Federal Aviation Administration

Site Survey Report

09/13/2016 FAK VOR, Replace Roof, Flat Rock VA Unstaffed Infrastructure Sustainment Project, (UIS)

JCN: 1504869 JON: 1216SO0590

Background:

On 09/13/2016 FAA Engineering Services visited Flat Rock Virginia VOR to perform a site survey in order to develop a general plan to replace roof & other improvements. Richard Polk AJW-2E15J from the Atlanta Engineering Center was accompanied by Wayne Thilkey WEX32-RIC from Richmond SSC during inspection.

Report:

FAK VOR is West of Richmond. It’s a 28 mile drive from RIC SSC. South of I-64 and West of I-95. It’s 1/3 mile off State Road 60 down a paved entrance road. The site is enclosed by a 3 rail white vinyl fence.

This is a mountain top VOR facility. There’s a standalone VOR equipment building, VOR/TACAN antenna w/teepee, 16 mailbox monitor antennas, three fold over antenna poles & one wood antenna pole, propane tank, three transformers, and well enclosure located on site. Inside equipment room are racks that contain BUEC, DME, TACAN, & VOR equipment plus various receivers, monitors, amps, battery chargers, & other items. There’s a UPS that contains 18 lead acid batteries inside equipment room.

The equipment building is 36-1/2’ x 37’ with a 40’x40’ roof. Roof has a slight pitch from a ½’ crown down the middle and has gutters along two sides. The roof appears to be a one ply, rolled sheet, modified bitumen type. Exterior walls are 11' high with 6” lap vinyl siding on exterior. The vinyl siding on exterior is in fair to poor condition with some pieces missing around the HVAC equipment. Building contains three rooms.

Equipment, Lavatory, & EG room. Interior walls are masonite. There are two exterior metal doors.

There is not much evidence of moisture damage inside the building. Walls, ceilings and, floors are in reasonably fair condition. Interior paint on walls is in fair condition. Interior looks like it’s been painted sometime over the last ten years.

The roof is in fair to poor condition with a couple of locations that need immediate repair. The one ply modified roll roof has two places where the membrane is pushing up and beginning to separate. The FAA usually only allows a minimum of two ply layer for this type of roofing material. The original installation contractor provided minimum labor & materials necessary to install this roof.

There is one Bard wall-hung HVAC unit and one pad mounted package HVAC unit serving the equipment room. Both units are less than two years old and, in fine condition. The electrical main distribution panel in the equipment room is a modern Square D type NQOB. The smaller distribution panel in the EG room is also a Sq. D NQOB but, is much older and may need to be replaced soon. EG room has an exhaust fan system.

The building has a water supply line provided by a submersible electric pump inside a deep well casing. A small storage tank approximately 5 gallon size is inside the equipment room. A very old filter on the water line needs to be replaced.

Power lines go underground somewhere before site that I did not locate. There are three separate step down transformers near the perimeter. A plug style electric meter is on exterior wall outside of EG room on the back right hand side of building.

The building is equipped with a 50KW, 208V, 3ph Kohler propane generator set and, a 500 gal propane tank. Commercial power to the site is reliable.

There are several drawings that describe the FAK VOR site & building in the database. Drawings are marked up with an as-built date of 1951. That would make this building about 65 years old. Drawings indicate VOR was upgraded to VORTAC in 1957. BUEC added in 1976. A 2007 UIS Assesment report indicates roof was replaced in 1999. At the time of this report, roof is approximately 17 years old.

Field Notes:

1. Warm day, dry & sunny.

2. Site is located on a hillside in a clearing that was originally forested.

3. (4) antenna poles. BUEC, DME and, TACAN monitor antenna.

4. Vinyl siding 11’ high. 1’ overhang all around building. Gutters on two sides.

5. 1600’ paved asphalt entrance drive & gravel parking lot.

6. Building interior appears to have all original finishes. Appears to be Masonite or plywood on ceilings. No suspended ceiling installed in equipment room.

7. Observed a large area of vinyl siding missing on NE side of building. SSC reported this is scheduled to be repaired soon.

8. (1) Bard wall hung package unit HVAC heat pumps w/emergency strip heat & (1) pad mounted package HVAC unit were installed within the last two years.

9. Drawings indicate water well near fence on East side of site. Well was not inspected during this visit.

10. Drawings show a 500 steel septic tank on West side of site.

11. Propane tank name plate data indicates year built 1993 and capacity 500 gallon.

12. Building foundation on South corner is sinking. It has separated 1” from floor slab.

13. Building axis is turned 90 degrees and walls don’t face North & South.

14. Contact Brian Sotdorus WEX32-RIC at 804-226-6528 or Wayne Thilkey at 804-551-0863 to arrange a visit.

15. Phone number at facility: 804-598-3206

Location:

37.5285 N, 77.82821 W, elev. 460’

Entrance at intersection of State Road 60 and paved entrance drive.

Flat Rock, Powhatan County, 28 mi. West of Richmond VA, South of I-64 and West of I-95.

Measurements:

1. Building dimensions: 36-1/2’ x 37 x 9’h

2. Roof dimension: 40’x40’

3. Equipment room: 35' x 15’ + 20’x20’ x 9'h

4. E.G. room: 20’ x 15' x 11'h

5. Lavatory: 3’x6’ x 8'h

6. 6” lap vinyl siding covers exterior walls.

7. (2) exterior doors measure 40”x84”x2”

Reference Drawings:

1-E-3650-C01, Flat Rock, VA. Vortac Facility, Plot Layout, 7/26/51 (Rev. 8, 2/3/77) 1-E-3650-C02, Flat Rock, VA. Vortac Facility, Rev. 9, 10/22/76 EA-D-23422, Std. VORTAC Facility, Flat Rock VA, Electrical Layout, As-Built, Rev. 1, 4/10/67 EA-D-27320, Flat Rock, VA. VORTAC, BUEC Power Wiring, 9/30/76, (Rev. 4, 4/13/87)

Action items:

1. Produce a comprehensive scope of work design & cost estimate to replace FAK VOR roof.

2. Discuss project with EOSH. Locate the current asbestos report or procure funding for asbestos testing.

Determine if asbestos abatement will need to be added to SOW.

3. Produce a narrative scope of work document to include with drawings that can be advertised for bid offers.

4. Obtain construction project funding authorization.

5. Work with the FAA Procurement system. Locate at least three qualified construction contractors and, ask for bid offers.

6. Provide RIC SSC with a refurbished FAK VOR.

Pictures:

1. FAK VOR Equipment Building

2. FAK VOR & TACAN Antenna

3. S & E building entrance

4. S & W wall. Note foundation settling on South corner.

5. Foundation separation on South corner of building

6. N & W wall. Note missing vinyl siding and, wood pole used for DME antenna.

7. N & E wall

8. BUEC antenna

9. BUEC & DME antenna

10. VOR & TACAN monitor antenna

11. 500 gallon propane tank

12. (3) step down transformers on N&W corner of fence

13. HVAC units & missing vinyl siding on N & W side of building

14. Building roof membrane. Note: it’s a one ply roof

15. Roof membrane pushing up. Almost separated. Needs repair

16. Gutter

17. Equipment room view towards back wall

18. Equipment room view towards front wall

19. Back of equipment room (No storage room in this building)

20. Back of equipment room

21. Equipment racks

22. Lead acid battery rack

23. 50KW EG set

24. Water storage tank in EG room

25. Transfer switch

26. Main Distribution panel in Equipment room

27. Main distribution panel index

28. EG Room distribution panel index

Let me know if you have any questions or concerns about this report.

Richard Polk

DOT/FAA, AJW-2E15J

Campus Building 1701 Columbia Ave.

College Park, GA 30337 o: 404-305-7445 c: 678-485-6811

*~* END *~*