Results of Bid Opening - MD SP NASA 2(1).pdf
PDF 121 KB Posted
- Attached to
- NASA Goddard Space Flight Center
- Solicitation number
- 693C73-24-B-000003
About this file
This document summarizes the results of a bid opening for a federal contract solicitation. The solicitation was issued by the Federal Highway Administration Eastern Federal Lands Highway Division on behalf of the National Aeronautics and Space Administration Goddard Space Flight Center. Two bids were received in response to solicitation number 693C73-24-B-000003 for a project identified as MD SP NASA 2(1). Central Southern Construction Corp. provided a total bid price of $7,215,131 including $3,640,750 for Schedule A work and $3,574,381 for Schedule B work. RBA Engineering International, PLLC bid a total of $4,212,258 with $1,221,040.91 for Schedule A and $2,991,217.41 for Schedule B. The engineer's estimate was $6,460,000 with $1,367,000 for Schedule A and $5,093,000 for Schedule B. The period of performance to complete both Schedule A and B work is 500 calendar days from the effective date of the Schedule A and B notices to proceed.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Highway Administration
Eastern Federal Lands Highway Division
Bid Opening for
National Aeronautics and Space Administration, Goddard Space Flight Center
PROJECT: MD SP NASA 2(1)
SOLICITATION NO. 693C73-24-B-000003
November 16, 2023 at 2:00 p.m. EST
Ashburn, Virginia
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-24-B-000003
Project: MD SP NASA 2(1)
November 16, 2023, 2:00 p.m. EST
BIDDER’S BID TOTALS DAYS TOTAL PRICE
Central Southern Construction
Corp.
SCHEDULE A
$3,640,750.00
SCHEDULE B
$3,574,381.00
SCHEDULE A + SCHEDULE B =
$7,215,131.00
RBA Engineering International, PLLC
SCHEDULE A
$1,221,040.91
SCHEDULE B
$2,991,217.41
SCHEDULE A + SCHEDULE B =
$4,212,258.32
Engineer’s Estimate SCHEDULE A
$1,367,000.00
SCHEDULE B
$5,093,000.00
SCHEDULE A + SCHEDULE B =
$6,460,000.00
The performance period to complete all Schedule A and Schedule B work will be 500 calendar days and will start on the effective date of Schedule A and Schedule B’s Notice to Proceed.