IFB Solicitation - PR ST ER PRMNT RPR (8).pdf
PDF 3 MB Posted
- Attached to
- Landslide Repairs - East Region Contract 1
- Solicitation number
- 693C73-21-B-000012
About this file
This is a solicitation for a construction project to repair landslide damage in Puerto Rico caused by hurricanes. Certified small businesses are invited to bid on the Landslide Repairs - East Region Contract 1 project, with solicitation number 693C73-21-B-000012. The project involves repairing landslides and washouts on three roads, and includes installing a gabion basket wall, marine gabions, a mechanically stabilized earth wall, excavation, pavement, erosion controls, traffic controls, and other work. The project will be split into multiple schedules and contract options, with a total estimated cost between $1 million and $5 million. Bids are due on a date specified in the solicitation. Interested vendors must register at the provided website to receive notifications. Annual representations and certifications must be completed online, as well as the required Vets-4212 form. Questions should be sent to the listed email. Bidders must be registered in the System for Award Management database and allow for payment registration.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract No.
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
CONTRACTOR:
ADDRESS:
EASTERN FEDERAL LANDS HIGHWAY DIVISION
PR ER PRMNT RPR(8)
Puerto Rico Highway and Transportation Authority
Landslide Repairs - East Region Contract 1
SOLICITATION
IFB No. 693C73-21-B-000012
This Contract Cites
PRHT A's Standard Specifications for Road and Bridge Construction
STATE Puerto Rico
COUNTY Municipalities: Naguabo, Cayey, Humacao
AGENCY Puerto Rico Highway and Transportation Authority
TYPE OF IMPROVEMENT
The project consists ofrepairing landslides and washouts caused by Hurricanes Inna and Maria on PR-3 Km 69.3, PR-1 Km 61.8 and PR-909 Km 5.55.
Project Length Totals
1.06 0.00
For Parking Areas, Lane Miles is calculated as SQFT/11 ft (nominal) lane
Parking Roadway / Parking Area / Other Mileposts/ SQFT Linear Route Lane
Schedule Area Feet Miles Miles
A □ ER-HWY-344 (PR-3 km 69.3 to 70.6) To 5,036 0.95 0.00
B □ ER-HWY-2 (PR-1 km 61.8) To 295 0.06 0.00
C □ ER-HWY-463 (PR-909 Km 5.55) To 263 0.05 0.00
TABLE OF CONTENTS
Page
Notice to Bidders 1 through 2
Checklist for Bid Submission 1 through 2
*SF-1442 Solicitation, Offer, and Award 1 through 6
Bid Schedule Instructions 1 through 4
*Bid Schedule B-1 through B-8
*SF-24 Bid Bond C-1 through C-2
FEDERAL ACQUISITION REGULATION & TRANSPORTATION ACQUISITION
REGULATION SOLICITATION PROVISIONS & CONTRACT CLAUSES
Index to Federal and Transportation Acquisition Regulations 1 through 7
Representations and Certifications (SAMs online) D-1 through D-2
Instructions to Bidders E-1
*Socioeconomic Program Requirements F-1 through F-4
Minimum Wage Schedule F-5 through F-10
*General Contract Requirements G-1 through G-9
Construction Contract Requirements H-1 through H-5
Special Contract Requirements J-1 through J-263
Section K K-1 through K-3
Permits pending
SPECIFICATIONS On CD
Plans 1 through 107
PRHTAS Standard Specifications 1 through 1158
DTOPS Manual de Senales de Transito (MST) 1 through 174
PRHTAS Standard Drawings 1 through 59
Master Utility Agreement PRHTA and PRASA 1 through 3
Master Utility Agreement PRHTA and PREPA 1 through 4
Project Funding Sign Details 1 page
TABLE OF CONTENTS
USFWS Conservation Measures 1 through 23
Report_Asbestos_Sch A_Site 344 1 through 18
Report_Asbestos_Sch B_Site 2 1 through 12
Report_Asbestos_Sch C_Site 463 1 through 12
Report_Lead_Sch A_Site 344 1 through 32
Report_Lead_Sch B_Site 2 1 through 21
Report_Lead_Sch C_Site 463 1 through 12
NEPA_Sch A_Site 344_Part 1 1 through 56
NEPA_Sch A_Site 344_Part 2 1 through 74
NEPA_Sch B_Site 2 1 through 112
NEPA_Sch C_Site 463 1 through 95
* Bidder’s Qualifications Form 1 through 7
* Federal Contractor Veterans’ Employment Report VETS-4212 1 through 5
*BOLD FACED ITEMS ARE TO BE INCLUDED WITH THE BID SUBMITTAL PACKAGE
NOTICE TO BIDDERS
CONTRACT FORMAT:
Bidders should note that the format of this contract is in accordance with Federal Acquisition Regulations (FAR), promulgated by the General Services Administration (GSA), effective April 1, 1984, including all applicable revisions. Applicable FAR provisions and clauses are incorporated in this contract by reference or full text as indicated in the INDEX before the D-pages in this booklet.
FAR provisions and clauses incorporated by reference can be accessed on the Internet website at https://www.acquisition.gov/. Bidders are encouraged to review the documents thoroughly before submitting a bid.
PROPOSAL BOOKLET AND OFFER SUBMITTAL:
It is the responsibility of the Bidder to verify that this proposal is complete as listed in the Table of Contents. The Bidder is responsible for submitting all required forms and documents with the bid.
Bidders should use the Checklist for Bid Submission included in this booklet to check that their bids are complete.
HAZARDOUS MATERIALS IDENTIFICATION AND MATERIAL SAFETY DATA:
As required by FAR Clause 52.223-3, Hazardous Materials Identification and Safety Data, the apparent low Bidder must submit prior to award a Material Safety Data Sheet (MSDSs) for all hazardous materials that the Bidder identifies in paragraph (b) of this clause in Section G of this booklet. Failure to submit MSDSs may render the Bidder ineligible for award of contract. The apparent low Bidder should submit their MSDSs within two weeks after bid opening.
INTERNET BASED DATA BASES - REQUIRED INPUT:
According to FAR Subpart 4.1102 contractors are required to be registered in the System for Award Management (SAM) at the time a bid is submitted. Access the following web site to register: https://www.sam.gov/.
According to FAR Subpart 4.1201 contractors are required to complete electronic annual representations and certifications in SAM accessed via https://www.sam.gov/ as a part of required registration.
According to FAR Subpart 22.1302 (b) federal contractors and sub-contractors MUST complete the required annual Vets-4212 Form in order to be eligible for a contract award. It can be completed on-line at http://www.dol.gov/vets/vets4212.htm. The annual filing period for Form VETS-4212 is August 1 through September 30. Reports filed before August 1 will be treated as part of the previous year's filing cycle. Federal contractors and subcontractors who are required to file a form VETS-4212 can submit their forms electronically by using either the VETS-4212 Reporting Application or batch filing process, or by using the paper form by email or U.S. mail. It is recommended that you file your form electronically at https://vets4212.dol.gov/vets4212. Please visit http://www.dol.gov/vets/vets4212.htm for more information on the reporting process.
PAYMENT:
Bidders are advised to review the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP), subsection 109.05, concerning direct and indirect payment included under a pay item in the bid schedule.
PROGRESS PAYMENTS:
ALL payments will be made via Electronic Funds Transfer (EFT) as such; the payment information in SAM must be accurate in order for contractors' invoices to be considered proper invoices for the purpose of prompt payment under DOT contracts. Contractors must input and maintain (update as necessary) their EFT information in the SAM database. Bidders are advised that under FAR Clause 52.232-5, Payments Under Fixed Price Construction Contracts, upon request, progress payments will include premiums paid by the Contractor to obtain performance and payment bonds as required under this contract. These payments shall not be made in addition to the contract price. As specified in the https://www.sam.gov/ https://www.sam.gov/ http://www.dol.gov/vets/vets4212.htm https://vets4212.dol.gov/vets4212 http://www.dol.gov/vets/vets4212.htm
NOTICE TO BIDDERS
FP, “Section 151 - MOBILIZATION", payments for performance and payment bond premiums shall be included in mobilization.
WELFARE-TO-WORK INITIATIVE:
The President’s Welfare Reform Bill was initiated to assist welfare recipients and hopefully aid welfare recipients to find gainful employment. In support of this bill, Contractors are encouraged to hire welfare recipients whenever possible and to use welfare recipients in performance of duties on Government contracts.
INCREASING SEAT BELT USE IN THE UNITED STATES:
The President’s Executive Order 13043 dated April 16, 1997, was issued to increase the use of seat belts in the United States. In support of this Order, contractors and subcontractors are encouraged to adopt and enforce on-the-job seat belt policies for their employees when operating company-owned, rented, or personally owned vehicles.
OBTAINING BID DOCUMENTS:
Invitation For Bid (IFB) documents will not be mailed. All solicitation documents are available for direct download from the Contract Opportunities website: https://beta.sam.gov/. Contractors are encouraged to register on the website (for this specific project) in order to receive automatic notifications when a document is added or updated for this specific project. All questions about this construction project must be emailed to the following address:
eflhd.contracts@dot.gov.
THE CONTRACTOR IS SOLELY RESPONSIBLE FOR MONITORING THE WEB PAGES
NOTED ABOVE FOR ALL CHANGES TO THE SOLICITATION AND ACTING ON
THOSE CHANGES.
PLEASE NOTE: For security reasons, individuals requiring access to all government buildings must present a valid photo ID and be escorted to their destination by a Government employee. All visitors attending bid openings are urged to arrive at least 1 hour prior to a scheduled bid opening. All visitors must sign in at the main entrance of the Quantum Park facility and wait to be escorted by a Government employee to Eastern Federal Lands Highway Division (EFLHD) in Suite 200. Visitors must then register with the EFLHD Receptionist. A Government employee will collect all bids. Prior to the bid opening, a Government employee will escort all bidders to the bid opening. Unescorted visitors will be denied entry and no exceptions will be made.
https://beta.sam.gov/ mailto:eflhd.contracts@dot.gov
CHECKLIST FOR BID SUBMISSION
The following is a checklist of items included in the proposal/bid package that are required to be completed and returned (or filled in on-line) to the address in Block 7 of the Standard Form 1442, Solicitation, Offer, and Award (page 1). This checklist is for informational purposes only and is not required to be filled out by the bidder. Failure to submit a complete bid may be cause to reject your bid.
1. Bid Envelope:
a. Addressed as shown in Block 7 of SF-1442
b. In the lower left corner, indicate the following: Solicitation No., Project Name & Number, and mail to Suite E2-3-300, ATTENTION: ACQUISITIONS. If bids are hand-delivered, bring them to the main entrance of Quantum Park, and ask for the Federal Highway Administration (EFLHD) Receptionist to be contacted and an EFLHD representative will come to collect the bid.
2. Standard Form 1442: Solicitation, Offer and Award
a. Block 14: Name and Address of Bidder.
b. Block 15: Telephone Number of Bidder.
c. Block 16: Remittance Address if different from Block 14.
d. Block 19: All Amendments Acknowledged, with dates of Amendments.
e. Block 20: Bid is signed and dated.
3. Bid Schedule - (Pages B-1 through B-8)
a. Unit bid price and bid amount provided for each pay item in numbers.
b. Corrections initialed.
4. Standard Form 24, Bid Bond (Pages C-1 through C-2) (Required if bid guarantee is bid bond)
a. Date executed
b. Legal name and address of bidder.
c. Type of organization.
d. State of incorporation (if applicable).
e. Name and business address of Treasury approved surety.
f. Penal sum of bond (not less than 20% of bid total).
g. Bid identification.
h. Signature of Bidder
i. Seal, if corporation
j. Signature of Surety
k. Seal, if corporation
BIDS RECEIVED WITHOUT A VALID BID BOND WILL BE REJECTED.
5. Power of Attorney.
a. Dated on or before execution date of bond
b. Power has original signature of surety, or is embossed with surety's seal in the certification section
BIDS RECEIVED WITHOUT A VALID POWER OF ATTORNEY WILL BE REJECTED.
CHECKLIST FOR BID SUBMISSION
6. Bidder's Qualifications form (provided separately as part of the Bid Documents Package).
Form completed, signed and submitted with bid
7. System for Award Management (SAM): The contractor is currently registered in the System For Award Management (SAM) database at https://www.sam.gov/ at the time the bid is submitted. If the contractor elects to not have its active SAM registration viewable by the public, then the contractor must submit a copy with the bid.
8. Online Representations and Certifications Application: The contractor's Representations and Certifications have been input online via the electronic database at https://www.sam.gov/.
9. VETS – 4212 Reporting: The contractor has completed the annual reporting requirement online at http://www.dol.gov/vets/vets4212.htm.
The annual filing period for Form VETS-4212 is August 1 through September 30. Reports filed before August 1 will be treated as part of the previous year's filing cycle. Federal contractors and subcontractors who are required to file a form VETS-4212 can submit their forms electronically by using either the VETS- 4212 Reporting Application or batch filing process, or by using the paper form by email or U.S. mail. It is recommended that you file your form electronically at https://vets4212.dol.gov/vets4212. Please visit http://www.dol.gov/vets/vets4212.htm for more information on the reporting process.
NOTE: THE CONTRACTOR IS FULLY RESPONSIBLE TO VERIFY THAT ALL
DATA IN THE ABOVE DATABASES IS CORRECT EACH TIME A BID PACKAGE IS
SUBMITTED. FAILURE TO PROPERLY INPUT AND/OR UPDATE YOUR DATA
PRIOR TO BID SUBMISSION MAY CAUSE THE BID TO BE REJECTED.
https://www.sam.gov/ https://www.sam.gov/SAM/ http://www.dol.gov/vets/vets4212.htm https://vets4212.dol.gov/vets4212
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY
SUITE E2-3-300
693C73
ATTN: ACQUISITIONS
ASHBURN VA 20147
See Block 7
YULIYA KENT
b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
EFLHD.Contracts@dot.gov
See Block 10 x
04/16/2021
693C7321B000012
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
This Invitation for Bids is for the Puerto Rico Landslide Repairs East Region
Contract I, Project No. PR ST ER PRMNT RPR (8), located in municipalities of Cayey, Humacao and Naguabo, Puerto Rico in strict accordance with the Solicitation/Contract instructions, notices, clauses, provisions, items listed below, and for the quantities of work actually performed at the unit prices as bid in the Bid Schedule, including all applicable Federal, State, and local taxes.
PRHTAS Standard Specifications, pages 1 through 1158.
DTOPS Manual de Senales de Transito (MST), pages 1 through 174.
PRHTAS Standard Drawings, pages 1 through 59.
Bid Schedule, Section B - pages B-1 through B-8.
Special Contract Requirements, Section J - pages J-1 through J-263.
Plans, Sheets 1 through 107.
Master Utility Agreement PRHTA and PRASA, pages 1 through 3.
Master Utility Agreement PRHTA and PREPA, pages 1 through 4.
Project Funding Sign Details, 1 page.
USFWS Conservation Measures, pages 1 through 23.
Report_Asbestos_Sch A_Site 344, pages 1 through 18.
Report_Asbestos_Sch B_Site 2, pages 1 through 12.
Continued ...
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 460 calendar days and complete it within ________________ ________________ calendar days after receiving
Continuation Sheet , Block 11
05/18/2021
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
�����./�0::/303�#73//5�20�9/3:03;�2./�=03D�3/AB83/>�#2�2./�9384/5�59/48:8/>�$/60=�81�523842�#4403>#14/�=82.�2./�2/3;5�0:�2.85�5068482#2801?�8:�2.85�0::/3�85�#44/92/>
$@�2./��0E/31;/12�81�=382817�=82.81�--------------------�4#6/1>#3�>#@5�#:2/3�2./�>#2/�0::/35�#3/�>B/����������
| � | %(�� |
| �) | �� |
| �� | ����� |
| � | �� |
| ����� ���������� | ���� | ����� |
| � | �� |
�����./�0::/303�#73//5�20�:B3185.�#1@�3/AB83/>�9/3:03;#14/�#1>�9#@;/12�$01>5�
0��#������ ��2�
| ����� | ������ | � |
| H���� | �� |
������� �)4��
3�2���%����
| �����" | ��� � ����� | ��� |
| ����������� | �� |
| ��" ���� | ���������� | |
| �������� | ����� | "��� |
����������3 4��� '5 '6 �--����7��
3�2���%���
| �� | ������ | �� | ������ | ������ | � |
| H���� | �� |
������� )4������ �$���� �� �4������
���� 2 of 6������������������������
����2�� #��0 ��2�����
�)��������� )�&4'��������������� ������������ &4'���������������
�"������&��*���G��'����, Block 26
Federal Highway Administration Eastern Federal Lands Highway Division ATTN: Construction Branch Quantum Park 22001 Loudoun County Parkway Suite E2-2-200 Ashburn, VA 20147
Federal Highway Administration Eastern Federal Lands Highway Division A/P Branch, AMZ-150 P.O. Box 25710 or E-MAIL
9-AMC-AMZ-EFLINVOICES@FAA.GOV
Oklahoma City, OK 73125
EFLHD-CO
peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 6
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
693C7321B000012
Report_Asbestos_Sch C_Site 463, pages 1 through
12.
Report_Lead_Sch A_Site 344, pages 1 through 32.
Report_Lead_Sch B_Site 2, pages 1 through 21.
Report_Lead_Sch C_Site 463, pages 1 through 12.
NEPA_Sch A_Site 344_Part 1, pages 1 through 56.
NEPA_Sch A_Site 344_Part 2, pages 1 through 74.
NEPA_Sch B_Site 2, pages 1 through 112.
NEPA_Sch C_Site 463, pages 1 through 95.
Permits pending.
00001 Schedule A - The project consists of repairing landslide and washout damaged by Hurricanes Irma and Maria on PR-3 Km 69.3-70.6, PR-1 km 61.8 and
PR-909 km 5.55 and other miscellaneous work. The work includes a gabion basket wall, marine gabions, a mechanically stabilized earth wall, excavation, pavement, erosion and sediment control, traffic control, and among others.
00002 Schedule B - Government Option 1
00003 Schedule C - Government Option 2
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
CONTINUATION OF SF 1442
Block 2:
This project is RESTRICTED - Bids will be accepted from all eligible Small Business concerns.
This procurement falls under North American Industry Classification System (NAICS) code 237310 - Highway, Street, and Bridge Construction (see FAR Subpart 19.10)
Facsimile and electronic bids will not be accepted.
PHYSICAL DATA AVAILABLE FOR REVIEW
1. Manual on Uniform Traffic Control Devices for Streets and Highways, 2009 Edition, published by the Federal Highway Administration. http://mutcd.fhwa.dot.gov.
2. PRHTAS Standard Specifications
3. DTOPS Manual de Senales de Transito (MST)
4. PRHTAS Standard Drawings
5. Master Utility Agreement PRHTA and PRASA
6. Master Utility Agreement PRHTA and PREPA
7. Project Funding Sign Details
8. USFWS Conservation Measures
9. Report_Asbestos_Sch A_Site 344
10. Report_Asbestos_Sch B_Site 2
11. Report_Asbestos_Sch C_Site 463
12. Report_Lead_Sch A_Site 344
13. Report_Lead_Sch B_Site 2
14. Report_Lead_Sch C_Site 463
15. NEPA_Sch A_Site 344_Part 1
16. NEPA_Sch A_Site 344_Part 2
17. NEPA_Sch B_Site 2
18. NEPA_Sch C_Site 463
19. Permits pending
Block 9:
In accordance with FAR Provision 52.236-27, Site Visit, a Government representative can be available to show the project to prospective bidders. All requests for site visits see Section E of the solicitation and e-mail all questions concerning this construction project to the following e-mail address eflhd.contracts@dot.gov. Interested parties must provide the Solicitation Number and the relevant project name with all requests and questions.
∗Block 11:
Maximum Time Allowed if Schedules A + B + C are Awarded at the Same Time:
If the Government awards the contract as Schedules A + B + C, the performance period to complete all contract work will be 460 calendar days.
Maximum Time Allowed for Each Schedule of Work if Awarded Separately:
If the Government awards the contract as Schedules A + B, the performance period to complete all contract work will be 450 calendar days.
If the Government awards the contract as Schedules A + C, the performance period to complete all contract work will be 420 calendar days.
If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 310 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.
If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 195 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.
If Schedule C (Government Option 2) is exercised after the award of the original contract, the performance period to complete all Schedule C work will be 170 calendar days and will start on the effective date of Schedule C’s Notice to Proceed.
See Completion of Work section of the B-Pages – Bid Schedule Instructions for further information. The completion time for the contract is not to exceed the maximum time above.
Work restrictions can be found in SCR Sections 108 and 156.
Notice to Proceed will be issued within 30 days following receipt of acceptable performance and payment bonds. (Actual Notice to Proceed date will be 10 days from issuance or the date specified in the Notice.)
Block 12A:
Furnish performance and payment bonds in accordance with FAR Clause 52.228-15.
Block 13:
A bid guarantee in the amount of not less than 20 percent of the bid price or $3 million, whichever is less, is required with this bid. If the bidder fails to provide the required bid guarantee, such failure may require rejection of the bid. Reference FAR Provision 52.228-1, Bid Guarantee.
Block 17:
Amounts should be completed as follows:
Schedule A - $ Schedule B (Government Option 1) - $ Schedule C (Government Option 2) - $
Other:
The estimated price is expected to fall within the price range of $1,000,000 to $5,000,000.
Responsibility of bidders shall be evaluated in accordance with the information provided on the Bidder's Qualification Form, which can be downloaded from the Contract Opportunities website located at http://beta.SAM.gov. Puerto Rico Highway and Transportation Authority’s Standard Specifications for Road and Bridge Construction Manual can be downloaded at the ACT (Autoridad de Carreteras y Transportación) web site. ACT web site is https://act.dtop.pr.gov/manual-de-especificaciones-estandares-para-la-construccion-de-carreteras-y-puentes/ http://beta.sam.gov/ https://act.dtop.pr.gov/manual-de-especificaciones-estandares-para-la-construccion-de-carreteras-y-puentes/ https://act.dtop.pr.gov/manual-de-especificaciones-estandares-para-la-construccion-de-carreteras-y-puentes/
BID SCHEDULE INSTRUCTIONS
PROJECT: PR ST ER PRMNT RPR(8)
BIDDERS PLEASE NOTE: Before preparing the bid, carefully read the Instructions to
Bidders. While preparing the bid, comply with the following:
COMPLETING THE BID SCHEDULE
Complete the Bid Schedule(s) by handwriting in ink or typing. Specify a Unit Bid Price, in figures with cents to only two decimal places, for each pay item in the Unit Bid Price column for which a quantity is given. Do not enter or tender a Unit Bid Price for any pay item for which no estimated quantity appears in the Bid Schedule. Determine the products of the respective unit prices and quantities, and show them, in figures, in the Amount Bid column. If a Unit Bid Price and Amount Bid have been inserted by the Government for a pay item, do not change the Unit Bid Price and Amount Bid for the pay item. Determine the Bid Total for each specific individual Schedule of Work by adding the amounts of the listed items, and show in the block provided for that individual Schedule of Work. In case of multiplication errors, the Amount Bid for the item will be based on the Unit Bid Price.
To be eligible for award, bidders must submit prices for each pay item.
Review Subsection 109.05 of the Special Contract Requirements (SCR) regarding scope of payment for direct and indirect payment work.
Fill in the Bid Total(s) for each individual Schedule of Work as directed on the Bid Summary page. Fill in the Evaluation Total Price of Project in the space provided on the Bid Summary page.
The amount in Block 17 of the SF 1442 should be completed as follows:
Schedule A - $ .
Schedule B - $ .
Schedule C - $ .
SCHEDULES OF WORK
The Bid Schedule is comprised of the following separate schedules and options of work:
Schedule A (Base Contract) - Pages B-1 thru B-2 Schedule B (Government Option 1) - Pages B-3 thru B-4 Schedule C (Government Option 2) - Pages B-5 thru B-7
The Government will award the project as a Base Contract (Schedule A) with the option to award Schedules B and C (Government Option 1 and 2); see FAR Clauses 52.217-4 and 52.217-5.
The purpose of the multiple schedules and options is to give the Government maximum flexibility in completing the project in a timely manner and at a cost-effective price, by proper utilization of programmed funds and upon receipt of any additional funds required to award the contract. If complete funding is in place at the time of award of Schedule A (Base Contract), the Government may award Schedules B or C (Government Options 1 or 2) at that time. If additional funding is required for the award of Schedules B or C (Government Options 1 or 2), and is received after the award of Schedule A (Base Contract), the Government has the right to exercise Schedules B or C (Government Options 1 or 2) at the unit prices bid according to the following schedule:
Schedule B (Government Option 1): No later than 365 calendar days after the Notice To Proceed for Schedule A (Base Contract).
Schedule C (Government Option 2): No later than 365 calendar days after the Notice To Proceed for Schedule A (Base Contract).
COMPLETION OF WORK
The Government has estimated the number of calendar days necessary to complete all contract work from the effective date of the Notice to Proceed to contract completion for the various contract award scenarios. The maximum number of calendar days allowed (i.e., the contact performance period) is shown in Block 11 of the SF-1442 and described below.
If the Government awards the contract as Schedules A + B + C, the performance period to complete all contract work will be 460 calendar days.
If the Government awards the contract as Schedules A + B, the performance period to complete all contract work will be 450 calendar days.
If the Government awards the contract as Schedules A + C, the performance period to complete all contract work will be 420 calendar days.
If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 310 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.
If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 195 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.
If Schedule C (Government Option 2) is exercised after the award of the original contract, the performance period to complete all Schedule C work will be 170 calendar days and will start on the effective date of Schedule C’s Notice to Proceed.
In developing a construction schedule to determine the number of calendar days, the
Government considered and included the work limitations shown in Sections 108 and 156 of the SCR’s and the plans. Specific work limitations may be (but are not limited to): National legal and local holidays, weekends, rush hours, night work, specified no work periods, work or traffic control phasing, etc. The Government also considered those work items that are weather sensitive and when those work items will be performed. Specific work items may include (but not limited to): those that require a minimum ambient air temperature (asphalt paving and surface treatment, pavement striping, stone masonry, etc); those that require maintaining a minimum surface temperature (concrete pavement, structural concrete, painting, etc); and those that have specific planting seasons (turf establishment, sod, trees, plants, etc). The Government also considered time required for preparing material and drawing submittals, and the allowable Government review times for those submittals (Subsection 104.03 of the SCR’s).
Bidders are to assume that the award of the contract and approval of the Contractor’s Performance and Payment Bonds (see Block 12a of the SF-1442 and FAR Clause 52.228-
15) may result in the start of construction activities to be June 2021. See Subsection 108.01 of the SCR’s for additional details.
BASIS FOR AWARD
The contract will be awarded to the responsive, responsible bidder with the lowest Evaluation Total Price of Project, which is defined as:
Schedule A (Base Contract) Bid Total + Schedule B (Government Option 1) Bid Total + Schedule C (Government Option 2) Bid Total.
Bidder/Offeror please note: Before preparing the bid, carefully read the Solicitation Provisions. Insert a unit bid price, in figures, for each pay item for which a quantity appears in the bid schedule. Multiply the unit price by the quantity for each pay item and show the amount bid. Should any mathematical check made by the Government show a mistake in the amount bid, the corrected unit price extension shall govern. When the word "LPSM" (Lump Sum) appears as a unit bid price, insert an amount for each lump sum pay item. When a sum based on a fixed rate appears for any pay item in the amount bid column, include the Government inserted amount bid for the item in the total bid amount. Total all of the amounts bid for each pay item and show the total bid amount.
Bid Schedule
Project No: PR ST ER PRMNT RPR(8) Project Name: Landslide Repairs - East Region Contract 1
B I D S C H E D U L E Schedule A
Project No: PR ST ER PRMNT RPR(8)
Name: ER-HWY-344
Item No. Quantity Unit Unit Price Amount
15101-0000 Line A0020 ALL LPSM $
15102-0000 Line A0040 1 CTSM $
15201-0000 Line A0060 ALL LPSM $
15401-0000 Line A0080 ALL LPSM $
15401-1000 Line A0100 ALL LPSM $
15501-0000 Line A0120 ALL LPSM $
20100-0000 Line A0140 2.65 Cuerda $ $
20100-2000 Line A0160 8 Each $ $
20100-3000 Line A0180 12 Each $ $
20100-4000 Line A0200 3 Each $ $
20300-0000 Line A0220 1,000 m3 $ $
21000-0000 Line A0240 3,000 M $ $
21000-2000 Line A0260 15 Each $ $
21000-3000 Line A0280 5 Each $ $
21012-0000 Line A0300 4 Each $ $
30500-1000 Line A0320 20 m3 $ $
40301-0000 Line A0340 420 m3 $ $
42100-1000 Line A0360 1,100 TON $ $
60600-1000 Line A0380 1,200 M $ $
Mobilization
Reimbursement for Municipality Tax Payments
Construction survey and staking
Contractor testing
Contractor testing (Biological Monitoring)
Construction schedule
W-Beam Guardrail
Fiber Rolls (sediment log)
Stabilized Construction Exit
Erosion Control for Inlet (Bag)
Clearing and Grubbing
Cutting and Removing Trees, Small (7" to 12" Diameter)
Cutting and Removing Trees, Small (13" to 24" Diameter)
Cutting and Removing Trees, Large (25" to 46" Diameter)
Unclassified Excavation (Cut to Waste)
Silt Fence
Lean Concrete Base (0.15m)
Cold Milling Bituminous Concrete Pavement (0.05m)
Hot Plant-Mix Bituminous Pavement S (75) (38)
Schedule Total: ________________________
Submitted by: _________________________
Schedule A
Project No: PR ST ER PRMNT RPR(8)
Name: ER-HWY-344
Item No. Quantity Unit Unit Price Amount
60600-7000 Line A0400 2 Each $ $
61101-0000 Line A0420 ALL LPSM $
61400-1000 Line A0440 700 m3 $ $
61800-1000 Line A0460 3,100 M $ $
61800-2000 Line A0480 390 M $ $
61800-3000 Line A0500 800 M $ $
61800-4000 Line A0520 600 M $ $
62500-0000 Line A0540 65 m3 $ $
62600-0000 Line A0560 10,000 Each $ $
63800-1000 Line A0580 ALL LPSM $
64000-0000 Line A0600 260 Each $ $
66100-1000 Line A0620 2 Each $ $
66400-0000 Line A0640 1,600 M $ $
93501-0000 Line A0660 5 Each $ $
Project Funding Sign
Centerline Rumble Strip
Locate Utility, Test Pit
Crashworthy End Terminal Type 1
Field Office
Thermoplastic Pavement Marking Stripes, white (0.20 mts. Width)
Thermoplastic Pavement Marking Stripes, white (0.46 mts. Width)
Furnishing and Placing Loamy Topsoil
Planting Vetiveria zizanioides (Vetiveria Grass)
Maintenance of Traffic (MOT)
Reflective Raised Pavement Markers (Two way)
Gabions (Marine Gabion Mattress)
Thermoplastic Pavement Marking Stripes, yellow (0.15 mts. Width)
Thermoplastic Pavement Marking Stripes, white (0.15 mts. Width)
Schedule B
Project No: PR ST ER PRMNT RPR(8)
Name: ER-HWY-2
Item No. Quantity Unit Unit Price Amount
15101-0000 Line B0020 ALL LPSM $
15102-0000 Line B0040 1 CTSM $ $
15201-0000 Line B0060 ALL LPSM $
15401-0000 Line B0080 ALL LPSM $
15401-1000 Line B0100 ALL LPSM $
15501-0000 Line B0120 ALL LPSM $
20100-0000 Line B0140 0.26 Cuerda $ $
20200-1000 Line B0160 20 M $ $
20200-5000 Line B0180 ALL LPSM $
20200-6000 Line B0200 7 M $ $
20200-7000 Line B0220 7 M $ $
20300-0000 Line B0240 950 m3 $ $
21000-0000 Line B0260 110 M $ $
21000-1000 Line B0280 60 Each $ $
21000-2000 Line B0300 5 Each $ $
21000-3000 Line B0320 1 Each $ $
30400-1000 Line B0340 28 m3 $ $
30400-2000 Line B0360 120 m3 $ $
40301-0000 Line B0380 34 m3 $ $
Mobilization
Reimbursement for Municipality Tax Payments
Construction survey and staking
Contractor testing
Contractor testing (Biological Monitoring)
Construction schedule
Cold Milling Bituminous Concrete Pavement (0.05m)
Silt Fence
Straw Bale (Dikes)
Fiber Rolls (sediment log)
Clearing and Grubbing
Removal of Concrete Barrier
Removal of Structures and Obstructions (Concrete Retaining Wall)
Removal of Structures and Obstructions (Water line)
Removal of Structures and Obstructions (Telephone line)
Unclassified Excavation (Cut to Waste)
Stabilized Construction Exit
Aggregate Base Course Class, A, (0.15m)
Aggregate Base Course Class, A-1-a (AASHTO Soil Classification System), (0.63m)
Schedule B
Project No: PR ST ER PRMNT RPR(8)
Name: ER-HWY-2
Item No. Quantity Unit Unit Price Amount
42100-1000 Line B0400 110 TON $ $
42100-3000 Line B0420 38 TON $ $
60600-1000 Line B0440 130 M $ $
60600-7000 Line B0460 2 Each $ $
60900-0000 Line B0480 75 M $ $
60900-1000 Line B0500 32 M $ $
61312-4000 Line B0520 31 SQFT $ $
61312-5000 Line B0540 13 SQFT $ $
61312-6000 Line B0560 9 SQFT $ $
61312-7000 Line B0580 4 SQFT $ $
61800-1000 Line B0600 190 M $ $
61800-2000 Line B0620 190 M $ $
62600-0000 Line B0640 900 Each $ $
63800-1000 Line B0660 ALL LPSM $
66100-1000 Line B0680 2 Each $ $
91300-4000 Line B0700 3 Each $ $
92500-0000 Line B0720 200 m2 $ $
93501-0000 Line B0740 5 Each $ $
94000-1000 Line B0760 1,200 m3 $ $
Thermoplastic Pavement Marking Stripes, white (0.15 mts. Width)
Planting Vetiveria zizanioides (Vetiveria Grass)
Maintenance of Traffic (MOT)
Hot Plant-Mix Bituminous Pavement S (75) (38)
Hot Plant-Mix Bituminous Pavement B (75) (1)
Concrete Curb, Type-D
Traffic Sign Assembly, W1-8R (24"x30")
Traffic Sign Assembly, W1-2R, 2L (30"x30")
Traffic Sign Assembly, W13-1P (24"x24")
Traffic Sign Assembly, D10-2A (10"x36")
Thermoplastic Pavement Marking Stripes, yellow (0.15 mts. Width)
W-Beam Guardrail
Crashworthy End Terminal Type 1
Combination Concrete Curb and Gutter, Type-F
Locate Utility, Test Pit
Select Granular Backfill
Project Funding Sign
Removal of Existing Traffic Signs
Mechanically Stabilized Earth Retaining Wall
Schedule C
Project No: PR ST ER PRMNT RPR(8)
Name: ER-HWY-463
Item No. Quantity Unit Unit Price Amount
15101-0000 Line C0020 ALL LPSM $
15102-0000 Line C0040 1 CTSM $
15201-0000 Line C0060 ALL LPSM $
15401-0000 Line C0080 ALL LPSM $
15401-1000 Line C0100 ALL LPSM $
15501-0000 Line C0120 ALL LPSM $
20100-0000 Line C0140 0.11 Cuerda $ $
20200-8000 Line C0160 60 M $ $
20200-9000 Line C0180 35 M $ $
20300-0000 Line C0200 420 m3 $ $
20500-0000 Line C0220 26 m3 $ $
21000-0000 Line C0240 11 M $ $
21000-2000 Line C0260 13 Each $ $
21000-3000 Line C0280 1 Each $ $
21000-4000 Line C0300 75 M $ $
30400-1000 Line C0320 35 m3 $ $
30400-2000 Line C0340 30 m3 $ $
30500-1000 Line C0360 7 m3 $ $
40301-0000 Line C0380 18 m3 $ $
Mobilization
Reimbursement for Municipality Tax Payments
Construction survey and staking
Contractor testing
Contractor testing (Biological Monitoring)
Construction schedule
Cold Milling Bituminous Concrete Pavement (0.05m)
Fiber Rolls (sediment log)
Stabilized Construction Exit
Silt Fence (Wire Backing)
Clearing and Grubbing
Removal of Guard Rail
Removal of Structures and Obstructions (Gutter)
Unclassified Excavation (Cut to Waste)
Trench Excavation, Unclassified (4" PVC Pipe, SDR 14)
Silt Fence
Aggregate Base Course Class, A, (0.15m)
Aggregate Base Course Class, A-1-a (AASHTO Soil Classification System), (0.63m)
Lean Concrete Base (0.15m)
Project No: PR ST ER PRMNT RPR(8)
Name: ER-HWY-463
Item No. Quantity Unit Unit Price Amount
42100-1000 Line C0400 12 TON $ $
42100-2000 Line C0420 6 TON $ $
42100-3000 Line C0440 12 TON $ $
60600-1000 Line C0460 80 M $ $
60600-7000 Line C0480 1 Each $ $
60900-0000 Line C0500 55 M $ $
60900-3000 Line C0520 40 M $ $
61400-0000 Line C0540 2 m3 $ $
61400-2000 Line C0560 17 m3 $ $
61700-0000 Line C0580 27 M $ $
61800-1000 Line C0600 160 M $ $
61800-2000 Line C0620 160 M $ $
62200-0000 Line C0640 3 m3 $ $
62600-0000 Line C0660 900 Each $ $
63600-0000 Line C0680 24 M $ $
63600-1000 Line C0700 1 Each $ $
63600-2000 Line C0720 2 Each $ $
63600-3000 Line C0740 1 Each $ $
63600-5000 Line C0760 1 CTSM $
Thermoplastic Pavement Marking Stripes, white (0.15 mts. Width)
Dumped Riprap, Class 3
Planting Vetiveria zizanioides (Vetiveria Grass)
Hot Plant-Mix Bituminous Pavement Mix S (75) (38)
Hot Plant-Mix Bituminous Pavement Mix B (75) (1)
Combination Concrete Curb and Gutter, Type-F
Concrete Gutter (Shallow)
Gabions (Riprap/ Revetment)
Filter Blanket (Riprap/ Revetment)
Concrete Chute
Thermoplastic Pavement Marking Stripes, yellow (0.15 mts. Width)
Hot Plant-Mix Bituminous Pavement Mix B (75) (12)
W-Beam Guardrail
Crashworthy End Terminal Type 1
4" Gate Valve
Utility Company Compensation (PRASA)
4" PVC Pipe, SDR 14
4" SD Cast Iron Elbow (22.5° Bend)
4" SD Cast Iron Elbow (45° Bend)
Project No: PR ST ER PRMNT RPR(8)
Name: ER-HWY-463
Item No. Quantity Unit Unit Price Amount
63800-1000 Line C0780 ALL LPSM $
65000-0000 Line C0800 65 m2 $ $
66100-1000 Line C0820 2 Each $ $
92500-0000 Line C0840 120 m2 $ $
93501-0000 Line C0860 5 Each $ $
94000-1000 Line C0880 380 m3 $ $
Maintenance of Traffic (MOT)
Concrete Slope Paving (Embankment Protection)
Project Funding Sign
Mechanically Stabilized Earth Retaining Wall
Locate Utility, Test Pit
Select Granular Backfill
B - 8
BID SUMMARY
Project PR ST ER PRMNT RPR(8)
(1) $____________________
(2) $____________________
Schedule A (Base Contract) Bid Total (from Page B-1) =
Schedule B (Government Option 1) Bid Total (from Page B- ) =
Schedule C (Government Option 2) Bid Total (from Page B- ) = (3) $____________________
Total Price of Project (for evaluation purposes only)
EVALUATION TOTAL PRICE OF PROJECT = (1) + (2) + (3) $____________________
Maximum Time Allowed for the Contract if all schedules are Awarded at the Same Time
If the Government awards the contract as Schedules A + B + C, the performance period to complete all contract work will be 460 calendar days.
If Schedules A, B, and C are not awarded at the same time, Maximum Time Allowed for completion of each award configuration is as follows:
If the Government awards the contract as Schedules A + B, the performance period to complete all contract work will be 450 calendar days.
If the Government awards the contract as Schedules A + C, the performance period to complete all contract work will be 420 calendar days.
If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 310 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.
If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 195 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.
If Schedule C (Government Option 2) is exercised after the award of the original contract, the performance period to complete all Schedule C work will be 170 calendar days and will start on the effective date of Schedule C’s Notice to Proceed.
BID BOND
(See instructions on reverse)
OMB Control Number: 9000-0045 Expiration Date: 8/31/2022
PRINCIPAL (Legal name and business address) TYPE OF ORGANIZATION ("X" one)
STATE OF INCORPORATION
SURETY(IES) (Name and business address)
PERCENT
OF BID
PRICE
PENAL SUM OF BOND
AMOUNT NOT TO EXCEED
MILLION(S) THOUSAND(S) HUNDRED(S) CENTS
BID IDENTIFICATION
BID DATE INVITATION NUMBER
PRINCIPAL
SIGNATURE(S)
NAME(S) &
TITLE(S)
(Typed)
1.
1. 2.
2.
3.
3.
(Seal) (Seal) (Seal) Corporate Seal
INDIVIDUAL SURETY(IES)
SIGNATURE(S)
NAME(S)
(Typed)
1.
1.
2.
2.
(Seal) (Seal)
CORPORATE SURETY(IES)
NAME &
ADDRESS
STATE OF INCORPORATION LIABILITY LIMIT ($)
SIGNATURE(S)
NAME(S) &
TITLE(S)
(Typed)
1.
1.
2.
2. Corporate Seal
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is NOT usable
STANDARD FORM 24 (REV. 8/2016)
Prescribed by GSA - FAR (48 CFR) 53.228(a)
FOR (Construction, Supplies or Services)
OBLIGATION:
We, the Principal and Surety(ies) are firmly bound to the United States of America (hereinafter called the Government) in the above penal sum. For payment of the penal sum, we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally. However, where the Sureties are corporations acting as co-sureties, we, the Sureties, bind ourselves in such sum "jointly and severally" as well as "severally" only for the purpose of allowing a joint action or actions against any or all of us. For all other purposes, each Surety binds itself, jointly and severally with the Principal, for the payment of the sum shown opposite the name of the Surety. If no limit of liability is indicated, the limit of liability is the full amount of the penal sum.
CONDITIONS:
The Principal has submitted the bid identified above.
THEREFORE:
The above obligation is void if the Principal - (a) upon acceptance by the Government of the bid identified above, within the period specified therein for acceptance (sixty (60) days if no period is specified), executes the further contractual documents and gives the bond(s) required by the terms of the bid as accepted within the time specified (ten (10) days if no period is specified) after receipt of the forms by the principal; or (b) in the event of failure to execute such further contractual documents and give such bonds, pays the Government for any cost of procuring the work which exceeds the amount of the bid.
Each Surety executing this instrument agrees that its obligation is not impaired by any extension(s) of the time for acceptance of the bid that the Principal may grant to the Government.
Notice to the surety(ies) of extension(s) is waived. However, waiver of the notice applies only to extensions aggregating not more than sixty (60) calendar days in addition to the period originally allowed for acceptance of the bid.
WITNESS:
The Principal and Surety(ies) executed this bid bond and affixed their seals on the above date.
DATE BOND EXECUTED (Must not be later than bid opening date)
Paperwork Reduction Act Statement - This information collection meets the requirements of 44 USC § 3507, as amended by section 2 of the Paperwork Reduction Act of 1995. You do not need to answer these questions unless we display a valid Office of Management and Budget (OMB) control number. The OMB control number for this collection is 9000-0045. We estimate that it will take 1 hour to read the instructions, gather the facts, and answer the questions. Send only comments relating to our time estimate, including suggestions for reducing this burden, or any other aspects of this collection of information to: General Services Administration, Regulatory Secretariat Division (M1V1CB), 1800 F Street, NW, Washington, DC 20405.
JOINT VENTURE
OTHER (Specify)
PARTNERSHIPINDIVIDUAL
CORPORATION
INSTRUCTIONS
1. This form is authorized for use when a bid guaranty is required. Any deviation from this form will require the written approval of the Administrator of General Services.
2. Insert the full legal name and business address of the Principal in the space designated "Principal" on the face of the form. An authorized person shall sign the bond. Any person signing in a representative capacity (e.g., an attorney-in-fact) must furnish evidence of authority if that representative is not a member of the firm, partnership, or joint venture, or an officer of the corporation involved.
3. The bond may express penal sum as a percentage of the bid price. In these cases, the bond may state a maximum dollar limitation (e.g., 20% of the bid price but the amount not to exceed dollars).
4. (a) Corporations executing the bond as sureties must appear on the Department of the Treasury's list of approved sureties and must act within the limitations listed therein. The value put into the LIABILITY LIMIT block is the penal sum (i.e., the face value) of the bond, unless a co-surety arrangement is proposed.
(b) When multiple corporate sureties are involved, their names and addresses shall appear in the spaces (Surety A, Surety B, etc.) headed "CORPORATE SURETY(IES)." In the space designated "SURETY(IES)" on the face of the form, insert only the letter identifier corresponding to each of the sureties. Moreover, when co-surety arrangements exist, the parties may allocate their respective limitations of liability under the bond, provided that the sum total of their liability equals 100% of the bond penal sum.
(c) When individual sureties are involved, a completed Affidavit of Individual Surety (Standard Form 28) for each individual surety, shall accompany the bond.
The Government may require the surety to furnish additional substantiating information concerning its financial capability.
5. Corporations executing the bond shall affix their corporate seals. Individuals shall execute the bond opposite the word "Corporate Seal"; and shall affix an adhesive seal if executed in Maine, New Hampshire, or any other jurisdiction requiring adhesive seals.
6. Type the name and title of each person signing this bond in the space provided.
7. In its application to negotiated contracts, the terms "bid" and "bidder" shall include "proposal" and "offeror."
NAME &
ADDRESS
STATE OF INCORPORATION LIABILITY LIMIT ($)
SIGNATURE(S)
NAME(S) &
TITLE(S)
(Typed)
1.
1.
2.
2. Corporate Seal
Corporate Seal
LIABILITY LIMIT ($)STATE OF INCORPORATION
2.
2.
1.
1.NAME(S) &
TITLE(S)
(Typed)
SIGNATURE(S)
NAME &
ADDRESS
Corporate Seal
LIABILITY LIMIT ($)
2.
2.
STATE OF INCORPORATION
1.
1.
NAME(S) &
TITLE(S)
(Typed)
SIGNATURE(S)
NAME &
ADDRESS
Corporate Seal
LIABILITY LIMIT ($)
2.
2.
STATE OF INCORPORATION
1.
1.
NAME(S) &
TITLE(S)
(Typed)
SIGNATURE(S)
NAME &
ADDRESS
Corporate Seal
LIABILITY LIMIT ($)
2.
2.
STATE OF INCORPORATION
1.
1.
NAME(S) &
TITLE(S)
(Typed)
SIGNATURE(S)
NAME &
ADDRESS
Corporate Seal
LIABILITY LIMIT ($)
2.
2.
STATE OF INCORPORATION
1.
1.
NAME(S) &
TITLE(S)
(Typed)
SIGNATURE(S)
NAME &
ADDRESS
STANDARD FORM 24 (REV. 8/2016) BACK
CONTRACT CLAUSES INDEX
FEDERAL ACQUISITION REGULATION (FAR) TRANSPORTATION ACQUISITION REGULATION (TAR)
(Updated thru FAC 2021-05 on 3/10/2021)
FAR & TAR CLAUSES INCORPORATED BY REFERENCE
CLAUSE TITLE DATE REMARKS
52.202-1 DEFINITIONS Jun-20 52.203-3 GRATUITIES Apr-84 52.203-5 COVENANT AGAINST CONTINGENT FEES May-14 52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT Jun-20 52.203-7 ANTI-KICKBACK PROCEDURES Jun-20 52.203-8 CANCEL & RECOVER OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY May-14 52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY May-14
52.203-11
CERTIFICATION AND DISCLOSURE REGARDING PAYMENTS TO INFLUENCE CERTAIN FEDERAL
TRANSACTIONS Sep-07
52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS Jun-20 52.203-13 CONTRACTOR CODE OF BUSINESS ETHICS AND CONDUCT Jun-20 52.203-14 DISPLAY OF HOTLINE POSTER(S) Jun-20 52.204-2 SECURITY REQUIREMENTS (ALT II - (Apr 84)) Mar-21 52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT PAPER May-11 52.204-7 SYSTEM FOR AWARD MANAGEMENT Oct-18 Contractor Mandatory Internet Data Input 52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS Jun-20 Contractor Mandatory Internet Data Input 52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE Oct-18 Contractor Mandatory Internet Data Input 52.204-14 SERVICE CONTRACT REPORTING REQUIREMENTS Oct-16 Contractor Mandatory Internet Data Input 52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING Aug-20 52.204-17 OWNERSHIP OR CONTROL OF OFFEROR Aug-20 52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE Aug-20 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS Dec-14 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS Jun-16
52.209-6
PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS
DEBARRED, SUSPENDED OR PROPOSED FOR DEBARMENT Jun-20
52.209-11
REPRESENTATION BY CORPORATIONS REGARDING DELINQUENT TAX LIABILITY OR A FELONY
CONVICTION UNDER ANY FEDERAL…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .