Results of Bid Opening - VA NP BLRI 1G27.pdf

PDF 107 KB Posted

Attached to
Project VA NP BLRI 1G27 - Blue Ridge Parkway
Solicitation number
693C73-25-B-000005
Issued by

About this file

This is a bid opening results document for Federal Highway Administration (FHWA) Eastern Federal Lands Highway Division Solicitation No. 693C73-25-B-000005, Project VA NP BLRI 1G27 on the Blue Ridge Parkway, with bids opened on February 25, 2025 at 2:00 p.m. in Ashburn, VA.

Seven contractors submitted bids for the project, which is divided into four schedules (A, B, C, and D). Gemstone, LLC submitted the lowest total bid at $7,569,466.50, followed by Structural Engineering Group, Inc. at $7,802,640.96 and RBA Engineering International, PLLC at $8,947,808.00. The Engineer's Estimate was $10,075,000.00. The performance period is 872 calendar days if awarded as a complete package (Schedules A+B+C+D), or if awarded separately: Schedule A is 183 days, Schedule B is 400 days, Schedule C is 76 days, and Schedule D is 211 days. The project involves rehabilitation work on the James River Bridge including crack repairs, vegetation removal, spall patching, graffiti cleaning, stonework repairs, steel beam painting, asphalt work, and bearing replacements.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Federal Highway Administration

Eastern Federal Lands Highway Division

Bid Opening for

Blue Ridge Parkway

PROJECT: VA NP BLRI 1G27

SOLICITATION NO. 693C73-25-B-000005

February 25, 2025, at 2:00 p.m.

Ashburn, VA

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

BID OPENING for SOLICITATION NO. 693C73-25-B-000005

Project: VA NP BLRI 1G27

February 25, 2025, 2:00 p.m. local time

If the Government awards the contract as Schedules A + B + C + D, the performance period to complete all the contract work will be 872 calendar days. If awarded separately, Schedule A will be 183 calendar days, Schedule B will be 400 calendar days, Schedule C will be 76 calendar days, and Schedule D will be 211 calendar days.

BIDDER SCHEDULE TOTAL TOTAL PRICE

Eclipse Companies, LLC SCHEDULE A

$2,707,119.00

SCHEDULE B (GOVERNMENT OPTION 1)

$7,430,426.00

SCHEDULE C (GOVERNMENT OPTION 2)

$596,388.00

SCHEDULE D (GOVERNMENT OPTION 3)

$906,119.00

SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3 =

$11,640,119.00

Gemstone, LLC SCHEDULE A

$1,861,796.00

SCHEDULE B (GOVERNMENT OPTION 1)

$5,074,997.80

SCHEDULE C (GOVERNMENT OPTION 2)

$404,492.70

SCHEDULE D (GOVERNMENT OPTION 3)

$228,180.00

SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3 =

$7,569,466.50

Highway and Safety Services, Inc

SCHEDULE A

$2,128,120.00

SCHEDULE B (GOVERNMENT OPTION 1)

$8,841,998.00

SCHEDULE C (GOVERNMENT OPTION 2)

$839,705.00

SCHEDULE D (GOVERNMENT OPTION 3)

$1,796,200.00

SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3 =

$13,606,023.00

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

BID OPENING for SOLICITATION NO. 693C73-25-B-000005

Project: VA NP BLRI 1G27

February 25, 2025, 2:00 p.m. local time

If the Government awards the contract as Schedules A + B + C + D, the performance period to complete all the contract work will be 872 calendar days. If awarded separately, Schedule A will be 183 calendar days, Schedule B will be 400 calendar days, Schedule C will be 76 calendar days, and Schedule D will be 211 calendar days.

BIDDER SCHEDULE TOTAL TOTAL PRICE

Kovilic Construction Company, Inc.

SCHEDULE A

$3,771,400.00

SCHEDULE B (GOVERNMENT OPTION 1)

$5,750,950.00

SCHEDULE C (GOVERNMENT OPTION 2)

$566,275.00

SCHEDULE D (GOVERNMENT OPTION 3)

$826,800.00

SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3 =

$10,915,425.00

RBA Engineering International.

PLLC

SCHEDULE A

$1,297,580.00

SCHEDULE B (GOVERNMENT OPTION 1)

$5,238,580.00

SCHEDULE C (GOVERNMENT OPTION 2)

$948,346.00

SCHEDULE D (GOVERNMENT OPTION 3)

$1,463,302.00

SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3 =

$8,947,808.00

Structural Engineering Group, Inc.

SCHEDULE A

$2,428,449.50

SCHEDULE B (GOVERNMENT OPTION 1)

$4,397,426.38

SCHEDULE C (GOVERNMENT OPTION 2)

$609,297.73

SCHEDULE D (GOVERNMENT OPTION 3)

$367,467.35

SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3 =

$7,802,640.96

BIDDER SCHEDULE TOTAL TOTAL PRICE

Engineer’s Estimate SCHEDULE A

$2,821,000.00

SCHEDULE B (GOVERNMENT OPTION 1)

$6,080,000.00

SCHEDULE C (GOVERNMENT OPTION 2)

$627,000.00

SCHEDULE D (GOVERNMENT OPTION 3)

$547,000.00

SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3=

$10,075,000.00

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

BID OPENING for SOLICITATION NO. 693C73-25-B-000005

Project: VA NP BLRI 1G27

February 25, 2025, 2:00 p.m. local time

If the Government awards the contract as Schedules A + B + C + D, the performance period to complete all the contract work will be 872 calendar days. If awarded separately, Schedule A will be 183 calendar days, Schedule B will be 400 calendar days, Schedule C will be 76 calendar days, and Schedule D will be 211 calendar days.

Slide 1
Slide 2: FEDERAL HIGHWAY ADMINISTRATION EASTERN FEDERAL LANDS HIGHWAY DIVISION BID OPENING for SOLICITATION NO. 693C73-25-B-000005 Project: VA NP BLRI 1G27 February 25, 2025, 2:00 p.m. local time If the Government awards the contract as Schedules A + B +
Slide 3: FEDERAL HIGHWAY ADMINISTRATION EASTERN FEDERAL LANDS HIGHWAY DIVISION BID OPENING for SOLICITATION NO. 693C73-25-B-000005 Project: VA NP BLRI 1G27 February 25, 2025, 2:00 p.m. local time If the Government awards the contract as Schedules A + B +
Slide 4: FEDERAL HIGHWAY ADMINISTRATION EASTERN FEDERAL LANDS HIGHWAY DIVISION BID OPENING for SOLICITATION NO. 693C73-25-B-000005 Project: VA NP BLRI 1G27 February 25, 2025, 2:00 p.m. local time If the Government awards the contract as Schedules A + B +

File details come from the government source that posted it. Updated .