Questions and Answers for 6973GH-18-R-00255 Amendment 2..pdf

PDF 10 KB Posted

Attached to
AMENDMENT 2: Headquarters Parking Lot at the Mike Monroney Aeronautical Center, Oklahoma City, Oklahoma.
Solicitation number
6973GH-18-R-00255
Issued by

About this file

Questions and Answers for 6973GH-18-R-00255 Amendment 2. (pdf)

View the file

Other files

File Type Posted
For Construction_Specifications_Revised.pdf PDF
AMP400 OC Construction contractors combined.pdf PDF
Questions and Answers for 6973GH-18-R-00255 Amendment 2..pdf PDF
6973GH-18-R-00255 Amendment 2.pdf PDF
Wage Determination.pdf PDF
For Construction_Drawings.pdf PDF
Contractor's Release.pdf PDF
6973GH-18-R-00255 Amendment 1.pdf PDF
HQB Parking Lot Amendment 2 Attachment.pdf PDF
Pre Bid Sign In 9-6-2018.pdf PDF
26 56 00 BSD-Exterior Lighting-DC15128-ADDM---2018-09-07.pdf PDF
SIR 6973GH-18-R-00255.pdf PDF
Chapter_33 Construction Safety.pdf PDF
SF25 Performance Bond.pdf PDF
SF25A Payment Bond.pdf PDF
Pre Bid Sign In 9-6-2018.pdf PDF
6973GH-18-R-00255 Amendment 1.pdf PDF
For Construction_Specifications_Revised.pdf PDF
SF25 Performance Bond.pdf PDF
For Construction_Drawings.pdf PDF
HQB Parking Lot Amendment 2 Attachment.pdf PDF
Chapter_33 Construction Safety.pdf PDF
AMP400 OC Construction contractors combined.pdf PDF
6973GH-18-R-00255 Amendment 2.pdf PDF
SF25A Payment Bond.pdf PDF
SIR 6973GH-18-R-00255.pdf PDF
Contractor's Release.pdf PDF
Wage Determination.pdf PDF
Wage Determination.pdf PDF
SF25 Performance Bond.pdf PDF
AMP400 OC Construction contractors combined.pdf PDF
Contractor's Release.pdf PDF
SF25A Payment Bond.pdf PDF
Chapter_33 Construction Safety.pdf PDF
For Construction_Drawings.pdf PDF
SIR 6973GH-18-R-00255.pdf PDF
For Construction_Specifications_Revised.pdf PDF
6973GH-18-R-00255 Amendment 1.pdf PDF
SF25A Payment Bond.pdf PDF
AMP400 OC Construction contractors combined.pdf PDF
SF25 Performance Bond.pdf PDF
For Construction_Specifications_Revised.pdf PDF
For Construction_Drawings.pdf PDF
Chapter_33 Construction Safety.pdf PDF
SIR 6973GH-18-R-00255.pdf PDF
Contractor's Release.pdf PDF
Wage Determination.pdf PDF
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers for 6973GH-18-R-00255 Amendment 2.

1. Would FAA be able to confirm the source of the primary feeder to transformer # 72 Sheet E4 Specific Note #1? Please review attachment titled HQB Parking Lot Amendment 2 Attachment.

2.

2. The light pole that is to be removed on Sheet E2 Specific Note #3. I order to maintain the circuit do we install an in ground traffic rated junction box or do we install new conduit and pull new conductors to the existing poles. I now that some of the street lighting has been in direct buried cable so I'm not sure what's existing so this could be an issue. Please review attachment titled HQB Parking Lot Amendment 2 Attachment.

3.

3. The Light pole specification indicate a square pole.26 5600-3 2.05. I think most of the poles at FAA are round taper. Also there is not a height indicated in the fixture schedule put on the point by point Sheet E3 indicates MH 30 which I assume is 30 Ft.

Another thing the pole finish is to match the luminaire but that not the standard FAA color. Please advise. Please review attachment titled HQB Parking Lot Amendment 2 Attachment.

4. Can you please tell me the expected start date is for the Headquarters Parking Lot at the Mike Monroney Aeronautical Center?

The SIR states that the schedule will be 240 days after the Notice to Proceed. The exact date that the project will start is unknown at this time.

5. On sheet C3 I don't see where there is underground primary conduit going to the electrical manhole # 20. On sheet E 4 we are to extend new primary conductors thru manhole # 20 to switch # 27430 so can FAA confirm that the duct bank is existing.

Please review attachment titled HQB Parking Lot Amendment 2 Attachment.

6. When install the new primary conductors in the existing duct bank conduit I assume that this work will be done after normal business hours so the existing conductors can be de-energized please confirm. Please review attachment titled HQB Parking Lot Amendment 2 Attachment.

7. Was the pre-proposal mandatory for this project? No it was not.

8. But I do not see a bid form for this project? The bid sheet is the Schedule B of the Solicitation.

9. Is it possible to get the CAD files? No, the FAA prefers you use the PDF files attached to the announcement.

10. Do you happen to have a copy of the attendees for the pre-bid meeting? Yes, I have attached it to this Amendment.

11. Should we use ISQFT for the specs and drawings? No please review the information on faaco.faa.gov.

12. Can we use paint on concrete instead of the Thermoplastic listed? Yes. Please review attachment titled HQB Parking Lot Amendment 2 Attachment.

13. Will the NAICs code be changed? The NAICS code was changed to 237310.

14. Is the proposal guarantee too high? The proposal guarantee will be 20% of the proposal.

15. Can we get additional days for questions? The questions were extended until September 10th, 2018.

16. What needs to be done to utilities on the ground? It is addressed in the attached addendum to the specifications.

17. What should we do with the extra dirt? It will need to be hauled off by the contractor.

18. Who should the proposal guarantee bond be made out to? The Standard Form 24 used does not state who it should be issued to. It does require a project name. The project name for this one would be 6973GH-18-R-00255 FAA Headquarters Parking Lot at MMAC. Please note the power of attorney letter must be attached to the form 24.