prove, up-to-date safety and mechanical inspections.
5.0 Deliverables and Delivery Schedule
The following table outlines the deliverables the Contractor shall submit for review and approval.
Item
Number Deliverable Title Deliver To Format Frequency SOW Referemce
3 Schedule of Values (SOV) COR & USBP
POC
Electronic Via Email
Within five (5) calendar days after issuance of the design
NTP
5.2.3
4 Safety, Health and Accident Prevention Plan (Submitted for
COR & USBP
POC
Electronic Via Email
Within five (5) calendar days after issuance of the design
NTP
5.2.4
Informational Purposes Only)
7 Progress /Daily Reports COR & USBP
POC
Electronic Via Email
Weekly by 4 PM (Local Time) every Friday during performance
5.3.1
8 Post Construction Submittals
COR & USBP
POC
Electronic Via Email
When construction is completed 5.4
5.1 Deliverable Submittals
All submittals shall be provided through a Material Approval Submittal (or Contractor format) process and submitted to the Contracting Officer’s Representative (COR) in a Portable Document Format (PDF) file format. Unless noted otherwise, all deliverables shall be in electronic format and provided no less than fifteen (15) calendar days prior to the proposed drilling.
5.1.1 Additional Deliverable Requirements
5.1.1.1 Submittal information shall relate specifically to the requirements, and components required for the work and activities described in Section 4 of this SOW for the project. If the contract provides for the submission of shop drawings, samples, lists and descriptive data for approval, it is important that these be transmitted as early as possible in order to allow time for review and approval. In order to expedite the review for approval, the Contractor shall ensure that the submittals are clearly marked to properly identify the specific items proposed.
5.1.1.2 General statements relating to the methods of work to be completed and material manufacturer’s generic or booklet type information will be returned without review.
5.1.1.3 The Contractor shall allow the Government seven (7) calendar days (after receipt of submittal information) for review and action relative to submittals.
5.1.1.4 Submittal information returned to the Contractor shall be corrected and resubmitted to the Government within five (5) calendar days of Contractor receipt of returned submittal.
5.1.1.5 Failure, on the part of the Contractor, to provide acceptable submittal information within the time frames defined herein shall not be cause for a contract time extension.
5.2 Types of Deliverable
5.2.1 Schedule of Values (SOV)
The Contractor shall submit within five (5) calendar days after NTP issuance the SOV that will provide sufficient breakdown of all unit costs related to individual tasks listed in this SOW. This SOV shall be submitted with each payment request.
5.2.2 Safety, Health and Accident Prevention Plan
The Contractor shall prepare and submit a Task Specific Accident Prevention Plan and Task Specific Safety Plan. This plan shall be submitted within five (5) calendar days after NTP issuance. This plan shall be provided for information only.
5.2.3 Progress Reports/Daily Reports
The Contractor shall prepare reports and shall transmit the reports to the COR/POC via email by 4:00 pm (Local Time) each Friday, or prior to the weekly progress meeting if one is held.
5.2.4 Post – Construction Submittals
5.2.4.1 Contractor shall provide one (1) set of as-built drawings in hard copy format and one (1) set in electronic (PDF) format. Each drill hole shall be labeled on a scale map showing the GPS coordinates, known depth.
5.2.4.2 The Contractor shall provide one electronic PDF copy of all the following that apply, but not limited to: waste/debris disposal documents associated with the tasks of this SOW within fifteen
(15) calendar days after construction is complete.
5.2.4.3 All post-construction submittals shall be provided to the Contractor and approved by the Government before final Government acceptance of completion of the tasks in this SOW.
Electronic copies must be delivered on CD or DVD; USB Flash Drive (Thumb Drive) is not acceptable.
6.0 Government Furnished Equipment and Property
• The Government will provide Geographic Technology Reports to the Contactor.
• The Government will provide technology devices.
7.0 Place of Performance
Calexico, CA
8.0 Period of Performance
The performance period will be defined upon award. An NTP schedule and mobilization expectations will be discussed at time of award.
9.0 Security
9.1 Security Requirements
The work to be performed under this SOW is categorized as unclassified. The Contractor shall be responsible for its employees following all the laws of the United States or other governing bodies affecting operations at all sites. This shall include regulations imposed by the CBP.
9.1.1 Security – Work Clearance
9.1.1.1 All Contractor personnel shall be subject to the security provisions and requirements of the facility. Work on the site may incur time constraints associated with security compliance activities, i.e., personnel and vehicle inspections, etc. The Contractor shall ensure that security compliance activities are properly factored into the work schedule and cost proposals. The Contractor shall coordinate with security officials at the facility regarding all applicable security/safety requirements.
9.1.1.2 All personnel entering in or working on federal property will be screened and checked for criminal history and proper immigration status. Personnel who do not meet the minimum standards will not be allowed on the job site. The following items determine whether a person has met the minimum standards as it relates to the criminal history requirement:
• Felony conviction
• Immigration violation (unless exonerated by a judge)
• Active warrant (anywhere)
9.1.1.3 If an individual does not clear vetting, the Government cannot disclose (for privacy reasons) the specific results of the vetting process.
9.1.1.4 The Contractor shall submit the following information to the applicable CBP Sector/Station Security Manager for each employee (including subcontractor personnel) having access to the site, no less than ten (10) working days prior to work start:
• Individual's full name
• Date of birth (DOB)
• Place of birth (POB)
• Driver's Licenses Number and State
• SSN or Alien Registration Number
• On a case-by-case basis, the Contractor may be asked to furnish photocopies of the driver license or state identification card and the social security number or alien registration number in order to help verify and/or resolve conflicting information resulting from the security screening process.
9.1.1.5 Should any Contractor employee, Subcontractor employee, or any other person working on behalf of the Contractor (through further investigation) be found unfit to work on a CBP site, that person shall be removed from the site and barred from returning to the project site.
9.1.1.6 Contractor shall provide the required information showing proof of personnel security screening within ten (10) calendar days of receiving the notice of contract award. The personnel information shall be included in a protected Word attachment to an email. A separate email with the password for the Word document shall be sent after the initial email.
9.1.1.7 The Contractor shall submit all required information for access and security clearances required by CBP.
9.2 Physical Security
The Contractor shall be responsible for safeguarding all Government equipment, information, and property provided for Contractor use. At the close of each workday, Government facilities, equipment, and materials under Contractor control shall be secured.
10.0 Hours of Operation
This site is accessible at all times between 7:00 am to 5:00 pm (Pacific Time), Monday thru Friday. The Contractor will not be required to work on the weekends or Federal Holidays, but may do so with approval from the Contracting Officer.
11.0 General Information
11.1 Safety and Environmental
• The Contractor shall conduct work and maintain the work site in such a manner as to not be the cause of any adverse environmental issues to the surrounding environment, CBP, or personnel in or around the immediate area.
• The Contractor shall comply with all OSHA requirements. The Contractor shall provide a Site Safety and Health Officer (SSHO) and be on-site at all times when work is being performed.
• The Contractor shall be required to wear personal protective equipment (PPE) such as hard hats, safety glasses, reflective vests, safety shoes and long pants within the work perimeter at all times. All equipment operators shall be licensed and/or certified to operate equipment and have all the necessary safety training.
• All Contractor accidents, involving injuries or property damage that occur during the performance of this contract shall be reported to the COR/POC within four (4) hours of the Contractor being aware of the occurrence.
11.2 Other/Meetings
• Other - In the event that the necessary materials or methods of installation are not defined by direction or documents provided for this project, the Contractor shall utilize industry standards for any such material or installation method.
• Meetings – The Contractor shall be required to attend the following meetings.
o The Contractor shall attend a job walk-through prior to commencement of any activities.
This meeting will consist of a one-half (1/2 day) meeting at the project site. The designated Contractor Project Superintendent/ Manager, as well as key Subcontractors and trades, are required to attend this meeting.
o Prior to project completion, the Contractor shall conduct a preliminary punch list walk-through on the works and forward the punch list to the COR/POC for review (pre-final inspection) o The Contractor shall conduct a final punch list walk-thru at the completion of the project (final inspection). The final walk-thru shall be attended by the Contractor’s key personnel, site staff, and the COR/POC.
11.3 Special Considerations
• All work to be performed with the least amount of interruption to on-going operations.
Contractor must be aware that interruption of CBP and USBP operations, while necessary, shall be kept to a minimum, and scheduled and coordinated through Border Patrol and CBP personnel ahead of time. This includes any kind of constraint or disruption to BPS activities.
• It is possible that there could be an interruption in the work due to unplanned emergencies and events beyond the control of the Government due to the nature of the facility and Border Patrol operations.
• Contractor shall complete final cleaning of all affected areas by the work. Cleaning shall be to the extent there is no remaining evidence that demolition or construction took place.
11.4 Points of Contact
Notwithstanding the Contractor’s responsibility for management during performance, the administration of this contract will require coordination between CBP, USBP and the Contractor.
The Contracting Officer (CO) will appoint the COR to assure orderly performance of the tasks and provide technical direction. The COR/POC is:
12.0 Questions or Concerns
All technical questions and concerns shall be directed to the COR/POC. All contractual questions shall be directed to the CO/Contract Specialist.
The types of actions within the purview of the COR/POC authority:
• Assure that the Contractor performs the technical requirements of the contract
• Assure that the Contractor perform inspections necessary in connection with performance of the contract
• Maintain both written and oral communications with the Contractor concerning the aspects of the contract within his/her purview
• Issue interpretations of technical requirements
• Monitor the Contractor’s performance under the contract and notify the Contractor and CO of any deficiencies observed
• Coordinate Government-Furnished Property or Data availability and provide for site entry of Contractor personnel (if required)
The COR/POC is not empowered to make any commitments or changes which affect the contract price, delivery or other items and conditions. Any such proposed changes shall be brought to the immediate attention of the CO for action. The acceptance of any changes by the Contractor without specific approval and written consent of the CO shall be at the Contractor’s risk.
| 1.0 BACKGROUND |
| 2.0 SCOPE |
| 2.1.1 Technical Design and Pre-project Planning |
| Due to the overall complexity of the project, the contractor will need to execute technical research and design activities in addition to the coordination of multiple suppliers, vendors, and subcontractors (See below) prior to field work taking place.... |
| 2.1.2 Cased Borehole Drilling |
| The Contractor shall drill five (5) observation wells to a depth of sixty (60’) feet at specific locations as indicated by USBP/CBP representative. Each observation well will be completed by drilling an eight (8) inch diameter precision borehole, low... |
| NOTE: While equipment selection is left to the discretion of the Contractor. It is recommended that the use of a dual rotary air-driven drill rig be considered for this project given the challenges of the geology and the site conditions. Bentonite, ... |
| 2.2 Optional Tasks |
| 2.2.1 Optional Task 1: Cone Penetration Testing (CPT) |
| 2.2.2 Optional Task 2: Uncased Borehole Drilling |
| 2.2.9 Optional Task 9: Technology Support Services |
| The Contractor shall provide up to six (6) days of technology deployment support services. The type of technology deployed shall be by direction of the CBP/USBP representative. The Government will supply the technology (hardware, software, supplies), ... |
| 2.2.10 Optional Task 10: Technology Deployment Services |
| The Contractor shall provide up to six (6) days of technology deployment and provide the analyzed data output to the on-site Government representative to inform the placement, sequence, and depth of the boreholes. The type of technology deployed shall... |
| 2.2.11 Optional Task 11: Change Management Contingency |
| 2.2.12 Mobilization and Demobilization |
| 2.2.13 Surface Marking of Underground Utilities |
| 2.2.14 Spoils |
| 3.0 Applicable Documents |
| 4.0 Specific Tasks |
| 4.1 General Requirements |
| 4.1.2 Contractor shall: |
| 4.2 Delivery and Inspection Instructions |
| 4.2.2 The Contractor shall: |
| 5.0 Deliverables and Delivery Schedule |
| 5.1 Deliverable Submittals |
| 5.1.1 Additional Deliverable Requirements |
| 5.2 Types of Deliverable |
| 5.2.2 Safety, Health and Accident Prevention Plan |
| 5.2.3 Progress Reports/Daily Reports |
| 5.2.4 Post – Construction Submittals |
| 6.0 Government Furnished Equipment and Property |
| 7.0 Place of Performance |
| 8.0 Period of Performance |
| 9.0 Security |
| 9.1.1 Security – Work Clearance |
| 9.2 Physical Security |
| 10.0 Hours of Operation |
| 11.0 General Information |
| 11.2 Other/Meetings |
| 11.3 Special Considerations |
| 11.4 Points of Contact |
| 12.0 Questions or Concerns |