Results of Bid Opening - Project NP ROCR 15(2).pdf

PDF 108 KB Posted

Attached to
Rock Creek Park - Joyce Road Bridge
Solicitation number
693C73-24-B-000010
Issued by

About this file

This document is the Results of Bid Opening for Solicitation No. 693C73-24-B-000010 for Project NP ROCR 15(2) - the replacement of the Joyce Road bridge over Luzon Branch in Rock Creek Park, Washington, DC. The project is expected to cost between $2,000,000 and $5,000,000 and has a performance period of 327 calendar days. Bids were received and opened on June 4, 2024 from 6 small business contractors, with the low bid of $3,290,167 submitted by RBA Engineering International, PLLC. The government's pre-bid estimate for the work was $2,560,000. The procurement is set aside for certified small businesses, with mandatory SAM registration and annual Reps & Certs requirements. Interested vendors are instructed to register at www.sam.gov to receive notifications and access bid documents.

View the file

Other files

File Type Posted
FP14_Eng.pdf PDF
ADV Bidders Qualifications Form.doc DOC document
Geotechnical Report.pdf PDF
IFB Solicitation - NP ROCR 15(2).pdf PDF
Plans - NP ROCR 15(2).pdf PDF
Bridge Inspection Report_3450-003P.pdf PDF
Categorical Exclusion Form (NEPA).pdf PDF
VETS-4212 Form.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Federal Highway Administration Eastern Federal Lands Highway Division

Bid Opening for

Rock Creek Park

PROJECT: NP ROCR 15(2)

SOLICITATION NO. 693C73-24-B-000010

June 4, 2024 at 2:00 p.m.

Ashburn, VA

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

BID OPENING for SOLICITATION NO. 693C73-24-B-000010 Project: NP ROCR 15(2)

June 4, 2024, 2:00 p.m. local time The performance period to complete all Schedule A work is 327 calendar days and will start on the effective date of Schedule A’s

Notice to Proceed.

BIDDER SCHEDULE TOTAL TOTAL PRICE

Central Southern Construction Corp. SCHEDULE A $3,966,222.00

SCHEDULE A =

$3,966,222.00

Kovilic Construction Co., Inc. SCHEDULE A $4,125,400.00

SCHEDULE A =

$4,125,400.00

RBA Engineering International, PLLC

SCHEDULE A

$3,290,167.00

SCHEDULE A =

$3,290,167.00

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

BID OPENING for SOLICITATION NO. 693C73-24-B-000010 Project: NP ROCR 15(2)

June 4, 2024, 2:00 p.m. local time The performance period to complete all Schedule A work is 327 calendar days and will start on the effective date of Schedule A’s

Notice to Proceed.

BIDDER SCHEDULE TOTAL TOTAL PRICE

Terra Site Constructors, LLC SCHEDULE A $3,356,735.00

SCHEDULE A =

$3,356,735.00

Veteran’s Kitchen Maintenance SCHEDULE A $4,192,164.00

SCHEDULE A =

$4,192,164.00

Engineer’s Estimate SCHEDULE A $2,560,000.00

SCHEDULE A =

$2,560,000.00

Slide Number 1
FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-24-B-000010�Project: NP ROCR 15(2)�June 4, 2024, 2:00 p.m. local time�The performance period to complete all Schedule A work is 327 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.
FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-24-B-000010�Project: NP ROCR 15(2)�June 4, 2024, 2:00 p.m. local time�The performance period to complete all Schedule A work is 327 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.

File details come from the government source that posted it. Updated .