STATEMENT OF WORK
This Statement of Work describes bridge maintenance and pavement preservation work across four National Park Service sites organized into four schedules: Thomas Edison National Historical Park (EDIS) in Essex, NJ; Fort McHenry National Monument and Historic Shrine (FOMC) in Baltimore, MD; Upper Delaware Scenic and Recreational River (UPDE) in Pike and Wayne, PA; and Steamtown National Historic Site (STEA) in Lackawanna, PA. Work encompasses micro surfacing, thin lift asphalt overlay, crack cleaning and sealing, asphalt concrete pavement patching, milling and overlay, concrete repair, drainage repairs, speed bump replacement, concrete paver installation, pavement markings, minor bridge repairs, and miscellaneous maintenance activities. Schedule A includes work on Honeysuckle Avenue, Edison Lab Visitor Parking, Maintenance/Visitor Center Parking, and Laboratory Courtyard Parking at EDIS. Schedule B covers Fort Avenue, Seawall Road, and Visitor Center Parking at FOMC. Schedule C includes Roebling Bridge Road and Headquarters Complex Parking at UPDE. Schedule D addresses three Main Entrance Roads (A, B, and C) and Turntable Bridge work at STEA, with special requirements for removing and replacing speed humps, sidewalk precast concrete paver installation, and epoxy injection of cracks on retaining walls.
The performance period is 152 calendar days after issuance of the Notice to Proceed, with construction activities to start no earlier than March 22, 2027. Detailed pay item tables specify estimated quantities and units for each schedule, including materials such as asphalt concrete pavement (ranging from 570 to 6,900 square yards depending on schedule), crack cleaning and sealing (1,150 to 5,000 linear feet), pavement markings (2,300 to 6,200 linear feet), and various signage installations. Special considerations include protection of historic cobble drainage swales and coordination of archaeological monitoring with contractors at EDIS and FOMC, with the NPS providing and funding archaeological monitors.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
This FP-24 project includes bridge maintenance and pavement preservation of roadways and parking areas for the following sites:
Park County State PMIS #
Thomas Edison National Historical Park (EDIS) Essex NJ 341149 Fort McHenry National Monument and Historic Shrine
(FOMC)
City of Baltimore MD 341529
Upper Delaware Scenic and Recreational River (UPDE) Pike, Wayne PA 341193 Steamtown National Historic Site (STEA) Lackawanna PA 341541
341542
This project is divided into 4 schedules, each Park consisting of one schedule. Work includes micro surfacing, thin lift asphalt overlay, crack cleaning and sealing, asphalt concrete pavement patching, milling and overlay, concrete repair, drainage repairs, speed bump replacement, concrete paver installation, pavement markings, minor bridge repairs, and other miscellaneous work as listed below:
Schedule A – EDIS
0010: Honeysuckle Avenue
Mill and overlay (asphalt pavement milling, 1.5” asphalt concrete pavement) Asphalt concrete pavement patch, type 2 Chip seal (appearance is preferred to match historic area of these grounds) Traffic detector wire loop replacement Removal of structure, utility box replacement
0901: Edison Lab Visitor Parking
Crack cleaning and sealing Remove signage o Four (4) “ELECTRIC VEHICLE PARKING ONLY WHILE CHARGING”.
o Two (2) “RESERVED PARKING”.
o Two (2) “PENALTY TOW-AWAY ZONE”.
Install signage o Four (4) “ELECTRIC VEHICLE PARKING ONLY WHILE CHARGING”.
o Two (2) “RESERVED PARKING”.
o Two (2) “PENALTY TOW-AWAY ZONE”.
o One (1) “VAN ACCESSIBLE”.
Pavement markings Pavement markings, symbols Remove rubber wheelstops and replace them with concrete wheelstops (approximate net loss of 3 wheelstops)
0902: Maintenance/Visitor Center Parking
Mill and overlay (asphalt pavement milling, 1.5” asphalt concrete pavement) Asphalt concrete pavement patch, type 2 Drainage grate replacement (inlet top, metal frame and grate) Signage o Two (2) “DO NOT ENTER”.
Pavement markings Pavement markings, symbols Concrete slab for dumpster installation Reset wheelstops (NPS to provide these wheelstops) Underdrain system installation Removal of frame and grate
0906: Laboratory Courtyard Parking
Asphalt concrete pavement patch, type 2
Miscellaneous/ General Notes
Protect historic cobble drainage swale along roadway during construction.
Coordinate Archaeological Monitoring with Contractor and NPS for any ground disturbance during construction. NPS to provide and fund monitor.
Schedule B – FOMC
0010: Fort Avenue
Pavement markings (do not restripe crosswalk at the overflow parking driveway) Pavement markings, type B, solid Pavement markings, type B, “STOP” word message Install signs
0400: Seawall Road
Micro surfacing, type 2 Asphalt concrete pavement patch, type 3 Underdrain system installation Install sign (modified R3-7R, “Motorized Vehicles Must Turn Right”)
0900: Visitor Center Parking
Mill and overlay (asphalt pavement milling, 1” asphalt concrete pavement) Thin lift asphalt concrete pavement Manhole adjustment Pavement markings, type B, solid Pavement markings, symbols Pavement markings, type B, straight arrow
Pavement markings, type B, accessibility symbol
Schedule C – UPDE
0010: Roebling Bridge Road
Crack cleaning and sealing Asphalt concrete pavement patching, type 2 Cleaning of drainage structures Removal of pavement markings Pavement markings, type C, solid Install signs
0900: Headquarters Complex Parking
Removal and replacement of wheelstops ¾” mill and thin lift overlay (3/4”) Crack cleaning and sealing Asphalt concrete pavement patching, type 2 Removal of pavement markings Pavement markings, type C, solid Pavement markings, type C, accessibility symbol
Schedule D – STEA
0400AZ: Main Entrance Road A
Removal of pavement markings, symbols and word Removal of pavement markings (crosswalks) Removal of pavement, asphalt Mill and overlay (asphalt pavement milling, 1.5”) Crack cleaning and sealing Asphalt concrete pavement, type 2 Asphalt concrete pavement patching, type 2 Removal and replacement of speed humps (reconstruct in kind) Removal of curb Sidewalk precast concrete paver installation Removal of curb, timber rail lines/blocks, 4 foot width Install signs Pavement markings (crosswalks) Pavement markings, type C, solid Pavement markings, type C, turn arrow Pavement markings, type C, “STOP” word message Pavement markings, type H, straight arrow Traffic detector wire loop replacement
0400BZ: Main Entrance Road B
Mill and overlay (asphalt pavement milling, 1.5”) Asphalt concrete pavement, type 2
Removal of curb, concrete, 1-foot width
0400CZ: Main Entrance Road C
Asphalt concrete pavement patching, type 2
4810-033P: Turntable Bridge
Remove debris inside turntable pit Epoxy inject cracks on retaining walls around turntable pit
The performance period to complete the contract work for all schedules will be 152 calendar days after the issuance of the Notice to Proceed with the construction activities to start no earlier than March 22, 2027.
Table 1 lists the routes included in Schedule A of this project.
Table 1 – Schedule A Project Routes
Route ID Route Name
0010 Honeysuckle Avenue
0901 Edison Lab Visitor Parking
0902 Maintenance/Visitor Center Parking 0906 Laboratory Courtyard Parking
Table 2 lists the routes included in Schedule B of this project.
Table 2 – Schedule B Project Routes
0010 Fort Avenue 0400 Seawall Road 0900 Visitor Center Parking
Table 3 lists the routes included in Schedule C of this project.
Table 3 – Schedule C Project Routes
0010 Roebling Bridge Road
0900 Headquarters Complex Parking
Table 4 lists the routes and structures included in Schedule D of this project.
Table 4 – Schedule D Project Routes and Structures
Route / Structure ID Route / Structure Name
0400AZ Main Entrance Road A 0400BZ Main Entrance Road B 0400CZ Main Entrance Road C
4810-033P Turntable Bridge
Table 5 lists the pay items and quantities for Schedule A of the project.
Table 5 – Schedule A Tabulation of Quantities
Table 6 lists the pay items and quantities for Schedule B of the project.
Table 6 – Schedule B Tabulation of Quantities
Table 7 lists the pay items and quantities for Schedule C of the project.
Table 7 – Schedule C Tabulation of Quantities
Table 8 lists the pay items and quantities for Schedule D of the project.
Table 8 – Schedule D Tabulation of Quantities